HomeMy WebLinkAboutPERMISSION TO START CONSTRUCTION
Safety and Buildings
2331 SAN LUIS PL STE 150
GREEN BAY WI 54304
TDD #: (608) 264-8777
www.commerce.wi.gov/sb/
www.wisconsin.gov
'~
Jim Doyle, Governor
Mary P. Burke, Secretary
October 31,2005
CUST ill No. 646685
ATTN: Buildings & Structures Inspector
MARK C ROHLOFF
UTSCHIG IMPERIAL BUILDING SYSTEMS
N1040 CRAFTSMAN DR
GREENVILLE WI 54942
BUILDING INSPECTION
CITY OF OSHKOSH
POB 1130
OSHKOSH WI 54902
PERMISSION TO START CONSTRUCTION
SITE:
Orion Flight Services
3418 Park Drive
City of Oshkosh
FOR:
Object Type: Building ICC Regulated Object ill No.: 1043135
Major Occupancy: Storage; Type lIB Metal Frame Unprotected class of construction; New plan; 12,000 project sq ft;
Occupancy: S-I Storage Moderate-Hazard
The Department of Commerce has received construction plans for review for the subject project, submitted in
accordance with the provisions ofComm 61.32, accompanied by the owner's request to begin construction work on
the Footings and Foundations prior to Departmental review and approval.
This letter will serve as the department's permission to the local building officials to allow construction of the
Footings and Foundations, only, for the subject project prior to review and approval by this department
NO REVIEW OF THE SUBMITTED DOCUMENTS HAS BEEN UNDERTAKEN BY THE
DEPARTMENT AT THIS TIME FOR CODE COMPLIANCE.
In accordance with the provisions of the owner's signed request to begin construction prior to departmental review
and approval, the owner will be required to make any changes after the plans have been reviewed, and to remove or
replace non-code complying parts of the foundations and/or footings.
Prior to the start of construction, all applicable building permits should be obtained from the local authorities having
jurisdiction in accordance with local laws and ordinances Nothing in this approval limits the power of municipalities
to make, or enforce, additional or more stringent regulations, providing the regulations do not conflict with this code
or any other rule of the department, or law.
DEPARTMENT CONDITIONS
I. If this project is in an unsewered area, a sanitary permit must be obtained prior to the issuance of a local building
permit.
2. This permission is only for footing and foundation work. Construction of the remainder of the building shall not
take place prior to departmental review and conditional approval of the construction plans.
3. If this construction project will disturb one or more acres ofland, an Erosion Control Notice of Intent (NO!)
shall be filed with the department
4. This "Permission to Start" does not include permission to install any underground plumbing, including
sanitary/storm sewers, or water or mains. All projects needing submittal per Comm Tables 82.20-1&2 must
..
MARK C ROHLOFF
Page 2
10/31/2005
have complete plumbing plans, application, & fees submitted and approved prior to commencement of any
plumbing work.
Inquiries concerning this correspondence may be made to me at the telephone number listed below, or at the address
on this letterhead. Please refer to Transaction ID No. referred to in the regarding line when making an inquiry or
submitting additional information.
Sincerely,
Vicky L Brennan
Customer Service Representative, Integrated Services
Mon. - Fri. 8:00 a.Ill. - 3:00 p.Ill.
vbrennan@commerce.state.wi.us
cc: Peter R Ochs, Building Inspector, (920) 948-3500 , Friday, 7:45 A.M. - 4:30 P.M.
Jeff Wanke, Orion Flight Services