HomeMy WebLinkAboutPW CNT 05-06/Cng Ord #1 CHANGE ORDER # 1 Dated: December 1, 2005 TO: Fischer-Ulman Construction, Inc. 1115 S. Theodore Street Appleton, WI 54915 Your present contract with the City of Oshkosh, Contract No. and changed as follows: 05-06 , is hereby amended NET INCREASE TO SECTION 1- SIDEWALK REHAB: $33,782.95 NET INCREASE TO CONTRACT: $33,782.95 CITY OF OSHKOSH Recommended: b~Jc, Director of Publi Approved and accepted: U/~.~a" Contractor I certify that provision has been made to pay the liability that will accrue to .the City of Oshkosh, Wisconsin, under the within Change Order. ~fl~ Q...f/~o~ Comptroller CONTRACT: 05-06 CHANGE ORDER # 1 SECTION I - SIDEWALK REHAB ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN DESCRIPTION CONTRACT CONTRACT NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 1 Approx. 71,000 square feet of sidewalk removal & driveway removal, complete as specified, per ($767.06) square foot 71,000.00 68,443.13 -2,556.87 $0.30 2 Approx. 4,000 linear feet of concrete/asphalt sawing, complete as specified, per linear foot 4,000.00 6,716.60 2,716.60 $2.60 $7,063.16 3 Construct approx. 78,500 square feet of 4" thick concrete sidewalk in various locations in the City of Oshkosh, complete as specified, per square foot ($636.86) 78,500.00 78,233.53 -266.47 $2.39 4 Approx. 150 square feet of brick paver restoration at six (6) sites on 400 block of N. Main Street (brick pavers to be supplied by ($1,950.00) citv), oer square foot 150.00 -150.00 $13.00 5 Construct approx. 20,400 square feet of 6" thick concrete sidewalk in various locations in the City of Oshkosh, complete as specified, per square foot 20,400.00 15,255.80 -5,144.20 $2.96 ($15,226.83) 6 Construct approx. 2,500 square feet of 6" thick textured concrete wheel chair ramps, complete as soecified oer square foot 2,500.00 3,691.22 1,191.22 $3.60 $4,288.39 7 Approx. 2,500 square feet of three (3") inch asphalt replacement, complete as soecified, oer square foot 2,500.00 948.80 -1,551.20 $3.00 ($4,653.60) 8 Approx. 250 linear feet of curb and gutter removal, complete as specified, per linear foot 250.00 156.90 -93.10 $4.00 ($372.40) 9 Approx. 300 linear feet of 30" curb and gutter, complete as specified, per linear foot 300.00 279.40 -20.60 $15.80 ($325.48) 10 Approx. 1,000 square yards of terrace restoration, including seed, fertilize, and mulch, complete as specified, per square yard 1,000.00 2,072.10 1,072.10 $3.50 $3,752.35 Page 1 CONTRACT: 05-06 CHANGE ORDER # 1 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 11 Furnish and install approx. 50 pavement ties, complete as specified, each 50.00 70.00 20.00 $7.00 $140.00 12 Construct approx. 4,000 square feet of 4" thick concrete sidewalk in Water Dept. repair locations at approx. 60 sites, complete as specified, per square foot 4,000.00 3,198.67 -801.33 $3.85 ($3,085.12) 13 Construct approx. 1,000 square feet of 6" thick concrete sidewalk in Water Dept. repair locations at approx. 20 sites, complete as specified, per square foot 1,000.00 1,069.09 69.09 $3.95 $272.91 14 Approx. 100 square yards of 7" non-reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, complete as specified, per square yard 100.00 78.53 -21.47 $37.30 ($800.83) 15 Approx. 1,500 square yards of 8" non-reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, complete as specified, per square yard 1,500.00 349.26 -1,150.74 $38.90 ($44,763.79) 16 Approx. 700 square yards of 8" special High Early Strength, non- reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb and grading, terracing and traffic control, complete as specified, per SQua 700.00 65.59 -634.41 $42.00 ($26,645.22) 17 Approx. 250 tons extra crushed stone base, complete as specified, per ton 250.00 290.74 40.74 $10.50 $427.77 Page 2 CONTRACT: 05-06 CHANGE ORDER # 1 . ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE 'UNIT CONTRACT CONTRACT PRICE PRICE 18 Approx. 1,200 linear feet of No.4 epoxy-coated reinforcement rods, installed as specified, per linear foot 1,200.00 800.00 -400.00 $1.35 ($540.00) 19 Provide $1,500 to the City of Oshkosh for project management communications, complete as specified, lump sum 1.00 1.00 $1,500.00 SECTION 1- (BID ITEMS 1 -19) - SUB-TOTALS $15,944.58 ($99,767.19) ADDlTONAL WORK REQUIRED: C.O. # 1 - SECTION I ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 1 7"/7 bag non- reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, complete as specified, per squareyard 110.29 110.29 $38.90 $4,290.28 2 8"/7 bag non- reinforced concrete " pavement removal and replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, complete as specified, per square yard 1,074.74 1,074.74 $40.45 $43,473.23 Page 3 CONTRACT: 05-06 CHANGE ORDER #'1 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 3 9"/6 bag non- ... reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, complete as specified, per square yard 24.80 24.80 $43.00 $1,066.40 4 9"/7 bag non- reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, complete as specified, per square yard 89.31 89.31 $44.00 $3,929.64 5 9"/9 bag non- reinforced concrete pavement removal and . replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, complete as specified, per square yard . 59.18 59.18 $45.00 $2,663.10 6 Brick mortar mahhole, lump sum 1.00 1.00 $100.00 $100.00 7 Construct 7" thick concrete sidewalk in various locations in the City of Oshkosh, complete as specified, per square foot 1,822.60 1,822.60 $3.46 $6,306.20 8 Repair misc. PVC sumps, lump sum 1.00 1.00 $100.00 $100.00 Page 4 CONTRACT: 05-06 CHANGE ORDER # 1 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRipTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT . CONTRACT CONTRACT . PRICE PRICE 9 Placement of two (2) castings at 509 Washburn Street, lump sum 1.00 1.00 $50.00 $50.00 10 Erosion mat on Washburn Street, per square vard 1,055.20 1,055.20 $2.50 $2,638.00 11 Filling, compacting services on backs lope area of Washburn Street/Witzel Avenue, I per hour 10.00 10.00 $105.00 $1,050.00 12 Inlet protection on Washburn Street, each 16.00 16.00 $30.00 $480.00 13 Miscellaneous apron installation services re: Contract 05-09, per square foot 17,384.70 17,384.70 $2.96 $51,458.71 NET INCREASE TO SECTION I - $117,605.56 NET INCREASE TO SECTION I NET DECREASE TO SECTIONS I, II, III, IV $133,550.14 ($99,767.19) NET INCREASE TO CONTRACT: $33,782.95 Page 5