HomeMy WebLinkAbout09-24JANUARY 27, 2009 09 -24 RESOLUTION
(CARRIED 7 -0 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 / PUBLIC WORKS
CONTRACT 08 -14 / RLAM, INC. / ASPHALT PAVING AND
STORM SEWER / ( +$10,301.17)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
RLAM, Inc.
1110 Dartford Rd.
Ripon, WI 54971
Net Increase to contract: $10,301.17
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 315 - 0410 - 7480 -00000 Street Improvement Fund Expenditures
Acct. No. 317 - 0410 - 7480 -03301 Special Assessment Fund - Streets
Acct. No. 561 - 2010 - 1799 -00000 Storm Water Utility - Construction Work in
Progress
0
OfHKOfH
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works
DATE: January 22, 2009
RE: Change Order #1 for Public Works Contract No. 08 -14;
Asphalt Paving
BACKGROUND
Change Order #1 for Contract 08 -14 is scheduled for consideration by the Common Council at the
January 27, 2009 meeting. The contract was originally awarded to RLAM Inc. of Ripon in September
2008. This change order is for various items to change quantities to those actually installed.
ANALYSIS
Following is a summary of the significant work changes for each section of the CIP.
- Street Construction included additional excavation and stone for removal and backfill of poor soil
below the alleys and additional asphalt pavement to blend to existing access points. Deductions
included reduced removal and replacement of trees due to shifting of the alleys.
-Storm Sewer included increases for additional pipe and deductions for erosion control items.
FISCAL IMPACT
Funds are available in the 2008 Capital Improvement Budget. The increased amount for each section is
as follows: Street Construction $10,226.17 and Storm Sewer $75.00.
RECOMMENDATIONS
recommend approval of the Change Order # 1 to Contact No. 08 -14 in the amount of $10,301.17 to
RLAM Inc.
Respectfully Submitted,
Approved:
No
Steven M. Gohde
Asst. Director of Public Works City Manager
I: \Engineering \08 -14 Asphalt Paving\Project_ Information \Correspondence\Nlemo \CO #I exp.doc
CHANGE ORDER # 1
DATED: January 13, 2009
TO: RLAM, Inc.
1110 Dartford Rd
Ripon, WI 54971
Your present contract with the City of Oshkosh, Contract, No.
08 -14 , is hereby amended
and changed as follows:
NET INCREASE TO: SECTION 1- ASHPALT PAVING
$10,226.17
NET INCREASE TO: SECTION II - STORM SEWER
$75.00
NET INCREASE TO CONTRACT:
$10,30.1.17
CITY OF OSHKOSH
BY:
- Recommended:
City Manager
Director of Public Works
City Clerk
Approved and accepted:
e m ' gyp ��� �..+ � Z✓
�' Contractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order:
Comptroller
Approved as to form:
City Attorney
SECTION I - ASHPALT PAVING
CONTRACT: 08 -14 CHANGE ORDER # 1
ITEM
Sidewalk and driveway
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
100
Sidewalk and driveway
removal, complete as
Square
s ecified
Feet
2,100
726.00
- 1,374.00
$0.50
($687.00)
101
Excavation, complete as
Cubic
s ecified
Yards
2,530
2,636.00
106.00
$14.00
.$1,484.00
102
Asphaltic concrete
pavement, lower layer,
complete asspecified
Tons
750
723.00
-27.00
$75.75
$2,045.25
103
Asphaltic concrete
pavement, upper layer,
complete as specified
Tons
560
663.00
103.00
$78.00
$8,034.00
104
Tack or prime coat,
complete asspecified
Gallon
130
150.00
20.00
$3.50
$70.00
105
6" concrete sidewalk &
driveway, complete as
Square
specified
Feet
800
866.20
66.20
$5.80
$383.96
106
Furnish and install crushed
stone base course,
complete as specified
Tons
3,030
3,432.00
402.00
$8.65
$3,477.30
Sawing, complete as
Linear
$2.25
107
specified
Feet
640
675.00
35.00
$78.75
108
Adjust manholes and inlets,
complete as specified
Each
10
14.0
4.00
$350.00
$1,400.00
109
Remove trees and stumps,
complete as specified
inch
Diameter
160
87.00
-73.00
1 $22.00
($1,606.00)
110
Furnish and install trees,
com lete asspecified
Each
7
4.00
-3.00
$280.00
($840.00)
111
Preparation of foundation
for asphalt paving on alley
north of Catherine. Avenue
(Punhoqua Street to
Rainbow Drive, complete
Lump
asspecified
Sum
1
1.00
$2,800:00
112
Preparation of foundation
for asphalt paving on alley
south of Catherine Avenue
(N. Eagle Street to Fox
Street), complete as
Lump
specified
Sum
1
1.00
$3,500.00
113
Preparation of foundation
for asphalt north. of
Oshkosh Avenue (N. Eagle
Street to Rainbow Drive),
complete as specified
Lump
Sum
1
1.00
$5,450.00
114
Terrace work on alley north
of Catherine Avenue
(Punhoqua Street to
Rainbow Drive), complete
Lump
asspecified
Sum
1
1.00
$1,650.00
Page 1
CONTRACT: 08 -14 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
115
Terrace work on alley
Linear
south of Catherine Avenue
Feet
1,000
1,002.00
2.00
$40.00
$80,00
201
(N. Eagle Street to Fox
Street), complete as
Lump
specified
Sum
1
1.00
$3,000.00
116
Terrace work on alley north
of Oshkosh Avenue (N.
