HomeMy WebLinkAbout08-42FEBRUARY 12, 2008 08 -42 RESOLUTION
(CARRIED 7 -0 LOST LAID OVER WITHDRAWN )
PURPOSE: CHANGE ORDER NO. 2, PUBLIC WORKS CONTRACT NO. 06 -11
(-$37,966.83)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
Vinton Construction Co.
PO Box 1987
Manitowoc, WI 54221 -1987
Net decrease to contract: (- $37,966.83)
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 561 - 2010 - 1799 -00000 Storm Water Utility — Construction in Progress
TO: Vinton Construction Co.
P. O. Box 1987
Manitowoc, WI 54221 -1987
CHANGE ORDER # 2
DATED: January 15, 2008
Your present contract with the City of Oshkosh, Contract No. 06 -11 , is hereby amended
and changed as follows:
NET DECREASE TO: SECTION I - STORM SEWER (Items 1A - 33A) ($38,958.91)
NET INCREASE TO: SECTION II - SANITARY SEWER (Items 34A - 35A) $32.33
NET INCREASE TO: SECTION III -WATER MAIN $959.75
NET DECREASE TO CONTRACT: ($37,966.83)
CITY OF OSHKOSH
EM
Recommended:
Director of Public Works
City Clerk
Approved and accepted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Manager
City Attorney
S �
CONTRACT: 06 -11 CHANGE ORDER # 2
SECTION I - STORM SEWER (Items 1A - 33A)
1A Furnish and install approx.
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE 1N
CONTRACT
DECREASE !N
CONTRACT
ITEM
NUMBER
DESCRIPTION
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
1A Furnish and install approx.
370 linear feet of 12" Storm
Sewer, complete as
specified, per linear.foot
Completed in 2006
2A Furnish and install approx.
127 linear feet of 15"
Storm Sewer, complete as
specified, per linear foot
Completed in 2006
3A Furnish and install approx.
380 linear feet of 24"
Storm Sewer, complete as
specified, per linear foot
69.00
50.53
-18.47
$38.84
$717.37)
4A Furnish and install approx.
32 linear feet of 27' Storm
Sewer, complete as
specified, per linear foot
32.00
28.93
-3.07
$85.81
($263.44)
5A Furnish and install approx.
49 linear feet of 30" Storm
Sewer, complete as
specified, per linear foot
Completed in 2006
6A Furnish and install approx.
945 linear feet of 36" Storm
Sewer, complete as
specified, per linear foot
945.00
956.071
11.07
$95.15
$1,053.3
7A Furnish and install approx.
1,405 linear feet of 42"
Storm Sewer, complete as
specified, per linear foot
1,405.00
1,393.52
-11.48
$106.45
$1,222.05
8A Furnish and install approx.
464 linear feet of 48" Storm
Sewer, complete as
specified, per linear foot
464.00
451.38
-12.62
$119.23
$1,504.68
9A Furnish and install approx.
1,376 linear feet of 24" x
38" HERCP Class HE -III
Storm Sewer, complete as
specified, per linear foot
Completed in 2006
10A Furnish and install approx.
164 linear feet of 43" x 68"
HERCP Class HE -III
Storm Sewer with rg avel
backfill complete as
specified, per linear foot
164.001
164.001
$131.33
Page 1
M
CONTRACT: 06 -11 CHANGE ORDER # 2
ITEM
CONTRACT
INSTALLED
NET
NET
COSTPER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
DESCRIPTION
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
11A
Furnish and install approx.
