HomeMy WebLinkAboutPW CNT 04-09/Cng Ord #1 CJy (!L~-J/,,- CHANGE ORDER # 1 DATED: May 16, 2005 TO: Ripon Lime & Materials Inc. 1110 Dartford Road Ripon, WI 54971 Your present contract with the City of Oshkosh, Contract No. and changed as follows: 04-09 , is hereby amended NET INCREASE TO SECTION I - GRADING & GRAVELING: NET DECREASE TO SECTION II - STORM SEWER: NET DECREASE TO SECTION III - SANITARY SEWER: NET INCREASE TO SECTION IV - WATER MAIN: NET DECREASE TO SECTION V - EROSION CONTROL/STORMWATER: $880.00 ($3,663.28) ($2,214.24) $7,110.81 $2,386.17 NET ~TO CONTRACT: :lNC..R~t..s~ $4,499.46 BY: Recommended: ~o,~:J c. I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. ?QA~ a~ Comptroller CONTRACT: 04-09 CHANGE ORDER # 1 SECTION I - GRADING & GRAVELING ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 1 Excavation for roadway 10,300 cubic yards, complete as specified per cubic yard 10,300.00 10,300.00 $1.90 2 Furnish and install 1 0,500 tons of crushed stone base course, complete as soecified, oer ton 10,500.00 10,500.00 $7.45 3 19 ton Asphaltic Concrete Pavement, Type E1, per ton 19.00 27.00 8.00 $110.00 $880.00 4 Terrace work on Fernau Avenue (Sta 1 +00 to Vinland Street) and Fernau Court, lumo sum 1.00 1.00 $16,000.00 5 Provide $375.00 to the City of Oshkosh for project management communications, complete as specified, lump sum 1.00 1.00 $375.00 SECTION I - (BID ITEMS 1 - 5) - SUB-TOTALS $880.00 $0.00 $880.00 NET INCREASE TO SECTION I - SECTION II - STORM SEWER ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 6 Furnish and install 444 linear feet of 12" RCP CL III or PVC w/gravel backfill, oer linear foot 444.00 488.92 44.92 $33.00 $1,482.36 7 Furnish and install 265 linear feet of 15" RCP CL III or PVC w/gravel backfill, oer linear foot 265.00 267.06 2.06 $34.50 $71.07 8 Furnish and install 210 linear feet of 18" RCP CL III or PVC w/gravel backfill, I oer linear foot 210.00 188.08 -21.92 $42.00 ($920.64 ) 9 Furnish and install 17 linear feet of 18" RCP CL III or PVC w/natural backfill, oer linear foot 17.00 17.00 $38.00 Page 1 CONTRACT: 04-09 CHANGE ORDER # 1 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 10 Furnish and install 316 linear feet of 21" RCP CL III w/gravel backfill, per linear foot 316.00 315.61 -0.39 $44.50 ($17.35) 11 Furnish and install 358 linear feet of 24" RCP CL III w/gravel backfill, per linear foot 358.00 355.50 -2.50 $49.75 ($124.38' 12 Furnish and install 69 linear feet of 24" RCP CL III w/natural backfill, per linear foot 69.00 69.00 $43.00 13 Furnish and install 633 linear feet of 27" RCP CL III w/gravel backfill, per linear foot 633.00 636.22 3.22 $46.00 $148.12 14 Furnish and install 18 linear feet of 30" RCP CL III wig ravel backfill, per linear foot 18.00 18.00 $51.00 15 Furnish and install 47 linear feet of 30" RCP CL III w/natural backfill, per linear foot 47.00 44.33 -2.67 $59.00 ($157.53) 16 Furnish and install 448 linear feet of 36" RCP CL III wig ravel backfill, per linear foot 448.00 462.36 14.36 $73.00 $1,048.28 17 Furnish and install 405 linear feet of 42" RCP CL III wig ravel backfill, per linear foot 405.00 388.73 -16.27 $78.00 ($1,269.06) 18 Furnish and install 87 linear feet of 42" RCP CL III w/natural backfill, per linear foot 87.00 87.00 $71.50 19 Furnish and install 50 linear feet of 18" CMCP w/gravel backfill, per linear foot 50.00 50.00 $30.00 20 Furnish and install 18 Type 3 Std. Inlet, each 18.00 18.00 $1,005.00 21 Furnish and install 25 vertical feet of 4' dia Storm Manhole w/casting, per vertiacl foot 25.00 22.96 -2.04 $295.00 ($601.80) 22 Furnish and install 27 vertical feet of 5' dia Storm Manhole w/casting, per vertical foot 27.00 24.51 -2.49 $335.00 ($834.15) 23 Furnish and install 18 vertical feet of 6' dia or Box Storm Manhole w/casting, I oer vertical foot 18.00 11.50 -6.50 $410.00 ($2,665.00) Page 2 CONTRACT: 04-09 CHANGE ORDER # 1 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 24 Furnish and install 20 vertical feet of 8' dia or Box Storm Manhole w/casting, oer vertical foot 20.00 20.34 0.34 $520.00 $176.80 25 Furnish and install two (2) 24" RCP Endwall, each 2.00 2.00 $550.00 26 Furnish and install one (1) 30" RCP Endwall, each 1.00 1.00 $630.00 27 Furnish and install one (1) 42" RCP Endwall, each 1.00 1.00 $1,070.00 28 Furnish and install one (1) 18" CMCP Endwall, each 1.00 1.00 $130.00 29 Install one (1) 15" RCP connection to existing structure, each 1.00 1.00 $410.00 30 Provide $375.00 to the City of Oshkosh for project management communications, complete as specified, lump sum 1.00 1.00 $375.00 NET DECREASE TO SECTION II - $2,926.63 ($6,589.91) ($3,663.28) SECTION II - (BID ITEMS 6 - 30) - SUB-TOTALS SECTION 11I- SANITARY SEWER ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 31 Furnish and install 2,187 linear feet of 8" PVC Sanitary Sewer wig ravel backfill, per linear foot 2,187.00 2,162.20 -24.80 $52.44 ($1,300.51) 32 Furnish and install 50 linear feet of 10" PVC Sanitary Sewer wig ravel backfill, per linear foot 50.00 52.00 2.00 $61.00 $122.00 33 Furnish and install 40 linear feet of 12" PVC Sanitary Sewer wig ravel backfill, per linear foot 40.00 40.00 $200.00 34 Furnish and install 2,559 linear feet of 12" PVC Sanitary Sewer w/natural backfill, per linear foot 2,559.00 2,566.71 7.71 $43.85 $338.08 35 Furnish and install eight (8) linear feet of 12 PVC Sanitary Sewer Sliplined in existing 15" Sanitary Sewer, oer linear foot 8.00 0.00 -8.00 $151.00 ($1,208.00) Page 3 CONTRACT: 04-09 CHANGE ORDER # 1 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 36 Furnish and install 33 linear feet of 6" PVC Sanitary Sewer Service Laterals, open trench, per linear foot 33.00 33.00 $31.00 37 Furnish and install one (1) 8" x 6" Sanitary Sewer Service Branches, each 1.00 1.00 $60.00 38 Furnish and install 173 vertical feet of 4' Diameter Standard Manhole, per vertical foot 173.00 171.75 -1.25 $171.00 ($213.75) 39 Furnish and install 8.1 vertical feet of 4' diameter Standard Manhole over existing 8" Sanitary and 6" FM w/inside drop, per vertical foot 8.10 8.11 0.01 $300.00 $3.00 40 Furnish and install 63 vertical feet of 4' Diameter Standard Manhole w/outside drop, per vertical foot 63.00 63.14 0.14 $321.00 $44.94 41 Terrace work on Sanitary Sewer Construction (Vinland Street to Jackson Street), complete as specified, lump sum 1.00 1.00 $13,000.00 42 Provide $375.00 to the City of Oshkosh for project management communications, complete as specified, lump sum 1.00 1.00 $375.00 NET INCREASE TO SECTION III - $508.02 ($2,722.26) ($2,214.24) SECTION III - (BID ITEMS 31 - 42) - SUB-TOTALS SECTION IV - WATER MAIN ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 43 Furnish and install 30 linear feet of 6" Ductile Iron Water Main w/gravel backfill and polywrap, per linear foot 30.00 28.00 -2.00 $41.00 ($82.00) Page 4 CONTRACT: 04-09 CHANGE ORDER # 1 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 44 Furnish and install 666 linear feet of 8" DI Water Main wig ravel backfill and Ipolywrap, per linear foot 666.00 742.00 76.00 $41.20 $3,131.20 45 Furnish and install 41 linear feet of 1 1/2" Water Service, per linear foot 41.00 40.50 -0.50 $35.00 ($17.50) 46 Furnish and install one (1) 1 1/2" Curb Stop, each 1.00 1.00 $300.00 47 Furnish and install one (1) 16" x 6" Tapping Tee w/valve, each 1.00 1.00 $3,210.00 48 Furnish and install one (1) 16" x 