HomeMy WebLinkAbout08-43REVISED FEBRUARY 12, 2008 08 -43 RESOLUTION (CARRIED 7 -0 LOST LAID OVER WITHDRAWN ) PURPOSE: CHANGE ORDER NO. 1, PUBLIC WORKS CONTRACT 07 -02 (DECREASE: $1,505.00) INITIATED BY: DEPARTMENT OF PUBLIC WORKS BE IT RESOLVED by the Common Council of the City of Oshkosh that the following Change Order, a copy of which is attached, is hereby approved: • TOWN & COUNTRY ELECTRIC 2662 American Drive Appleton, WI 54912 -0627 Net Decrease to contract: (- $1,505.00) PURPOSE: See attached Change Order. • Revised (No account numbers needed for decrease in contract.) _;�k SEH CHANGE ORDER City of Oshkosh OWNER Contract 07 -02 January 14, 2008 DATE 1 OWNER'S PROJECT NO. WWTP Security Improvements — Contract A (Cameras and Doors) PROJECT DESCRIPTION The following changes shall be made to the contract documents: CHANGE ORDER NO. OSHKO0701.01 SEH FILE NO. Description Change Order #la • Deduct 225 feet of 1 1 /2 -inch GRC conduit, and associated fittings and labor to install. Change Order #lb • Deduct 150 feet of GRC conduit and associated fittings and labor to install. • Add 150 feet of EMT conduit and associated fittings and labor to install. Purpose of Change Order. Change Order #la • Contractor will be utilizing an existing 2 -inch GRC conduit for a portion of the conduit run through the tunnel. [Total Deduct: - $1,315.00] Change Order #lb • In the office area contractor will install EMT conduit to match existing, in place of GRC. [Total Deduct: 4190.001 Change Order #1 Total Deduct - $1,505,00 Basis of Cost: ® Actual ❑ Estimated Attachments (list supporting documents) Change Order Proposals from Town & County Contract Status Original Contract Net Change Prior C.O.'s Change this C.O. Revised Contract Recommended forApproval: Time Cost $109,895.00 to - $1,505.00 $108,390.00 Short Elliott Hendrickson I nc, by P atrick PlantonlP Manager A reed to by Contractor. Approved for Owner. BY Town & Country barn Salm - P2o;ect Mana9e?- TITLE BY City of Oshkosh TITLE Distribution Contractor 2 Owner 1 Project Representative 1 SEH Office 1 p:\ko \o\oshko\ 070100 \project\contracts a&bkonstmetion\contract a\change orders\cbange order #1 \change order 1 - contract a.doc 1/04 Short Elliott Hendrickson Inc., 425 West Water Street, Suite 300, Appleton, WI 54911 -6058 SEH is an equal opportunity employer I www.sehinc.com 1 920.380.2800 1 888.413.4214 1 920.380.2801 fax �ELEGTR/C Faith Technologies, Inc. 2662 American Drive P.O. Box 627 Appleton, WI 54912 -0627 (920) 738 -1500 CHANGE ORDER SEH Attn: Joe Hoban 425 W. Water St Appleton, WI 54911 -6058 Date: 11 -29 -07 Prop. No.: DS0712000l Project: Deduct for GRC to EMT Location: Oshkosh Waste Water CC: Patrick Planton Phone: 920 - 380 -2814 Fax: 920- 380 -2801 Joe, Town & Country Electric - Specialty Systems Division would like to thank you for the opportunity to provide you with a proposal for the above referenced project. This is in reference to the office area we are going to install EMT conduit to match existing in place of GRC conduit: • Deduct 150' of GRC conduit, associated fittings and labor to install • Add 150' of EMT conduit, associated fittings and labor to install Total Deduct: - $190.00 If you have any questions or concerns, please feel free to contact me at 920- 225 -6527. Thank you, Dan Salm Project Manager ACCEPTANCE OF PROPOSAL The above prices, specifications and conditions are satisfactory and are hereby accepted. You are authorized to do the work specified. Payment terms are net 25 days after date of invoice. Customer Acknowledges receipt of Faith Technologies (d/b /a Town & Country Electric) Standard Terms and Conditions. Signature: Date of Acceptance: Please fax signed contracts to: DAN SALM (920- 738 -8988) Proposal price is good for 30 days. AMEBA " � J �ELEGTl2/G� CHANGE ORDER SEH Attn: Joe Hoban 425 W. Water St Appleton, WI 54911 -6058 Phone: 920 -380 -2814 Fax: 920 - 380 -2801 Joe, Faith Technologies, Inc. 2662 American Drive P.O. Box 627 Appleton, WI 54912 -0627 (920) 738 -1500 Date: 12 -10 -07 Prop. No.: DS07120002 Project: Deduct to use existing conduit in tunnel Location: Oshkosh Waste Water CC: Patrick Planton Town & Country Electric- Specialty Systems Division would like to thank you for the opportunity to provide you with a proposal for the above referenced project. This is in reference to Town & Country Electric using an existing 2" GRC conduit for a portion of the conduit run through the tunnel. • Deduct 225' of 1 t /2" GRC conduit, associated. fittings and labor to install Total Deduct: - $1,315.00 If you have any questions or concerns, please feel free to contact me at 920 - 225 -6527. Thank you, Dan Salm Project Manager ACCEPTANCE OF PROPOSAL The above prices, specifications and conditions are satisfactory and are hereby accepted. You are authorized to do the work specified. Payment terms are net 25 days after date of invoice. Customer Acknowledges receipt of Faith Technologies (d/b /a Town & Country Electric) Standard Terms and Conditions. Signature: Date of Acceptance: Please fax signed contracts to: DAN SALM (920- 738 -8988) Proposal price is good for 30 days.