HomeMy WebLinkAbout08-475DECEMBER 9, 2008 08 -475 RESOLUTION
(CARRIED LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 2 / PUBLIC WORKS
CONTRACT 08 -06 / FISCHER -ULMAN CONSTRUCTION /
CONCRETE SIDEWALK/ (- $26,618.31)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
Fischer -Ulman Construction
1115 S. Theodore St.
Appleton, WI 54915
Net decrease to contract: ($26,618.31)
PURPOSE: See attached Change Order.
CHANGE ORDER # 2
DATED: November 24, 2008
TO: Fischer -Ulman Construction
1115 S. Theodore St.
Appleton, WI 54915
Your present contract with the City of Oshkosh, Contract No. 08 -06 , is hereby amended
and changed as follows:
CONCRETE SIDEWALK (New and Reconstruction)
($26,618.31)
NET DECREASE TO CONTRACT:
($26,618.31)
CITY OF OSHKOSH
Recommended:
BY:
City Manager
Director of Public Works
City Clerk
roved and ac epted:
Co ractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 08 -06 CHANGE ORDER # 2
CONCRETE SIDEWALK (New and Reconstruction)
Page 1
INSTALLED
N ET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
ITEM
DESCRIPTION
UNIT
ECONTRACT
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
NUMBER
1
Sidewalk removal &
driveway removal,
com lete ass ecified
Square
Feet
95,725
104,187.74
8,462.74
$0.39 $3,300.47
$2,051.70
2
Concrete/asphalt sawing,
Linear
Feet
5,500
4,327.60
- 1,172.40
$1.75
complete ass ecified
3
Construct 4" thick concrete
sidewalk in various
locations
in the City of
Oshkosh, complete as
Square
Feet
93,600
97,194.90
3,594.90
$2,67
$9,598.38
s ecified
4
Construct 6" thick concrete
sidewalk in various
locations in the City of
Oshkosh, complete as
Square
19,100
20,695.96
1,595.96
$3.01
$4,803.84
s ecified
Feet
5
Construct 7" thick
crosswalk areas, complete
Square
4,125
4,721.63
596.63
$ 318
$ 1 897,28
ass ecified
Feet
6
Provide and install metal
detectable warning plates,
complete as specified
Square
Feet
264
288.00
24.00
$28.00
$672.00
7
Three (3 ") inch asphalt
replacement, complete as
Square
2,000
1,748.85
- 251.15
$3.50
$879.03
specified
Feet
8
Curb and gutter removal,
Linear
500
320.50
- 179.50
$3.00
$538:50)
com lete ass specified
Feet
9
Construct 30" curb and
gutter, complete as
Linear
500
369.70
- 130.30
$16.80
$2,189.04
s ecified
Feet
10
Terrace restoration,
including seed, fertilizer,
and mulch, complete as
Square
360
1,061.63
701.63
$3.50
$2,455.71
specified
Yards
11
Furnish and install
pavement ties, complete as
125
55.00
- 70.00.
$7.00
$490.001
s ecified
Each
12
Construct 4" thick concrete
sidewalk in Water Dept.
repair locations at approx.
60 sites, complete as
specified
Square
Feet
3,500
2,142.99
- 1,357.01
$3.95
($5,360.19
13
Construct 6" thick concrete
sidewalk in Water Dept.
repair locations at approx.
20 sites, complete as
specified
Square
Feet
1,0001
1,947.44
947.44
$4.101
$3,884.50
Page 1
CONTRACT: 08 -06 CHANGE ORDER # 2
ADDITIONAL WORK REQUIRED: C.O. #2
INSTALLED NET
NUMBER I DESCRIPTION I UNIT I CONTRACT
UANTITIES I QUANTITIES I INCREASE I DECREASE .) CO UNIT ER
1A Reduction of change order
#1, item #1, 8 "/7 -bag non-
reinforced concrete Square
Yard - 634.80 - 634.80 $43.75
INCREASE IN IDECREASEIN
CONTRACT CONTRACT
PRICE PRICE
Page 2
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT .
