CHANGE ORDER # 1
DATED: February 27, 2008
TO: Northeast Asphalt, Inc.
W6380 Design Drive
Greenville WI 54942
Your present contract with the City of Oshkosh, Contract No. 07 -08 , is hereby amended
and changed as follows:
NET DECREASE TO: SECTION I - ASPHALT PAVING ($20,780.86)
NET DECREASE TO: SECTION II - STORM SEWER ($320.00)
NET DECREASE TO: SECTION III -SANITARY SEWER ($7.10)
NET DECREASE TO CONTRACT: ($21,107.96)
E
Recommende
Director oWorks
Approved and accepted:
Contractor
Chris J. Winiecki, Agent
certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comet ller
r
CONTRACT: 07 -08 CHANGE ORDER # 1
SECTION I - ASPHALT PAVING
100.
Approx. 3,550 square
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
CONTRACT
INSTALLED
NET
NET
COST PER
CONTRACT
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
100.
Approx. 3,550 square
feet of sidewalk and
driveway removal,
complete as specified,
per square foot
3,550.00
3,585.00
35.00
$0.58
$20.30
101.
Approx. 350 cubic
yards of excavation,
complete as specified,
per cubic yard
350.00
13.00
- 337.00
$10.25
$3,454.25
102.
Approx. 9,700 square
yards of pavement
milling, complete as
specified, per square
and
9,700.00
9,733.00
33.00
$2.39
$78.87
103.
Approx. 1,140 tons of
asphaltic concrete
binder material,
complete as specified,
p er ton
1,140.00
1,059.00
-81.00
$51.00
($4,131.00)
104.
Approx. 990 tons of
asphaltic concrete
surface material,
complete as specified,
er ton
990.00
909.00 .
-81.00
$52.00
$4,212.00
105.
Approx. one (1)
asphaltic concrete
speed bump, complete
as specified, lump
sum
1.00
1.00
$2,500.00
106.
Approx. 375 gallons of
tack or prime coat,
complete as specified
er qallon
375.00
400.00
25.00
$2.00
$50.00
107.
Approx. 450 square
yards of 7" concrete
base course removal
and replacement,
complete as specified,
per square yard
450.001
107.00
1
1 - 343.00
1 $39.00
$13,377.00
Page 1
M
CONTRACT: 07 -08 CHANGE ORDER # 1
ITEM
DESCRIPTION
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
108.
Approx. 600 linear feet
of curb & gutter
removal and
replacement, complete
as specified, per linear
foot
600.00
958.00
358.00
$24.60
$8,806.80
109.
Approx. 75 linear feet
of 12" wide radius
curb head, complete
as specified, per linear
foot
75.00
108.00
33.00
$20,001
$660.00
110.
Approx. 2,340 square
feet of 4" concrete
sidewalk, complete as
specified, per square -
foot
2,340.00
2,291.00
-49.00
$2.80
($137.20
111.
Approx. 2,270 square
feet of 6" concrete
sidewalk & driveway,
complete as specified,
per square foot
2,270.00
2,451.00
181.00
$3.02
$546.62
112.
Provide and install
approx. 40 square feet
of metal detectable
warning plates,
complete as specified,
per square foot
40.00
64.00
24.00 =' `
$34.001
$816.00
113.
Furnish and install
approx. 760 tons of
crushed stone base
course, complete as
specified, per ton
760.00
56.00
- 704.00
$8.00
($5,632.00
114.
Approx..250 linear feet
of sawing, complete
as specified, per linear
foot
250.00
52.00
- 198.00
$2.00
$396.00
115.
Adjust approx. 20
manholes and inlets,
complete as specified,
each
20.00
19.00
-1.00
$420.00
$420.00)
Page 2
S
CONTRACT: 07 -08 CHANGE ORDER # 1
ITEM
DESCRIPTION
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
116.
Preparation of
foundation for asphalt
paving on Congress
Avenue (Algoma Blvd.
to Elmwood Ave.),
complete as specified,
lump sum
1.00
1.00
$3,225.00
117.
Preparation of
foundation for asphalt
paving on Congress
Avenue (Spruce St. to
Walnut St.), complete
as specified, lump
sum
1.00
1.00
$4,000.00
118.
