Potter Lawson
Contract Change Order
15 Ellis Potter Court
P.O. Box 44964
Madison, WI 53744-4964
Project:
Oshkosh Police Department Remodeling
608/274-2741
608/274-3674 (FAX)
Project No.: 2004.17.00
1/11/2006
To Contractor:
Fluor Brothers Date Issued:
Contract For:
All Work Contract Date:
DESCRIPTION OF THE WORK, STATEMENT OF NECESSITY, AND SOURCE OR REQUEST
(If work started, state reason, date and person authorizing)
The following shall be provided subject to the requirements of the contract and bond already executed the same as if
herein repeated. Furnish all labor, materials, tools, equipment and transportation required to complete the following
item(s) of work.
1. Add 3 & 4 way electrical switches in first floor corriodor area. Reference proposal request #2 for
additional detail.
2. Revise building fire alarm system as recommended by Simplex. Reference proposal request #3 for
additional detail.
3. Demo and replace carpeting in rooms 130 & 131. Reference proposal request #4 for additional detail.
~ hereby ;lE;cessary provisions
have been made to pay tl18 liability which will
accrue under this contract.
~+L~ 0 l~
City Comptroller
APPROVED
The Original Contract Sum was..............................................................................................
Net Change by Previously Authorized Change Orders.............................,...................................................
The Contract Sum prior to this Change Order was.....................................................................
The Contract Sum will be increased by this Change Order.........................
The New Contract Sum including this Change Order will be........................................................
The Contract Time will be unchanged by..................................................
The Date of Substantial Completion as of the date of this Change Order therefore is.......................................
CO# []I]
RECI:IVED
JAN 1 6 2006
f.otter JAwson
~,"""
Sep-OS
AMOUNT
$1 ,932.00
$20,556.00
$595.00
$
$
$
$
$
23,083.00
597,000.00
0.00
597,000.00
23,083.00
620,083.0Q
Q
Day!]
CE:
ARt;;;)~;;:~
(~gnature) .
Signature)
Richard A. l<<>11angk, City ~.
-~ -.2e1p?
DATE~7?t'.
'-.
Q:\MASTERS\Caforms\CO FORM .xls
----
Potter Lawson
Proposal Request PR# 02
15 Ellis Potter Court
P.O. Box 44964
Madison, WI 53744-4964
608/274-2741
Fax/274-3674
To:
Fluor Brothers
Construction Co. Inc
Date of Issuance: December 14,2005
Contract Date:
September 28, 2005
Contract for:
General Construction
Project Name:
City of Oshkosh Police
Department Renovation
and City Hall and Water
Treatment Facility
Security Upgrades
Project No.:
2004.17.01
Please submit an itemized quotation for changes in the Contract Sum and/or Time incidental to
proposed modifications to the Contract Documents described herein.
This is not a Change Order nor a direction to proceed with the work described herein.
Description: Revise Light Switching in Hallways 138 & 126.
02-01: Revise location of existing light switches in hallways 138 & 126. Add, as necessary, 3 and 4 way switches
to accommodate access to light switches at the entry and exit to the hallways noted. Note locations were discussed
with electrical contractor following the 11/15/05 progress meeting.
Architect: Potter Lawson, Inc.
By:
P:\2004\2004.17 .OO\Construction\Proposal_Requests\Fluor PR#2.12.14.05.doc
Page 1 of 1
Gary McLean
From: Richard Paulsen [rjp@f1uorbro.com]
Sent: Friday, December 16, 2005 8:01 AM
To: garym@potterlawson.com
Subject: Oshkosh Police Change Order Request PR#2
Gary
This is the cost for PR#2 revised light switching in hallways 136 & 126. If you have any questions, please give me
a call.Let me know as soon as possible.The back up for qwest will be faxed to you.
Qwest Electric------------------------- $1680.00
Fluor mark up-----------------------------$252.00
Total _______________________________~_______$1932.00
Thank you
Richard Paulsen
1/12/2006
Potter Lawson
Proposal Request PR# 03
15 Ellis Potter Court
P.O. Box 44964
Madison, WI 53744-4964
608/274-2741
Fax/27 4-367 4
To:
Fluor Brothers
Construction Co. Inc
Date of Issuance: December 14,2005
Contract Date:
September 28, 2005
Contract for:
General Construction
Project Name:
City of Oshkosh Police
Department Renovation
and City Hall and Water
Treatment Facility
Security Upgrades
Project No.:
2004.17.01
Please submit an itemized quotation for changes in the Contract Sum and/or Time incidental to
proposed modifications to the Contract Documents described herein.
This is not a Change Order nor a direction to proceed with the work described herein.
Description: Owner Requested Revisions to Fire Alarm System per the Simplex/Grinnell
Proposal 12/12/05.
03-01: Revise/Replace existing fire alarm devices to accommodate Owner request for additionally protected area.
Reference Simplex/Grinnell proposal dated 12/12/05 for additional detail. (Copy Attached).
Architect: Potter Lawson, Inc.
By:
P:\2004\2004.17 .00\Construction\Proposal_Requests\Fluor PR#3.12.14.05.doc
Page 1 of 1
.\
. .<
Gary McLean
From: Richard Paulsen [rjp@f1uorbro.com]
Sent: Friday, December 16, 2005 8:15 AM
To: garym@potterlawson.com
Subject: Oshkosh Police Department PR#3
Gary
This is the cost for PR#3. I will fax you the back up for Qwest Electric for the fire alarm system that was
requested.
Qwest ---------------------$17,875.00
FI uor ------------------------$2,681 .25
T otal-----------------------$20 ,556 .25
Thank you
Richard Paulsen
1/1212006
l
o .
" .
Potter Lawson
Proposal Request PR# 04
15 Ellis Potter Court
P.O. Box 44964
Madison, WI 53744-4964
608/274-2741
Fax/27 4-367 4
To:
Fluor Brothers
Construction Co. Inc
Date of Issuance: December 14,2005
Contract Date:
September 28,2005
Contract for:
General Construction
Project Name:
City of Oshkosh Police
Department Renovation
and City Hall and Water
Treatment Facility
Security Upgrades
Project No.:
2004.17.01
Please submit an itemized quotation for changes in the Contract Sum and/or Time incidental to
proposed modifications to the Contract Documents described herein.
This is not a Change Order nor a direction to proceed with the work described herein.
Description: Remove & Replace Flooring in Rooms 130 & 131
04-01: Remove & dispose of existing carpet and base in rooms 130 & 131.
04-02: Provide F1 floor finish (carpet) and B3 vinyl base in the above noted rooms.
Architect: Potter Lawson, Inc.
By:
P:\2004\2004.17.00\Construction\Proposal_Requests\FluOr PR#4.12.14.05.doc
Page 1 of 1
'I .1 ~'" . ~ y.#~.."
Gary McLean
From: Richard Paulsen [rjp@f1uorbro.com]
Sent: Friday, December 16, 2005 9:41 AM
To: garym@potterlawson.com
Subject: Oshkosh Police Department
Gary
This is the cost to furnish and install carpet and base in room 131. The hallway 130 was included in contract and
in room finish schedule.
Hughs f1ooring----------$517 .00
Fluor _______________________$77 .55
T otal-----------------------$594. 55
Thank you
Richard Paulsen
1/12/2006