CONTRACT
ITEM
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE •
UNIT
PRICE
PRICE
NUMBER
14
7" non - reinforced concrete
pavement removal and
replacement, including
sawing, pavement ties,
integral
curb & grading,
terracing & traffic control,
complete as specified
Square
100
52.55
-47.45
$38.00
$1,803.10
Yards
15
8" non - reinforced concrete
pavement removal and
replacement, including
sawing, pavement ties,
integral curb & grading,
terracing & traffic control,
complete as specified
Square
Yards
1,500
233.19
- 1,266.81
$37.50
$47,505.38
16
8" special High Early
Strength, non - reinforced
concrete pavement
removal and replacement,
including sawing,
pavement ties, integral
curb and grading, terracing
and traffic control,
complete as specified
Square
Yards
100
170.09
70.09
$45.00
$3,154.05
17
Factra crushed stone base,
complete as specified
Tons
200
279.67
79.67
$14.00
$1,115.38
18
No. 4 epoxy - coated
reinforcement rods,
Linear
Feet
600
280.00
- 320.00
$1.50
($480.00)
installed ass ecified
19
Furnish, install, and
maintain Type "C" inlet
protection, complete as
Each
20
8.00
- 12.00
$40.00
($480.00)
s ecified
20
Furnish, install, and
maintain Type "D" inlet
protection, complete as
Each
5 0.00
-5.00
$40.00
$200.00)
s ecified
21
Construct 12" wide radius
curb head, complete as
Linear
Feet
1501
179.00
29.00
$3.001
$87.00
s ecified
$30,968.61 ($61,976.94)
SUB -TOTAL
ADDITIONAL WORK REQUIRED: C.O. #2
INSTALLED NET
NUMBER I DESCRIPTION I UNIT I CONTRACT
UANTITIES I QUANTITIES I INCREASE I DECREASE .) CO UNIT ER
1A Reduction of change order
#1, item #1, 8 "/7 -bag non-
reinforced concrete Square
Yard - 634.80 - 634.80 $43.75
INCREASE IN IDECREASEIN
CONTRACT CONTRACT
PRICE PRICE
Page 2
CONTRACT: 08 -06 CHANGE ORDER # 2
$63,131.13 .($89,749.44)
NET DECREASE TO CONTRACT: ($26,618.31)
Page 3.
UNIT
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET.
INCREASE
NET
DECREASE
COST PER
UNIT
INCREASE IN
CONTRACT
PRICE ,
DECREASE IN
CONTRACT
PRICE
ITEM
DESCRIPTION
NUMBER
1
8 -bag non - reinforced
concrete removal & replace
ment, including sawing,
pavement ties, integral
curb & grading, terracing. &
traffic control, complete as
Square
475.46
475.46
$43.75
$20,801.38
specified
Yard
2
9 "/7 -bag non - reinforced
concrete removal &
replacement, including
sawing, pavement ties,
integral curb & gutter,
terracing & traffic control,
Square
195.25
195.25
$47.50
$9,274.38
complete asspecified
Yard
3
Patch apron at 2034
Lump
1.00
1.00
$ 1 00.00
$100.00
Memominee Drive
Sum
4
Construct 8" thick concrete
Square
122.40
$3.65
$446.76
sidewalk
Feet
..122.40
5
E -Mat on N. Main Street
Square
Yard
504.00
504.00
$2.50
$1,260.00
6
Fill in street patch at 932
Winnebago Ave. with
Lump
1.00
1.00
$ 280.00
$280.00
ravel, Jump sum
Sum
ADDITIONAL
WORK: C.O.
# 2 - (ITEMS
1 - 6) - SUB
TOTAL
$32,162.52
($27,772.50)
$63,131.13 .($89,749.44)
NET DECREASE TO CONTRACT: ($26,618.31)
Page 3.
( 0
OfHKO H
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works
DATE: December 4, 2008
RE: Change Order #2 for Public Works Contract No. 08 -06;
Concrete Sidewalk (New and Reconstruction)
BACKGROUND
Change Order #2 for Contract 08 -06 is scheduled for consideration by the Common Council at the
December 9, 2008 meeting. The contract was originally awarded to Fischer -Ulman Construction of
Appleton in March 2008. This change order finalizes all quantities to the units actually installed.
ANALYSIS
All construction for this contract has been completed and final measurements taken. Any additional work
items required to complete the project are included. The actual measured quantities are entered and the
final result is a decrease to the contract.
FISCAL IMPACT
Funding for the project was in the 2008 Capital Improvement Budget. The contract has been decreased
by $26,618.31.
RECOMMENDATIONS
I recommend approval of the Change Order #2 to Contact No. 08 -06 for a decrease of $26,618.31 to
Fisher -Ulman Construction.
Respectfully Submitted,
A7' x'�J
Steven M. Gohde
Asst. Director of Public Works
Approved:
City Manager
I:\Engineering \08 -06 Sidewalk Rehab\Project_ Information \Correspondence\Memo \CO #2 exp.doe