HomeMy WebLinkAbout08-03JANUARY 8, 2008 08-03 RESOLUTION
(CARRIED ~ ~ LOST LAID OVER WITHDRAWN )
PURPOSE: CHANGE ORDER NO. 1, PUBLIC WORKS CONTRACT NO, 07-06
($65,529.88)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
Fischer-Ulman Construction, Inc.
1115 S. Theodore St.
Appleton, WI 54915
Net Increase to contract: $65,529.88
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 311-0410-7480-00000 Sidewalk Construction Fund Expenditures
Acct. No. 317-0410-7480-03304 Special Assessments - Sidewalks
Acct. No. 541-1867-6401-08673 Water Utility - Maintenance of Mains
Acct. No. 541-1867-6401-08675 Water Utility - Maintenance of Services
CHANGE ORDER # 1
DATED: December 7, 2007
TO: Fischer-Ulman Construction, Inc.
1115 S. Theodore St..
Appleton, WI 54915
Your present contract with the City of Oshkosh, Contract No. 07-06 , is hereby amended
and changed as follows:
NET INCREASE - CONCRETE SIDEWALK (New and Reconstruction) $65,529.88 ~
NET INCREASE TO CONTRACT: $65,529.88
CITY OF OSHKOSH
BY:
Recommended:
Director of Public Works
-
Cifiy Manager
City Clerk
Approved and accep~~ n
~ ontr~ctor
~~ ~
I certify that provision has been made to pay the fiability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 07-06 CHANGE ORDER # 1
CONCRETE SIDEWALK (New and Reconstruction)
lNCREASE IN DECRF.ASElN
1TEM
DESCRlPTlON CONTRACT
QUANTlT/ES INSTALLED
QUANTITIES NET
/NCREASE NET
DECREASE COSTPER
UNlT CONTRACT
PRICE CONTRACT
PRICE
NUMBER
1. Approx. 88,000 square feet
of sidewalk removal &
driveway removal,
complete as specified, per
000
88
886.64
103
15,886.64 0.39
~ $6,195.79
s uare foot , ,
2. Approx. 5,500 linear feet of
concrete/asphalt sawing,
complete as specified, per
500
5
906.10
4
-593.90
$2•25 1,336.28
~
l inear foot , ,
3. Construct approx. 75,000
square feet of 4" thick
concrete sidewalk in
various locations in the City
o,f Oshkosh, complete as
specified, per square foot
75,000
97,218.59
22,218.59 2,67
~ $59,323.64
4. ~ Construct approx. 17,500
square feet of 6" thick
concrete sidewalk in
various locations in the City
of Oshkosh, complete as . '
specified, per square foot
17,500
17,283.16
-216.84
$3.05
($661.36
5. Construct approx. 1,800
square feet of 7" thick
crosswalk areas, complete
as specified, per square
800
1
933.60
3
2,133.60 $3.25 $6,934.20
foot , ,
6. Provide and install approx.
160 square feet of inetai
detectable warning plates,
complete as specified, per
160
00
260
100.00
$32.00
$3,200.00
s uare foot .
7. Approx. 2,000 square feet
of three {3"} inch asphalt
replacement, complete as
s ecified, er s uare foot
2,000
2,736.30
736.30 $3.20 $2,356.16
8. Approx. 400 linear feet of
curb and gutter removal,
complete as specified, per
400
70
557
157.70 $3.80 $599.26
linear foot .
9. Approx. 4~0 linear feet of
30" curb and gutter,
complete as specified, per
40
0
587.80
187.80 $16.8 0 $3,155.04
linear foot
page 1
CONTRACT: 07-06 CFiANGE ORDER # 1
INCREASE !N DECREASE !N
lTEM CONTRACT lNSTALLED NET NET COSTPER CONTRACT COMTRACT
NUMBE'R DESCRlPTlON QUANTlTIES QUANTlTlES lNCREASE DECREASE UNlT PRlCE PRlCE
10. Approx. 1,200 square yards
of terrace restoration,
including seed, fertilize,
and mulch, complete as
specified, per square yard
1,200
335.80 ~
-864.20
$3.50
$:3,024.70
11. Furnish and instali approx.
200 pavement ties,
complete as specified,
200
110
00
00
-90
$7.00
$630.00)
each . .