866 linear feet of 43" x 68"
HERCP Class HE -III
Storm Sewer with natural
backfill complete as
specified, per linear foot
866.00
861.67
-4.33
$109.83
$475.56
12A
Furnish and install approx.
two (2) 24" endwalls
n2.00
(Sherman Road), complete
as specified, each
2.00
$1,173.00
13A
Furnish and install one (1)
24" x 38" endwall with trash
guard and pipe ties,
complete as specified,
each
Completed in 2006
14A
Furnish and install one (1)
30" endwall with trash
guard and pipe ties,
complete as specified,
each
Eliminated from Contract
15A
Furnish and install one (1)
43" x 68" endwall with trash
guard and pipe ties,
complete as specified,
each
1.00
1.00
$4,290.00
16A
Construct approximately
1,240 linear feet of open
ditching, complete as
specified, per linear foot
Elimina from Contract
17A
Clean approximately 75
linear feet of existing storm
ditch, complete as
specified, per linear foot.
Eliminated from Contract
18A
Furnish and install one (1)
Std. Type I Inlet (30" inside
diameter with 18" sump)
with castings, complete as
specified, each
Completed in 2006
19A
Furnish and install approx.
13.62 vertical feet of std.
Storm Manhole (4' Inside
Diameter) in three (3)
locations with castings,
complete as specified, per
vertical foot
5.75
0.00
-5.75
$310.00
$1,782.50
20A
Furnish and install approx.
55.21 vertical feet of std.
Storm Manhole (6' Inside
Diameter) in eight (8)
locations with castings,
complete as specified, per
vertical foot
1 31.91
29.31
-2.60
$432.67
$1,124.94
Page 2
CONTRACT: 06 -11 CHANGE ORDER # 2
ITEM
CONTRACT..
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
DESCRIPTION
QUANTITIES
QUANTITIES.
INCREASE
DECREASE
UNIT
PRICE
PRICE
21A
Furnish and install approx.
57.35 vertical feet of std.
Storm Manhole (8' Inside
Diameter) in five (5)
locations, with castings, per
vertical foot
57.35
53.64
-3.71
$522.67
$1,939.11
22A
Furnish and install approx.
21.48 vertical feet of std.
Storm Box Manhole in four
(3) locations with castings,
complete as specified, per
vertical foot
21.48
19.02
-2.46
$591.67
$1,455.51
23A
Rebuild approx. 8.07
vertical feet of std. Storm
Manhole (6" Inside
Diameter) in one (1)
location with casting,
complete as specified, per
vertical foot
8.07
6.97
-1.10
$434.67
$478.14
24A
Furnish and install approx.
90 tons of medium riprap,
complete as specified, per
ton
30.00
19.35
-10.65
$31.35
$333.88)
25A
Saw out approx. 3,190
linear feet of asphalt
pavement (Sherman
Road), complete as
specified, per linear foot
3,190.00
3,190.00
$1.51
26A
Approx. 650 tons of 3 1/4" -
5" asphaltic concrete
pavement, complete as
specified, per ton
650.00
808.70
158.70
$67.85
$10,767.80
27A
Approx. 560 tons of gravel
shoulder restoration
(Sherman Road), complete
as specified, per ton
560.001
194.00
- 366.00.
$19.34
$7,078.44
28A
Salvage and reset ex.
Berntsen Monument at E.
Snell Road/ Sherman
Road, complete as
s ecified, lump sum
1.00
1.00
$765.00
29A
Terrace, sidewalk,
driveway and street
restoration on Bauman
Street, complete as
specified, lump sum
Completed in 2006
30A
Terrace and street
restoration on N. Main
Street, complete as
, specified, lump sum
0.25
0.25
$8,000.00
Page 3
CONTRACT: 06 -11 CHANGE ORDER # 2
ITEM
Credit item for approx.
