HomeMy WebLinkAbout09-213JUNE 9, 2009 09 -213 RESOLUTION
(CARRIED 7 -0 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 3 / PUBLIC WORKS
CONTRACT NO. 08 -05 / MIRON CONSTRUCTION CO. INC. /
WATER FILTRATION PLANT MODIFICATIONS AND DEMO-
LITION PROJECT/ ( +$161,283.00)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
MIRON CONSTRUCTION CO. INC.
PO Box 509
Neenah, WI 54957 -0509
Net Increase to contract: $161,283.00
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 541 - 1841 - 1799 -00000 - Water Utility Construction Work in Progress
I< H
(0
ON iNE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Stephan M. Brand, Utilities Superintendent
DATE: June 3, 2009
RE: Change Order #3 for Public Works Contract No, 08 -05; Water Filtration Plant
Modifications and Demolition Project
BACKGROUND
Change Order #3 for Contract 08 -05 is scheduled for consideration by the Common Council at the June
9th meeting. This contract was awarded to Miron Construction Co. Inc. of Neenah, WI. on May 27, 2008.
These changes are due to additional requirements of the Department of Natural Resources that are not
code related but part of departments internal decision making process, site conditions that have been
found in the field to be different than, or not shown on existing site plans and opportunities identified
during construction that can add value to the project. Whenever possible these prices reflect estimated
time and material costs and will be adjusted to reflect the actual cost of the work once it is completed. A
final adjustment will be done at the end of the contract on these items. The project is approximately 71 %
complete at this time.
ANALYSIS
3a Additional Hatch Changes -These changes are to satisfy WDNR requirements.
3b 42" to 30" Pipe Connection- This piping connection is being made to provide additional
operational flexibility between the backwash storage, filter to waste lines and clearwells.
3c 24" RW Valves LLPS - The 24" raw water intake valves from the back up intake lines at Low Lift
Pumping Station were found to be in worse condition than originally anticipated and are being
replaced.
3d Small Diameter Piping- WDNR as part of additional review comments wanted to have an
additional casing pipe installed around the chemical feed lines. This is to meet the additional
requirements of the WDNR.
3e Gate Access System Change- Changes in the gate access system location were made at the
request of plant staff. This revision does not cause any change to the contract price.
3f LP Gas Credit Cold Weather Concrete- This deduct is a credit based on the actual LP Gas
needed to meet cold weather requirements for concrete installation which was done on time and
materials basis.
3g Temporary Wiring at Center Clearwell- Temporary wiring was needed for the level controller at
the center clearwell.
Change Order #3 for Public Works Contract No, 08 -05;
Water Filtration Plant Modifications and Demolition Project
Page 2
3h Pump Testing Credit- The factory pump testing for the highlift pumps was completed but did not
meet the testing requirements of the specifications. The supplier is providing a deduct in addition
to more rigorous field testing during startup to meet the requirements of the specifications.
3i High Lift Pump Station Foundation- Unsuitable soils were discovered during excavation around
the highlift pumping station and needed to be removed and suitable fill brought in.
3j Re Route Ozone Cooling Water -This involves a temporary piping change to reroute cooling water
from the Low Lift Pumping Station to facilitate the 24 inch valve installation in the Low Lift
Pumping Station.
3k Combination Starter Disconnect- These changes are related to the exhaust fan starters and
disconnects at the highlift pumping station.
31 CT /BWS & Clearwell Elements- This is for the additional wiring required to provide heat elements
on the level control instruments in the clearwells.
3m Electrical Hand Holds and Ductbank Changes- An opportunity to reduce the number of hand
holds and shorten the ductbank resulted in this deduct.
3n PVC Coated Conduit- This is an upgrade in material and extends the long term durability of this
installation.
3o Deletion of Mow Strip- This was originally concrete and is being changed to landscaping stone
resulting in a deduct.
3p Installation of 24" valve- The existing valve that was the connecting point for the new 24 inch
piping did not work properly. This is the installation cost for a new valve that was provided by the
utility.
3q Change from 4" Conduit to 3" Conduit- This was a contractor request which resulted in a deduct.
3r Delete Wireway at GAC- An alternate method of installation made this wireway unnecessary
which resulted in a deduct.
3s Clearw ell Hatches — DNR is requiring upgrades to the hatches on the existing clearwells. A
number of locations identified as hatches are actually related to valve operator connections and
do not need to be modified. This resulted in deduct.
