HomeMy WebLinkAboutPolice Dept Remodel Chg Ord #1 ,.' i.. Potter Lawson Contract Change Order 15 Ellis Potter Court P.O. Box 44964 Madison, WI 53744-4964 Project: Oshkosh Police Department Remodeling 608/274-2741 608/274-3674 (FAX) Project No.: 2004.17.00 1/11/2006 To Contractor: Fluor Brothers Date Issued: Contract For: All Work Contract Date: DESCRIPTION OF THE WORK, STATEMENT OF NECESSITY, AND SOURCE OR REQUEST (If work started, state reason, date and person authorizing) The following shall be provided subject to the requirements of the contract and bond already executed the same as if herein repeated. Furnish all labor, materials, tools, equipment and transportation required to complete the following item(s) of work. 1. Add 3 & 4 way electrical switches in first floor corriodor area. Reference proposal request #2 for additional detail. 2. Revise building fire alarm system as recommended by Simplex. Reference proposal request #3 for additional detail. 3. Demo and replace carpeting in rooms 130 & 131. Reference proposal request #4 for additional detail. ~ hereby ;lE;cessary provisions have been made to pay tl18 liability which will accrue under this contract. ~+L~ 0 l~ City Comptroller APPROVED The Original Contract Sum was.............................................................................................. Net Change by Previously Authorized Change Orders.............................,................................................... The Contract Sum prior to this Change Order was..................................................................... The Contract Sum will be increased by this Change Order......................... The New Contract Sum including this Change Order will be........................................................ The Contract Time will be unchanged by.................................................. The Date of Substantial Completion as of the date of this Change Order therefore is....................................... CO# []I] RECI:IVED JAN 1 6 2006 f.otter JAwson ~,""" Sep-OS AMOUNT $1 ,932.00 $20,556.00 $595.00 $ $ $ $ $ 23,083.00 597,000.00 0.00 597,000.00 23,083.00 620,083.0Q Q Day!] CE: ARt;;;)~;;:~ (~gnature) . Signature) Richard A. l<<>11angk, City ~. -~ -.2e1p? DATE~7?t'. '-. Q:\MASTERS\Caforms\CO FORM .xls ---- Potter Lawson Proposal Request PR# 02 15 Ellis Potter Court P.O. Box 44964 Madison, WI 53744-4964 608/274-2741 Fax/274-3674 To: Fluor Brothers Construction Co. Inc Date of Issuance: December 14,2005 Contract Date: September 28, 2005 Contract for: General Construction Project Name: City of Oshkosh Police Department Renovation and City Hall and Water Treatment Facility Security Upgrades Project No.: 2004.17.01 Please submit an itemized quotation for changes in the Contract Sum and/or Time incidental to proposed modifications to the Contract Documents described herein. This is not a Change Order nor a direction to proceed with the work described herein. Description: Revise Light Switching in Hallways 138 & 126. 02-01: Revise location of existing light switches in hallways 138 & 126. Add, as necessary, 3 and 4 way switches to accommodate access to light switches at the entry and exit to the hallways noted. Note locations were discussed with electrical contractor following the 11/15/05 progress meeting. Architect: Potter Lawson, Inc. By: P:\2004\2004.17 .OO\Construction\Proposal_Requests\Fluor PR#2.12.14.05.doc Page 1 of 1 Gary McLean From: Richard Paulsen [rjp@f1uorbro.com] Sent: Friday, December 16, 2005 8:01 AM To: garym@potterlawson.com Subject: Oshkosh Police Change Order Request PR#2 Gary This is the cost for PR#2 revised light switching in hallways 136 & 126. If you have any questions, please give me a call.Let me know as soon as possible.The back up for qwest will be faxed to you. Qwest Electric------------------------- $1680.00 Fluor mark up-----------------------------$252.00 Total _______________________________~_______$1932.00 Thank you Richard Paulsen 1/12/2006 Potter Lawson Proposal Request PR# 03 15 Ellis Potter Court P.O. Box 44964 Madison, WI 53744-4964 608/274-2741 Fax/27 4-367 4 To: Fluor Brothers Construction Co. Inc Date of Issuance: December 14,2005 Contract Date: September 28, 2005 Contract for: General Construction Project Name: City of Oshkosh Police Department Renovation and City Hall and Water Treatment Facility Security Upgrades Project No.: 2004.17.01 Please submit an itemized quotation for changes in the Contract Sum and/or Time incidental to proposed modifications to the Contract Documents described herein. This is not a Change Order nor a direction to proceed with the work described herein. Description: Owner Requested Revisions to Fire Alarm System per the Simplex/Grinnell Proposal 12/12/05. 03-01: Revise/Replace existing fire alarm devices to accommodate Owner request for additionally protected area. Reference Simplex/Grinnell proposal dated 12/12/05 for additional detail. (Copy Attached). Architect: Potter Lawson, Inc. By: P:\2004\2004.17 .00\Construction\Proposal_Requests\Fluor PR#3.12.14.05.doc Page 1 of 1 .\ . .< Gary McLean From: Richard Paulsen [rjp@f1uorbro.com] Sent: Friday, December 16, 2005 8:15 AM To: garym@potterlawson.com Subject: Oshkosh Police Department PR#3 Gary This is the cost for PR#3. I will fax you the back up for Qwest Electric for the fire alarm system that was requested. Qwest ---------------------$17,875.00 FI uor ------------------------$2,681 .25 T otal-----------------------$20 ,556 .25 Thank you Richard Paulsen 1/1212006 l o . " . Potter Lawson Proposal Request PR# 04 15 Ellis Potter Court P.O. Box 44964 Madison, WI 53744-4964 608/274-2741 Fax/27 4-367 4 To: Fluor Brothers Construction Co. Inc Date of Issuance: December 14,2005 Contract Date: September 28,2005 Contract for: General Construction Project Name: City of Oshkosh Police Department Renovation and City Hall and Water Treatment Facility Security Upgrades Project No.: 2004.17.01 Please submit an itemized quotation for changes in the Contract Sum and/or Time incidental to proposed modifications to the Contract Documents described herein. This is not a Change Order nor a direction to proceed with the work described herein. Description: Remove & Replace Flooring in Rooms 130 & 131 04-01: Remove & dispose of existing carpet and base in rooms 130 & 131. 04-02: Provide F1 floor finish (carpet) and B3 vinyl base in the above noted rooms. Architect: Potter Lawson, Inc. By: P:\2004\2004.17.00\Construction\Proposal_Requests\FluOr PR#4.12.14.05.doc Page 1 of 1 'I .1 ~'" . ~ y.#~.." Gary McLean From: Richard Paulsen [rjp@f1uorbro.com] Sent: Friday, December 16, 2005 9:41 AM To: garym@potterlawson.com Subject: Oshkosh Police Department Gary This is the cost to furnish and install carpet and base in room 131. The hallway 130 was included in contract and in room finish schedule. Hughs f1ooring----------$517 .00 Fluor _______________________$77 .55 T otal-----------------------$594. 55 Thank you Richard Paulsen 1/12/2006