HomeMy WebLinkAboutPW CNT 07-06/Change Order #1City of Oshkosh
Department of Public Works
215 Church Avenue
P.O. Box 1130
Oshkosh, Wisconsin
54903 -1130
(920) 236 -5065
OIHKO H 9p[
ON THE WATER JAN _I
January 10, 2008 CITY `Y
Mr. Leroy Fischer
Fischer -Ulman Construction, Inca
1115 S. Theodore Street
Appleton, WI 54915
Re: Change Order #1 /Contract 07 -06
Dear Mr. Fischer:
Enclosed please find an executed copy of the Change Order between the City of Oshkosh and
Fischer -Ulman Construction, Inc. regarding the above- mentioned project.
If you have any questions, please call our office at (920) 236 -5065. Thank you.
Sincerely,
David C. Patek
Director of Public Works
DCP /clm
Enclosure
cc: Pam Ubrig, City Clerk (w /original)
Lynn Lorenson, Assistant City Attorney (w /copy)
File Copy (w /original)
CHANGE ORDER # 1
DATED: December 7, 2007
TO: Fischer -Ulman Construction, Inc.
1115 S. Theodore St.
Appleton, WI 54915
Your present contract with the City of Oshkosh, Contract No. 07 -06 , is hereby amended
and changed as follows:
NET INCREASE - CONCRETE SIDEWALK (New and Reconstruction) $65,529.88
NET INCREASE TO CONTRACT: $65,529.88
C
BY:
Recommended:
irector of Public orks
and accept :
ontr ctor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
- _-*
CONTRACT: 07 -06 CHANGE ORDER # 1
CONCRETE SIDEWALK (New and Reconstruction)
1.
Approx. 88,000 square feet
INCREASE IN
DECREASE /N
ITEM
of sidewalk removal &
CONTRACT
INSTALLED
NET
NET
COST PER
CONTRACT
CONTRACT
NUMBER
DESCRIPTION
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
1.
Approx. 88,000 square feet
of sidewalk removal &
driveway removal,
complete as specified, per
square foot
88,000
103,886.64
15,886.64
$0.39
$6,195.79
2.
Approx. 5,500 linear feet of
concrete /asphalt sawing,
complete as specified, per
linear foot
5,500
4,906.10
- 593.90
$2.25
$1,336.28)
3.
Construct approx. 75,000
square feet of 4" thick
concrete sidewalk in
various locations in the City
of Oshkosh, complete as
specified, per square foot
75,000
97,218.59
22,218.59
$2.67
$59,323.64
4.
Construct approx. 17,500
square feet of 6" thick
concrete sidewalk in
various locations in the City
of Oshkosh, complete as
specified, per square foot
17,500
17,283.16
- 216.84
$3.05
($661.36)
5.
Construct approx. 1,800
square feet of 7" thick
crosswalk areas, complete
as specified, per square
foot
1,800
3,933.60
2,133.60
$3.25
$6,934.20
6.
Provide and install approx.
160 square feet of metal
detectable warning plates,
complete as specified, per
square foot
160
260.00
100.00
$32.00
$3,200.00
7.
Approx. 2,000 square feet
of three (3 ") inch asphalt
replacement, complete as
specified, per square foot
2,000
2,736.30
736.30
$3.20
$2,356.16
8.
Approx. 400 linear feet of
curb and gutter removal,
complete as specified, per
linear foot
400
557.70
157.70
$3.80
$599.26
9.
Approx. 400 linear feet of
30" curb and gutter,
complete as specified, per
linear foot
400
587.80
187.80
$16.80
$3,155.04
Page 1
CONTRACT: 07 -06 CHANGE ORDER # 1
ITEM
DESCRIPTION
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
10.
Approx. 1,200 square yards
of terrace restoration,
including seed, fertilize,
and mulch, complete as
specified, per square yard
1,200
335.80
- 864.20
$3.50
($3,024.70)
11.
Furnish and install approx.
200 pavement ties,
complete as specified,
each
200
110.00
-90.00
$7.00
($630.00)
12.
