HomeMy WebLinkAboutPW CNT 06-05/Cng Ord #1
,-,,1
~~~, ,\
CHANGE ORDER # 1
DATED: September 15, 2006
TO: LaLonde Contractors, Inc.
P. O. Box 070420
Milwaukee, WI 53207-0420
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
06-05 , is hereby amended
NET INCREASE TO: ADDITIONAL WORK: SECTION I
NET INCREASE TO: ADDITIONAL WORK: SECTION IV
$4,654.92
$101,471.09
NET INCREASE TO CONTRACT:
$106,126.01
h<.vJ c.. ~L
Director of Pu lic Works
Recommended:
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
~Ql i.})~ Q (;~
Comptroller
~/
. ,~ "-
\
"
CONTRACT: 06-05 CHANGE ORDER # 1
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION I
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
1 Furnish and install a ten
(10) day detour with
changeable message
board for Algoma
Boulevard, complete as
specified, lump sum 1.00 1.00 $922.50 $922.50
2 Seventy percent of rental
cost for 2 changeable
message boards for
Harrison St. detour @
Nevada Avenue, 6 days,
lumo sum 1.00 1.00 $1,225.00 $1,225.00
3 Saw and remove curb
head for curb ramps @ two
(2) locations, lump sum 1.00 1.00 $537.50 $537.50
4 Slip form curb and gutter
on north side of Algoma
Boulevard, oer linear foot 1,152.00 1,152.00 $1.71 $1,969.92
NET INCREASE TO SECTION I -
$4,654.92
$4,654.92
$0.00
ADDITIONAL WORK: C.O. # 1 - (ITEMS 1 - 4) - SUB-TOTAL
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION IV
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
1 Relay new 8" water main (Fulton Avenue - N. Main St. to Grand St.)
Relay new 6" water main (Fulton Avenue - Grand St. to Railroad)
1A Relay 1,180 linear ft. of 8"
water main, oer linear ft. 1,180.00 1,180.00 $64.26 $75,826.80
1B Relay 260 linear ft. of 6"
water main, oer linear ft. 260.00 260.00 $64.26 $16,707.60
1C Install two (2) 6" valves,
each 2.00 2.00 $754.65 $1,509.30
10 Install six (6) 8" valves,
each 6.00 6.00 $922.50 $5,535.00
1E Install one (1) Hydrant,
each 1.00 1.00 $1,892.39 $1,892.39
ADDITIONAL WORK: C.O. # 1 (ITEMS 1A -1F) - SUB-TOTAL $101,471.09 $0.00
$101,471.09
NET INCREASE TO SECTION IV -
$106,126.01
NET INCREASE TO CONTRACT:
Page 1