HomeMy WebLinkAbout08-474DECEMBER 9, 2008 08 -474 RESOLUTION (CARRIED LOST LAID OVER WITHDRAWN ) PURPOSE: APPROVAL OF CHANGE ORDER NO. 2 / PUBLIC WORKS CONTRACT NO. 08 -04 / VINTON CONSTRUCTION CO. / STORM SEWER, SANITARY SEWER & WATER MAIN / ($44,790.80) INITIATED BY: DEPARTMENT OF PUBLIC WORKS BE IT RESOLVED by the Common Council of the City of Oshkosh that the following Change Order, a copy of which is attached, is hereby approved: Vinton Construction Co. PO Box 1987 Manitowoc, WI 54221 -1987 Net Increase to contract: $44,790.80 PURPOSE: See attached Change Order. BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated from: Acct. No. 541 - 1841 - 1799 -00000 Water Utility Construction Work in Progress Acct. No. 551 - 1910 - 1799 -00000 Sewer Utility Construction Work in Progress Acct. No. 561 - 2010- 1799 -00000 Stormwater Utility Construction Work in Progress CHANGE ORDER # 2 . DATED: November 18, 2008 TO: VINTON CONSTRUCTION CO P.O. BOX 1987 MANITOWOC, WI 54221 -1987 Your present contract with the City of Oshkosh, Contract No. 08 -04 , is hereby amended and changed as follows: NET INCREASE TO: SECTION II - STORM SEWER NET INCREASE TO: SECTION III - SANITARY SEWER NET INCREASE TO: SECTION IV -WATER MAIN NET INCREASE TO CONTRACT: Recommended: Director of Public Works M $10,584.48 $22,239.30 $11,967.02 $44,790.80 CITY OF OSHKOSH City Manager City Clerk Approved and accepted: OWN �. , WW — G iT Y'actor I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. Approved as to form: Comptroller City Attorney CONTRACT: 08 -04 CHANGE ORDER # 2 SECTION II - STORM SEWER ADDITIONAL WORK REQUIRED: C.O. # 2 - SECTION II DESCRIPTION CONTRACT INSTALLED NET NET COUN INCREASE ITEM CONTRACT CONTRACT NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE' PRICE ADDITIONAL WORK: C.O. # 2 - (ITEMS 223 - 225) - SUB -TOTAL $10,584.48 $0.00 NET INCREASE TO: SECTION II - SECTION III - SANITARY SEWER ADDITIONAL WORK REQUIRED: C.O. # 2 - SECTION III $10,584.48 Additional labor, equipment INCREASE IN DECREASE IN 223 and materials to abandon and materials to excavate INSTALLED NET NET COST PER CONTRACT CONTRACT NUMBER DESCRIPTION and install a storm lateral QUANTITIES INCREASE DECREASE UNIT PRICE PRICE sanitary manholes on at 740 Frederick St., per Hickory St., per Invoice Invoice #8363, lump sum 1.00 1.00 $635.00 $635.00 224 Additional labor, equipment 1.00 1.00 $15,231.20 $15,231.20 and materials to remove and replace existing storm manhole in front of 716 Central St., per Invoice #8364, lump sum 1.00 1.00 $1,865.00 $1,865.00 225 Additional labor and equipment to install storm sewer in Hughes /Oregon intersection due to utility conflicts and contaminated soil, per Invoice #8464, lump sum 1.00 1.00 $8,084.48 $8,084.48 ADDITIONAL WORK: C.O. # 2 - (ITEMS 223 - 225) - SUB -TOTAL $10,584.48 $0.00 NET INCREASE TO: SECTION II - SECTION III - SANITARY SEWER ADDITIONAL WORK REQUIRED: C.O. # 2 - SECTION III $10,584.48 319 Additional labor, equipment INCREASE IN DECREASE IN ITEM and materials to abandon CONTRACT INSTALLED NET NET COST PER CONTRACT CONTRACT NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 319 Additional labor, equipment and materials to abandon 15" sanitary sewer and sanitary manholes on Hickory St., per Invoice #8466, lump sum 1.00 1.00 $15,231.20 $15,231.20 Page 1 CONTRACT: 08 -04 CHANGE ORDER # 2 ITEM NUMBER DESCRIPTION CONTRACT QUANTITIES INSTALLED QUANTITIES NET INCREASE NET DECREASE COST PER UNIT INCREASE IN CONTRACT PRICE DECREASE IN - CONTRACT PRICE 320 Additional labor, equipment and materials to remove and materials to excavate and replace valve @ and install a clay dam to intersection of Division St. existing sanitary lateral at and Lincoln Ave., per City's 1900 Hickory St., per . request, per Invoice # invoice #8432, lump sum 8362, lump sum 1.00 1.00 1.00 $2,758.10 $2,758.10 $3,158.00 321 Additional