Construct approx. 3,000
square feet of 4" thick
concrete sidewalk in Water
Dept. repair locations at
approx. 60 sites, complete
as specified, per square
foot
3,000
3,955.21
1 955.21
$3.95
$3,773.08
13.
Construct approx. 750
square feet of 6" thick
concrete sidewalk in Water
Dept. repair locations at
approx. 20 sites, complete
as specified, per square
foot
750
989.06
239.06
$4.10
$980.15
14.
Approx. 100 square yards
of 7" non - reinforced
concrete pavement
removal and replacement,
including sawing,
pavement ties, integral
curb & grading, terracing &
traffic control, complete as
specified, per square yard
100
208.77
108.77
$38.00
$4,133.26
15.
Approx. 1,800 square yards
of 8" non - reinforced
concrete pavement
removal and replacement,
including sawing,
pavement ties, integral
curb & grading, terracing &
traffic control, complete as
specified, per square yard
1,800
688.06
- 1,111.94
$38.50
($42,809.69)
Page 2
CONTRACT: 07 -06 CHANGE ORDER # 1
ITEM
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
DESCRIPTION
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
16.
Approx. 100 square yards
�
PRICE
1.
of 8" special High Early
Strength, non -
reinforced concrete
0
31
31.00
$10.00
$310.00
2.
pavement removal and
replacement, including
sawing, pavement ties,
integral curb and grading,
terracing and traffic control,
0
1.00
1.00
$570.001
$570.00
3.
complete as specified, per
-88.69
$45.00
($3,991.05)
square and
100
11.31
77.60
$2.25
$174.60
17,
Approx. 200 tons extra
crushed stone base,
complete as specified, per
51.00
- 149.00
$14.00
($2,086.00)
ton
200
18.
Approx. 600 linear feet of
No. 4 epoxy- coated
reinforcement rods,
installed as specified, per
linear foot
600
840.00
240.00
$1.50
$360.00
19.
Furnish, install and
maintain Type "C' Inlet
protection in approx. 5
locations, complete as
1.00
$85.00
$85.00
specified, each
5
6.00
20.
Approx. 150 linear feet of
12" wide radius curb head,
complete as specified, per
-33.40
$3.00
($100.20)
linear foot
150
116.60
21.
Provide $1,500 to the City
of Oshkosh for project
management
communications, complete
as specified, lump sum
1
1.00
$1,500.00
BID ITEMS 1 -21 - SUB -TOTAL . $91,095.58 ($54,639.28)
ADDITIONAL WORK REQUIRED: C.O. # 1
Page 3
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
COST PER
UNIT
CONTRACT
CONTRACT
PRICE
NUMBER
�
PRICE
1.
Replace 6" curb head at
222 Jackson Street, per
lineal foot
0
31
31.00
$10.00
$310.00
2.
Clean out rubble from
basement and form base
for sidewalk installation at
101 Algoma Blvd. as
specified, lump sum
0
1.00
1.00
$570.001
$570.00
3.
Erosion control mat, per
square yard
0
77.60
77.60
$2.25
$174.60
Page 3
CONTRACT: 07 -06 CHANGE ORDER # 1
ADDITIONAL WORK: C.O. # 1 - (ITEMS 1 - 7) - SUB -TOTAL $29,073.58
NET INCREASE - $65,529.88
NET INCREASE TO CONTRACT: $65,529.88
$0.00
Page 4
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
COST PER
UNIT
CONTRACT
CONTRACT
PRICE
NUMBER
PRICE
4.
Replace 4" asphalt, per
square foot
0
977.85
977.85
$4.27
$4,175.42
5.
Construct 8" sidewalk,
complete as specified, per
square foot
0
885.00
885.00
$4.72
$4,177.20
6.
7 -13ag mix concrete /8 ", per
square yard
0
432.55
432.55
$42.50
$18,383.38
7.
7 -13ag mix concrete /9 ", per
square yard
1 0
27.01
27.01
$47.50
$1,282.98
ADDITIONAL WORK: C.O. # 1 - (ITEMS 1 - 7) - SUB -TOTAL $29,073.58
NET INCREASE - $65,529.88
NET INCREASE TO CONTRACT: $65,529.88
$0.00
Page 4