These changes were reviewed by CH2M Hill our consultant on the project and the costs related to these
changes were reasonable based on their experience with similar work.
Change Order #3 for Public Works Contract No. 08 -05;
Water Filtration Plant Modifications and Demolition Project
Page 3
FISCAL IMPACT
The estimate for this project was $9,005,950.00.The total project cost including this change order for
$161,283.00 is $8,114,940.52 which is $891,009.48 under budget. Funds are available in the 2008
Property Improvements Section (Water Utility Funds) of the Capital Improvement Budget.
RECOMMENDATIONS
I recommend approval of Change Order # 3 to Contact No. 08 -05 in the amount of $161,283.00 to Miron
Construction Co. Inc.
Respectfully Submitted, Approved:
Stephan M. Brand
Utilities Superintendent City Manager
i
i AECOM
AECOM
558 N. Main Street, Oshkosh, Wisconsin 54901
T 920.235.0270 F 920.235.0321 www.aecom.com
June 3, 2009
Change Order No. 3
Project:
Water Filtration Plant Modifications and Demolition Project
Owner:
City of Oshkosh
Contract:
08 -65
Contractor:
Miron Construction
Description of Change
Change Order No.: Request for Quotation No. (Project Modification No.)
3a: RFQ 03A (PM 029 -1) — Additional Hatch Changes add $1,683.00
3b: RFQ 08A (PM 011 -4) — 42" to 30" Pipe Connection add $71,792.00
3c:
RFQ 16 (PM 018 -1) — 24" RW Valves L.L.P.S.
add
$37,968.00
3d:
RFQ 17A (PM 019 -2) — Small Diameter Piping
add
$57,237.00
3e:
RFQ 22 (PM 027 -1) — Gate Access System Change
add
$0.00
3f:
PM 028 — LP Gas Credit Cold Weather Concrete
deduct ($3,025.00)
3g:
PM 030 — Temporary Wiring at Center Clearwell
add
$651.00
3h:
Submittal 088 -2 Pump Testing Credit
deduct ($6,720.00)
3i:
RFQ 23 (PM 03 1) — High Lift Pump Station Foundation
add
$5,319.00
3j:
RFQ 24A (PM 032) — Re -route Ozone Cooling Water
add
$2,892.00
3k:
RFQ 25 (PM 033) —Comb. Starter & Disconnect
add
$414.00
31:
RFQ 26 (PM 034 -1) — CT /BWS & Clearwell Level Elements
add
$2,383.00
3m: RFQ 27 (PM 035 -2) — Elect. HH & Duckbank Changes deduct ($13,713.00)
3n: RFQ 28 (PM 036 -2) — PVC Coated Conduit add $8,993.00
3o: RFQ 29 (PM 037) — Deletion of Mow Strip deduct ($574.00)
3p: RFQ 30 (PM 038) — Installation of a 24" Valve add $1;759.00
3q: RFQ 31 (PM 039 -2) — Change from 4" Conduit to 3" deduct ($378.00)
3r: RFQ 32 (PM 040 -2) — Delete Wireway at GAC deduct ($1,970.00)
3s: RFQ 33 (PM 042) — Clearwell Hatches deduct ($3,428.00)
TOTAL VALUE OF THIS CHANGE ORDER ADD $161,283.00
Contract Price Adjustment
Original Contract Price $6,070,273.00
Previous Change Orders $454,308.52
Adjustments in Contract Price this Change Order $161,283.00
Current Contract Price including this Change Order $6,685,864.52
Contract Duration Adjustment
Original Contract Duration (Substantial Completion)
365 days
Previous Change Orders
91 days
Adjustment to Contract Duration this Change Order
0 days
Current Contract Duration including this Change Order
456 days
Revised Contract Substantial Completion Date
Sept. 26, 2009 '
This document shall become a supplement to the Contract and all provisions will apply hereto.
AECOM
RECOMMENDED
Engineer — CH2M Hill of RPR — AECOM INC Date
" ' -8I+% X117
Contractor — Miron Construction Date
RECOMMENDED BY OWNER
Director of Public Works
Date
APPROVED BY OWNER
City Manager
Date
City Clerk
Date
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh,
Wisconsin under this Change Order.
City Comptroller
Date
APPROVED AS TO FORM
City Attorney Date
AECOM