labor, equipment Additional labor, equipment and materials for rock and materials to repair removal on Hickory St., per water service @ 1627 Invoice # 8433, lump sum Hickory St. which was 1.00 1.00 1 $4,250.00 1 $4,250.00 ADDITIONAL WORK: C. 0. # 2 - (ITEMS 319 - 321) - SUB -TOTAL $22,239.30 $0.00 NET INCREASE TO: SECTION III - $22,239.30 SECTION IV - WATER MAIN ADDITIONAL WORK REQUIRED: C.O. # 2 - SECTION IV Page 2 DESCRIPTION CONTRACT QUANTITIES INSTALLED QUANTITIES NET INCREASE NET DECREASE COST PER UNIT INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE ITEM NUMBER Page 2 Additional labor, equipment 434 and materials to remove and replace valve @ intersection of Division St. and Lincoln Ave., per City's request, per Invoice # 8362, lump sum 1.00 1.00 $3,158.00 $3,158.00 435 Additional labor, equipment and materials to repair water service @ 1627 Hickory St. which was mismarked by .City, per Invoice # 8365, lump sum 1.00 1.00 $1,140.20 $1,140.20 436 Additional labor, equipment and materials to install hydrant and 6 -inch lead on Lincoln Ave., per City request, Invoice # 8366, 1.00 1.00 $1,488.00 $1,488.00 lump sum Page 2 CONTRACT: 08 -04 CHANGE ORDER # 2 ITEM NUMBER DESCRIPTION CONTRACT QUANTITIES INSTALLED QUANTITIES NET INCREASE NET DECREASE COST PER UNIT INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 437 Additional labor, equipment and materials to install bentonite plugs in water service trenches on Lincoln Ave., per Invoice # 8465, lump sum 1.00 1.00 $600.00 $600.00 438 Additional labor, equipment and materials to install 6 -inch X 8 -inch tapping valve and sleeve, 8 -inch water main for Oshkosh Corporation @ Oregon /Hughes intersection, due to utility conflicts and contaminated soil, per Invoice # 8464, lump sum 1.00 1.00 $5,580.82 $5,580.82 ADDITIONAL WORK: C.O. # 2 (ITEMS 434 - 438) - SUB -TOTAL $11,967.02 $0.00 NET INCREASE TO: SECTION IV - NET INCREASE TO SECTIONS 11, III, IV NET DECREASE TO SECTIONS 11, 111, IV NET INCREASE TO CONTRACT: $11,967.02 $44,790.80 $0.00 $44,790.80 Page 3 0 OfHK OfH ON THE WATER MEMORANDUM TO: FROM DATE: RE: Honorable Mayor and Members of the Common Council Steven M. Gohde, Assistant Director of Public Works December 4, 2008 Change Order #2 for Public Works Contract No. 08 -04; Concrete Paving / Utilities BACKGROUND Change Order #2 for Contract 08 -04 is scheduled for consideration by the Common Council at the December 9, 2008 meeting. The contract was originally awarded to Vinton Construction Co. of Manitowoc in May 2008. This change order is for various additional storm sewer, sanitary sewer and water main items. The increases are a result of additional work need to complete the project due to existing conditions underground. ANALYSIS Following is a summary of the significant additional work items performed for each section of the CIP. -Storm Sewer included replacement of a deteriorated manhole, removal of contaminated soil and resolution of conflicts with other utilities. - Sanitary Sewer included rock excavation, installation of bentonite plugs, and abandonment of old sewer pipes. -Water Main included replacement of a failed valve, additional fire hydrant installation, repairs to water laterals and a new 8" water lateral. FISCAL IMPACT Funds are available in the 2008 Capital Improvement Budget. The increased amount for each section is as follows: Storm Sewer $10,584.48, Sanitary Sewer $22,239.30 and Water Main $11,967.02. $5,580.82 of the Water Main work is assessable to an abutting property. RECOMMENDATIONS I recommend approval of the Change Order # 2 to Contact No. 08 -04 in the amount of $44,790.80 to Vinton Construction Co. Respectfully Submitted, J&V;;, N J4 Steven M. Gohde Asst. Director of Public Works Approved: City Manager I:\Engineering108 -04 Concrete Paving and Utilities\Project_ Information \Correspondence\Memo\CO #2 exp.doc