Each
7
7.00
$900.00
202
Eagle Street to Rainbow
Drive), complete as
Lump
specified
Sum
1
1.00
$3,000.00_
117
Provide and install metal
Vertical
detectable warning plates,
Feet
9.20
9.55
.0.35
$400.00
$140.00
203
complete as specified
Square
complete as specified
Feet
8
8.00
$50.00
SECTION I - (BID ITEMS 100 -117) - SUB - TOTALS $14,928.01 ($5,178.25)
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION i IN
ITEM
Furnish and install 12"
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT T
PRICE
CONTRACT
PRICE
ADDITIONAL WORK: C.O. # 1 - (ITEMS 206) - SUB -TOTAL $476.41 $0.00
NET INCREASE TO: SECTION I - $10,226.17
SECTION II - STORM SEWER
ITEM
Furnish and install 12"
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
200
Furnish and install 12"
RCP Class III storm sewer,
complete as specified
Linear
Feet
1,000
1,002.00
2.00
$40.00
$80,00
201
Furnish and install std. type
1 inlet (30" inside diameter
with 18" sump) without
casting, complete as
s ecified
Each
7
7.00
$900.00
202
Furnish and install std.
storm manhole (4' inside
diameter) in 3 locations,
without casting, complete
Vertical
asspecified
Feet
9.20
9.55
.0.35
$400.00
$140.00
203
Abandon 10" storm sewer,
complete as specified
Linear
t
Feet
555. _.
555.00
-
Page 2
CONTRACT: 08 -14 CHANGE ORDER # 1
s
SECTION II - (BID ITEMS 200 - 205) - SUB- TOTALS $220.00 , ($860.00)
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION II
CONTRACT INSTALLED NET NET COST PER
ADDITIONAL WORK: C.O. # 1 - (ITEMS 206) - SUB -TOTAL $715.00 $0.00
NET INCREASE TO: SECTION II - $75.00
NET INCREASE TO SECTIONS 1,11 $16,339.42
NET DECREASE TO SECTIONS 1, II ($6,038.25)
NET INCREASE TO CONTRACT: $10,301.17 ,
Page 3
storm manhole Sum 1.00 1.00. .$715.00 $715.00
ITEM DESCRIPTION UNIT CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE PRICE PRICE
206 Extend 4" PVC storm drain
and connect to existing Lump
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
UNIT
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
COST PER
UNIT
CONTRACT
PRICE
CONTRACT
PRICE
NUMBER
UNIT
204
Abandon inlets or
manholes, complete as
specified
Each
4
3.00
-1.00
$360.00
($360.00
205
Furnish, install, and
maintain Type "D" inlet
protection, complete as
Each
10
5.00
-5.00
$100.00
($500.00)
storm manhole Sum 1.00 1.00. .$715.00 $715.00
ITEM DESCRIPTION UNIT CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE PRICE PRICE
206 Extend 4" PVC storm drain
and connect to existing Lump
INCREASE IN D
DECREASE IN
UNIT
206 Extend 4" PVC storm drain
and connect to existing Lump