Preparation of
foundation for asphalt
paving on W. Irving
Avenue, complete as
specified, lump sum
1.00
1.00
$2,825.00
119.
Preparation of
foundation for asphalt
paving on Jefferson
Street, complete as
s ecified lump sum
1.00
1.00
$6,635.00
120.
Preparation of
foundation for asphalt
paving at the Fountain
Avenue lift station,
complete as specified,
IUMD sum
1.00
1.00
$1,650.00
121.
Provide $600.00 to the
City of Oshkosh for
project management
communications,
complete as specified,
lump sum
1.00
1.00
$600.00
1
SECTION 1- (BID ITEMS 100 -121) - SUB - TOTALS $10,978.59 ($31,759.45)
NET DECREASE TO: SECTION I - ($20,780.86)
SECTION it - STORM SEWER
Page 3
CONTRACT: 07 -08 CHANGE ORDER # 1
200.
Furnish, install, and
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
CONTRACT
INSTALLED
NET
NET
COST PER
CONTRACT
CONTRACT
NUMBER
Inlet Protection in
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
200.
Furnish, install, and
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
CONTRACT
INSTALLED
NET
NET
COST PER
CONTRACT
CONTRACT
NUMBER
Inlet Protection in
QUANTITIES
QUANTITIES
INCREASE
DECREASE
__
UNIT
PRICE
PRICE
200.
Furnish, install, and
INCREASE IN
DECREASE IN
ITEM
maintain Type "C'
CONTRACT
INSTALLED
NET
NET
COSTPER
CONTRACT
CONTRACT
NUMBER
Inlet Protection in
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
approx. 30 locations,
complete as specified,
each
30.00
22.00
6.00
-8.00
$40.00
$585.30
$320.00
201.
Provide $200.00 to the
City of Oshkosh for
project management
communications,
complete as specified,
lump sum
73.00
75.00
2.00
$86.801
$173.60
302.
Furnish and install
1.001
1.00
1
1
1 $200.00
SECTION II - (BID ITEMS 200 - 201) SUB- TOTALS $0.00 ($320.00)
NET DECREASE TO: SECTION II - ($320.00)
SECTION III - SANITARY SEWER
300:
Furnish and install
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
CONTRACT
INSTALLED
NET
NET
COSTPER
CONTRACT
CONTRACT
NUMBER
of 10" sanitary sewer
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
300:
Furnish and install
approx. 80 linear feet
of 10" sanitary sewer
spot repair, complete
as specified, per linear
foot
80.00
86.00
6.00
$97.551
$585.30
301.
Furnish and install
approx. 73 linear feet
of 12" sanitary sewer
spot repair, complete
as specified, per linear
foot
73.00
75.00
2.00
$86.801
$173.60
302.
Furnish and install
approx. 10 linear feet
of 10" sanitary sewer
relay, complete as
specified, per linear
foot
10.00
2.00
-8.00
$37.55
$300.40
Page 4
CONTRACT: 07 -08 CHANGE ORDER # 1
ITEM
DESCRIPTION
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
303.
Furnish and install
approx. 12 linear feet
of 12" sanitary sewer
relay, complete as
specified, per linear
foot
12.00
8.33
-3.67
$39.60
$145.33
304.
Furnish and install
approx. 5 linear feet of
15" sanitary sewer
relay, complete as
specified, per linear
foot
5.00
6.33
1.33
$42.95
$57.12
305.
Furnish and install
approx. 36 linear feet
of 6" sanitary lateral
relay, complete as
specified, per linear,
foot
36.00
29.00
-7.00
$67.05
$469.35
306.
Furnish and install
approx. 7 10" x
6" factory wyes or
tees, completed as
s ecified each
7.00
7.00
$100.00
307.
Furnish and install
approx. 5 12"
x 6" factory wyes or
tees, completed as
specified, each
5.00
3.00
-2.00
$145.00
$290.00)
308.
Furnish and install
approx. 16
connections of new
sanitary main to
existing main, (various
locations and sizes),
completed as
specified, each
16.00
16.00
$85.00
309.
Abandon one sanitary
manhole, complete as
specified, each
1.00
1.00
$300.00
310.
Abandon approx. 10
lineal feet of 12"
sanitary sewer,
completed as
specified, per lineal
foot
1 10.001
10.00
1
$10.00
Page 5