HomeMy WebLinkAboutPW CNT 94-074/13/2009 CITY OF OSHKOSH, WISCONSIN Page 1 of 1
12:18:28PM C12000 Report -Legislative History (Detailed) UserlD: PENNY
Doc. Ref. CodDoc. Date Item Ref. Action Code Brief Description Ret.Code
Cont. Date Exp. Date Name Referred to File Reference # Security Class
Abstract Keywords
PWCNT 08 / 24 / 1994 7489 PUBLIC WORKS CONTRACT 94-07
7489 PUBLIC RECORD
PW CONTRACT 94-07 WITH VINTON PUBLIC WORKS
CONSTRUCTION CORPORATION FOR CONTRACTS
CONCRETE PAVING & UNDERGROUND WORK; PW CONTRACT 94-07
CHANGE ORDER NO 3 DATED APRIL 12, 1996 CONTRACT 94-07
ADD $1,145.62 94-07
VINTON
VINTON CONSTRUCTION
CONCRETE PAVING
PAVING
CHANGE ORDER NO 2
Total Items Printed: 1
4/13/2009 CITY OF OSHKOSH, WISCONSIN Page 1 of 1
12:19:21PM C12000 Report -Legislative History (Detailed) UserlD: PENNY
Doc. Ref. CodDoc. Date Item Ref. Action Code Brief Description Ret.Code
Cont. Date Exp. Date Name Referred to File Reference # Security Class
Abstract Keywords
CHO 09 / 06 / 1994 7489 CHANGE ORDER 1/PW CONTRACT 94-07
7489 PUBLIC RECORD
CHANGE ORDER 1/PW CONTRACT 94-07 WITH PUBLIC WORKS
VINTON CONSTRUCTION COMPANY FOR CHANGE ORDERS
CONCRETE PAVING WORK ON THE ALLEY CONTRACTS
SOUTH OF OSHKOSH AVENUE & WEST OF PW CONTRACT 94-07
SAWYER STREET IN THE AMOUNT OF $9,459.65 CONTRACT 94-07
94-07
VINTON
VINTON CONSTRUCTION
CONCRETE PAVING
PAVING
Total Items Printed: 1
4/13/2009 CITY OF OSHKOSH, WISCONSIN Page 1 of 1
12:20:20PM C12000 Report -Legislative History (Detailed) UserlD: PENNY
Doc. Ref. CodDoc. Date Item Ref. Action Code Brief Description Ret.Code
Cont. Date Exp. Date Name Referred to File Reference # Security Class
Abstract Keywords
CHO 09 / 21 / 1994 7489 CHANGE ORDER 2/PW CONTRACT 94-07
7489 PUBLIC RECORD
CHANGE ORDER 2/PW CONTRACT 94-07 WITH PUBLIC WORKS
VINTON CONSTRUCTION COMPANY FOR CHANGE ORDERS
ASPHALT PUBLIC PARKING LOT AT THE CONTRACTS
SOUTHWEST CORNER OF STATE STREET & PW CONTRACT 94-07
WASHINGTON AVENUE IN THE AMOUNT OF CONTRACT 94-07
$17,642.00 94-07
VINTON
VINTON CONSTRUCTION
ASPHALT PAVING
ASPHALT
Total Items Printed: 1
4/13/2009 CITY OF OSHKOSH, WISCONSIN Page 1 of 1
12:21:33PM C12000 Report -Legislative History (Detailed) UserlD: PENNY
Doc. Ref. CodDoc. Date Item Ref. Action Code Brief Description Ret.Code
Cont. Date Exp. Date Name Referred to File Reference # Security Class
Abstract Keywords
CHO 04 / 14 / 1995 7489 CHANGE ORDER 3/PW CONTRACT 94-07
7489 PUBLIC RECORD
CHANGE ORDER 3/PW CONTRACT 94-07 WITH PUBLIC WORKS
VINTON CONSTRUCTION COMPANY FOR CHANGE ORDERS
CONCRETE PAVING, STORM SEWER, SANITARY CONTRACTS
SEWER & WATER MAIN WORK IN THE AMOUNT PW CONTRACT 94-07
OF -$30,984.06 CONTRACT 94-07
94-07
VINTON
VINTON CONSTRUCTION
CONCRETE PAVING
PAVING
Total Items Printed: 1