HomeMy WebLinkAboutPW CNT 08-43/Change 1a & 1b-Joseph Hoban /seh
To sbrand @ci.oshkosh.wi.us
01/22/2008 05:07 PM
cc
bcc
Subject Change Order for Contract A an
I forgot to mention that you need to sign
all three copies of each of these document and return two to SEH
and we will distribute to Town and County - and -an° . Thanks.
Joseph T. Hoban, P.E.
Professional Engineer
Short Elliott Hendrickson Inc.
425 West Water Street Suite 300
Appleton, WI 54911 -6058
920 - 380 -2800 main
920- 380 -2814 direct
920- 380 -2801 fax
920- 470 -0957 cell
off-' 6 5 ' 2on
888- 413 -4214 toll free
B
SEH CHANGE ORDER
City of Oshkosh
OWNER
Contract 07 -02
January 14, 2008
DATE
1
OWNER'S PROJECT NO.
WWTP Security Improvements — Contract A (Cameras and Doors)
PROJECT DESCRIPTION
The following changes shall be made to the contract documents:
CHANGE ORDER NO.
OSHKO0701.01
SEH FILE NO.
Description:
Change Order #la
• Deduct 225 feet of 1 1 /2 -inch GRC conduit, and associated fittings and labor to install.
Change Order #lb
• Deduct 150 feet of GRC conduit and associated fittings and labor to install.
• Add 150 feet of EMT conduit and associated fittings and labor to install.
Purpose of Change Order:
Change Order #la
• Contractor will be utilizing an existing 2 -inch GRC conduit for a portion of the conduit run
through the tunnel. [Total Deduct: - $1,315.00]
Change Order #lb
• In the office area contractor will install EMT conduit to match existing, in place of GRC. [Total
Deduct: - $190.00]
Change Order #1 Total Deduct - $1,505,00
Basis of Cost: ® Actual ❑ Estimated
Attachments (list supporting documents)
Change Order Proposals from Town & County
Contract Status
Original Contract
Net Change Prior C.O.'s
Change this C. 0.
Revised Contract
Recommended for Approval:
Agreed to by�Contractor.
BY Town & Country
Dart Balm - Peo;ect Mana9elz
TITLE
to
Time Cost
$109,895.00
- $1,505.00
$108,390.00
Short Elliott Hendrickson I nc. by >kJ �
atrick Planton! roject Manager
Approved for Owner.- Q
SEE NEXT
BY City of Oshkosh
TITLE
Distribution Contractor 2 Owner 1 Project Representative 1 SEH Office 1
p: \ko \o \oshko \070100 \project\contracts a&b \construction \contract a \change orders \change order gl \change order 1 - contract a.doc 1/04
Short Elliott Hendrickson Inc., 425 West Water Street, Suite 300, Appleton, WI 54911 -6058
SEH is an equal opportunity employer I www.sehinc.com 1 920.380.2800 1 888.413.4214 1 920.380.2801 fax
Signed for and in behalf of the City of Oshkosh on February 13, 2008
• - •. • • 1
nager
Pamela R. Ubrig, City Clerk
LyKn Marquardt, Assis t Director of Finance
I hereby certify that the necessary provisions
have been made to pay the liability which will
accrue under this contract.
IA
P
CHANGE ORDER
SEH
Attn: Joe Hoban
425 W. Water St
Appleton, WI 54911 -6058
Phone: 920 - 380 -2814
Fax: 920- 380 -2801
Joe,
Faith Technologies, Inc.
2662 American Drive
P.O. Box 627
Appleton, WI 54912 -0627
(920) 738 -1500
Date: 11 -29 -07
Prop. No.: DS07120001
Project: Deduct for GRC to EMT
Location: Oshkosh Waste Water
CC: Patrick Planton
Town & Country Electric - Specialty Systems Division would like to thank you for the opportunity
to provide you with a proposal for the above referenced project. This is in reference to the office
area we are going to install EMT conduit to match existing in place of GRC conduit:
Deduct 150' of GRC conduit, associated fittings and labor to install
Add 150' of EMT conduit, associated fittings and labor to install
Total Deduct: - $190.00
If you have any questions or concerns, please feel free to contact me at 920 - 225 -6527.
Thank you,
Dan Salm
Project Manager
ACCEPTANCE OF PROPOSAL The above prices, specifications and conditions are satisfactory and are hereby
accepted. You are authorized to do the work specified. Payment terms are net 25 days after date of invoice.
Customer Acknowledges receipt of Faith Technologies (d/b /a Town & Country Electric) Standard Terms and
Conditions.
Signature: Date of Acceptance:
Please fax signed contracts to: DAN SALM (920- 738 -8988) Proposal price is good for 30 days.
U , MW __::C mitz
CHANGE ORDER
SEH
Attn: Joe Hoban
425 W. Water St
Appleton, WI 54911 -6058
Phone: 920 - 380 -2814
Fax: 920 - 380 -2801
Joe,
Faith Technologies, Inc.
2662 American Drive
P.O. Box 627
Appleton, WI 54912 -0627
(920) 738 -1500
Date: 12 -10 -07
Prop. No.: DS07120002
Project: Deduct to use existing conduit in
tunnel
Location: Oshkosh Waste Water
CC: Patrick Planton
Town & Country Electric- Specialty Systems Division would like to thank you for the opportunity
to provide you with a proposal for the above referenced project. This is in reference to Town &
Country Electric using an existing 2" GRC conduit for a portion of the conduit run through the
tunnel.
• Deduct 225' of 1 1 /2" GRC conduit, associated fittings and labor to install
Total Deduct: - $1,315.00
If you have any questions or concerns, please feel free to contact me at 920 - 225 -6527.
Thank you,
Dan Salm
Project Manager
ACCEPTANCE OF PROPOSAL The above prices, specifications and conditions are satisfactory and are hereby
accepted. You are authorized to do the work specified. Payment terms are net 25 days after date of invoice.
Customer Acknowledges receipt of Faith Technologies (d/b /a Town & Country Electric) Standard Terms and
Conditions.
Signature: Date of Acceptance:
Please fax signed contracts to: DAN SALM (920- 738 -8988) Proposal price is good for 30 days.