CONTRACT
INSTALLED
NET
NET
COSTPER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
DESCRIPTION
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
31A
Terrace restoration on
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
Sherman Road and
Sherman Road Easement,
complete as specified,
1 8,33
8,337.60
$4.00
($33,350.40
2B
lum sum
1.00
1.00
$12,900.00
32A
Terrace and street
restoration in Winnebago
County Park, complete as
specified, lump sum
0.25
0.25
$18,225.00
33A
Provide $1,000.00 to the
1.00
1 1.00
1
1 $946.00
1 $946.00
City of Oshkosh for project
management
communications, complete
as specified, lump sum
1.00
1.00
$1,000.00
_ —_ _ _
CAA A AA
/ @d4 R7t C91
JCl+11V1Y 1. -�11 GIYIJ IM `.a./et) - �v ��..v + a - - -•- ,T-- a- - -- - -•
ADDITIONAL WORK REQUIRED: C.O. # 2 - SECTION 1
113
Credit item for approx.
INCREASE /N
DECREASE fN
ITEM
DESCRIPTION
CONTRACT
I INSTALLED
NET
NET
COST PER
CONTRACT
CONTRACT
NUMBER
crushed concrete base
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
113
Credit item for approx.
INCREASE IN
DECREASE IN
ITEM
8337.6 tons of salvaged
CONTRACT
INSTALLED
NET
NET
COST PER
CONTRACT
T
CONTRACT
NUMBER
crushed concrete base
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
course supplied by the City.
Credit paid to the City per
ton.
1 8,33
8,337.60
$4.00
($33,350.40
2B
Additional cost of labor &
materials to reconnect
existing 21" storm sewer to
storm manhole #18, per
invoice #6530 dated
11/12/07, lump sum
1.00
1 1.00
1
1 $946.00
1 $946.00
ADDITIONAL WORK: C.O. # 2 - (ITEMS 1 B - 2B) - SUB -TOTAL $946.00 ($33,350.40)
NET DECREASE TO: SECTION I - ($38,958.91)
SECTION II - SANITARY SEWER (Items 34A - 35A)
34A Furnish and install approx.
77 linear feet of 10"
Sanitary Sewer Relay
(Sherman Road), complete
as specified, per linear foot
77.001 78.69 1 1.69 1 1 $83.63 1 $141.33
Page 4
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
CONTRACT
INSTALLED
NET
NET
COST PER
CONTRACT
T
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
34A Furnish and install approx.
77 linear feet of 10"
Sanitary Sewer Relay
(Sherman Road), complete
as specified, per linear foot
77.001 78.69 1 1.69 1 1 $83.63 1 $141.33
Page 4
Page 5
CONTRACT: 06 -11 CHANGE ORDER # 2
INCREASE IN DECREASE IN
ITEM
DESCRIPTION
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
COST PER
UNIT
CONTRACT
PRICE
CONTRACT
PRICE
NUMBER
35A
Rebuild approx. 13.45
vertical feet of std. Sanitary
Manhole with base and
casting (Sherman Road),
complete as specified, per
vertical foot
13.45
12.85
-0.60
$181.67
$109.00
SECTION II - (ITEMS 34A - 36A) - SUB - TOTALS
$141.33
($109.00)
NET INCREASE TO: SECTION 11-
$32.33
SECTION III -WATER MAIN
ADDITIONAL WORK REQUIRED: C.O. # 2 - SECTION III
INCR=iNDECR
EASE
ITEM
DESCRIPT ION
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
COST PER
UNIT
CONTNUMBER
PICE
113
Additional cost of labor and
materials to relocate
1 1/4" water service from
sanitary manhole, per
invoice #6503, dated
1.00
1.00
$440.75
$440.75
10/31/07, lum sum
2B
Additional cost of labor and
materials to raise existing
8" watermain at Station
33 +53, per invoice #6521,
dated 11/8/07, lump sum
1.00
1.00
$519.00
$519.00
ADDITIONAL WORK: C. 0.#2 -(ITEMS 1B -2B) -
SUB -TOTAL
$959.75
$0.00
NET INCREASE TO: SECTION 111-
$959.75
NET INCREASE TO SECTIONS I, II, III
$13,868.19
NET DECREASE TO SECTIONS I, 11, 111
($51,835.02)
NET DECREASE TO CONTRACT:
($37,966.83)
Page 5