12. Construct approx. 3,000
square feet of 4" thick
concrete sidewalk in Water
Dept. repair Iocations at
approx. 60 sites, complete
as specified, per square
foot
3,000
3,955.21
955.21
$3.95
$3;773.08
13. Construct approx. 750
square feet of 6" thick
concrete sidewalk in Water
Dept. repair locations at
approx. 20 sites, complete
as specified, per square
foot
750
989.06
239.06
$4.10
$980.15
14. Approx. 100 square yards
of 7" non-reinforced
concrete pavement
removai and replacement,
including sawing, ~
pavement ties; integral
curb & grading,terracing &
traffic control, complete as
specified, per square yard
100
208.77
108.77
$38.00
$4,133.26
15. Approx. 1,800 square yards
of 8" non-reinforced
concrete pavement
removal and replacement,
including sawing,
pavement ties, integral
curb & grading, terracing &
traffic control, complete as
specified, per square yard
1,800
688.06
-1,111.94
$38.50
($42,809.69
Page 2
CONTRACT: 07-06 CHANGE ORDER # 1
(NCREASEIN DECREASEIN
lTEM CONTRACT INSTALLED NET NET COSTPER CONTRACT CONTR,4CT
NUMBER DESCR/PTlON QUANTITIES QUANTITIES INCREASE DECREASE UN1T pRICE Pf~ICE
16. Approx. 100 square yards
of 8" special High Early
Strength, non-
reinforced concrete
pavement removal and
replacement, including
sawing, pavement ties,
integral curb and grading,
terracing and trafFic control,
complete as specified, per
100
31
11
-88.69
$45.00
$3,991.05)
s uare ard .
17. Approx. 200 tons extra
crushed sfone base,
complete as specified, per
ton
200
51.00
-149.00
$14.00
$2,086.00
18. Approx. 600 linear feet of
No. 4 epoxy-coated
reinforcement rods,
installed as specified, per
linear foot
600
840.00
240.00
$1.50
$360.00
19. Furnish, install and
maintain Type "C" Inlet
protection in approx. 5
locations, complete as
5
00
6
1.00
$85.00
$85.~0
s ecified, each .
20. Approx. 1501inear feet of '
12" wide radius curb head,
compiete as specified, per
ar foot
li
150
116.60
-33.40
$3.00
$100.20)
ne
21. Provide $1,500 to the City
of Oshkosh for project
management
communications, complete
as specified, lump sum $1
00
500
1 1.00 ,
.
BiD ITEMS 1-21 - SUB-T OTAL . $91,095.58 ($54,639.28)
ADDITIONAL WORK REQUIRED: C.O. # 1
JNCREASE fN DECREASE IN
ITEM CONTRACT WSTALLED NET NET COST PER CONTR,4CT C~NTRACT
NUMBER DESCRIPTION QUANTITIES QUANTITlES lNCREASE DECREASE UNIT pRICE i°R1CE
1. Replace 6" curb head at
222 Jackson Street, per
00
1
00
$10
$310.00
lineal foot 0 31 3
. .
2. Clean out rubble from
basement and form base
for sidewalk install.ation at
101 Algoma Blvd. as
1
00
00
1
$570.00
$570.00
s ecified, lum sum 0 . .
3. Erosion control mat, per
77
60
60
77 2,25
~ $174.60
s uare ard 0 . .
Page 3
CONTRACT: 07-06 CHANGE ORDER # 1
INCREASE 1N DECFtEASE !N
ITEM DESCRIPTION CONTRACT
QUANTITIES INSTALLED
QUANTITlES NET
/NCREASE NET
DECREASE COST PER
UNIT CONTRACT
pR1CE CONTRACT
PR1CE
NUMBER
4. Replace 4" asphalt, per
s uare foot 0 977.85 977.85 $4.27 $4,175.42
5. Construct 8" sidewalk,
complete as specified, per
s uare foot 0 885.00 885.00 $4.72 $4,177.20
6. 7-Bag mix concretel8", per
s uare ard 0 432.55 432.55 $42.50 $18,383.38
7. 7-Bag mix concrete/9", per
s uare ard 0 27.01 27.01 $47.50 $1,282.98
ADDITIONAL WORK: C.O, # 1-(ITEMS 1- 7) - SUB-TOTAL
NETiNCREASE-
$29,073.58
$65,529.88
$0.00
NET INCREASE TO CONTRACT:
• $65,529.88
Page 4