8" Tapping Tee w/valve, each 1.00 1.00 $3,400.00 49 Furnish and install one (1) 5' dia. Air Release Manhole with 8" valve, each 1.00 1.00 $2,810.00 50 Furnish and install one (1) 8" x 6" Tee, each 1.00 1.00 $200.00 51 Furnish and install one (1) 8" x 8" Tee, each 1.00 1.00 $215.00 52 Furnish and install four (4) 8" - 45 Degree Bend, each 4.00 4.00 $705.00 53 Furnish and install one (1) 8" Pluq, each 1.00 1.00 $80.00 54 Furnish and install one (1) 6" Valve, each 1.00 1.00 $630.00 55 Furnish and install two (2) 8" Valve, each 2.00 2.00 $780.00 56 Furnish and install one (1) 8" x 6" Reducer, each 1.00 1.00 $125.00 57 Furnish and install three 3) Fire Hvdrants, each 3.00 3.00 $1,530.00 58 Furnish and install 27 square yards of Insulation, per square vard 27.00 0.00 -27.00 $4.25 ($114.75' 59 Adjust one (1) Water Manhole,each 1.00 0.00 -1.00 $500.00 ($500.00) 60 Provide $375.00 to the City of Oshkosh for project management communications, complete as specified, lump sum 1.00 1.00 $375.00 SECTION IV - (BID ITEMS 43 - 60) - SUB-TOTALS $3,131.20 ($714.25) ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION IV Page 5 CONTRACT: 04-09 CHANGE ORDER # 1 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 1 Lower existing 16" water main on Fernau Avenue at Fernau Court for proposed storm sewer, 5/20104 - 5/21/04, lump sum 1.00 1.00 $4,693.86 $4,693.86 ADDITIONAL WORK: C.O. # 1 (ITEM 1) - SUB-TOTAL $4,693.86 $0.00 NET INCREASE TO SECTION IV - $7,110.81 SECTION V - STORMWATER MANAGEMENT ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 61 Construct 1,100 linear feet of Stormwater Management Pond Berm, per linear foot 1,100.00 1,062.20 -37.80 $4.50 ($170.10) 62 Construct 234 linear feet of Ditch, per linear foot 234.00 224.40 -9.60 $3.05 ($29.28) 63 Furnish and install 289 square yards of Heavy Riprap, per square yard 289.00 493.10 204.10 $19.00 $3,877.90 64 Furnish and install 289 square yards of Geotextile Fabric, Type "HR", per square yard 289.00 493.10 204.10 $2.50 $510.25 65 Furnish and install 100 square yards of Erosion Control Revegetation Mat, Class I, Type B, per square yard 100.00 176.40 76.40 $4.00 $305.60 66 Furnish and install 11 0 square yards of Provide Erosion Control Revegetation Mat, Class III, per square yard 110.00 0.00 -110.00 $6.00 ($660.00) 67 Furnish, install, and maintain 4,700 linear feet of Silt Fence Erosion Control, per linear foot 4,700.00 4,450.00 -250.00 $1.50 ($375.00) 68 Furnish, install, and maintain 50 Erosion Control Bales, each 50.00 4.00 -46.00 $8.00 ($368.00) 69 Furnish, install and maintain 20 Inlet Erosion Control, Type A, each 20.00 20.00 $75.00 Page 6 CONTRACT: 04-09 CHANGE ORDER # 1 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 70 Furnish, install and maintain two (2) Inlet Erosion Control, Type C, each 2.00 2.00 $50.00 71 Furnish, install, and maintain four (4) Tracking Pad,each 4.00 3.00 -1.00 $500.00 ($500.00) 72 Terrace work on Stormwater Management Facilities (berm, outfalls, spillway), complete as specified, lump sum 1.00 1.00 $6,800.00 73 Furnish and install 90 linear feet of 18" dia. RCP Class III or PVC Storm Sewer w/natural backfill, per linear foot 90.00 84.30 -5.70 $36.00 ($205.20) 74 Furnish and install one (1) 18" RCP Endwall, each 1.00 1.00 $400.00 75 Furnish and install one (1) 24" Standpipe with 10" orifice, each 1.00 1.00 $1,000.00 76 Provide $375.00 to the City of Oshkosh for project management communications, complete as specified, lump sum 1.00 1.00 $375.00 SECTION V - (BID ITEMS 61 - 76) - SUB-TOTALS $4,693.75 ($2,307.58) NET DECREASE TO SECTION V - $2,386.17 NET INCREASE TO SECTIONS I, II, III, IV, V NET DECREASE TO SECTIONS I, II, III, IV, V $16,833.46 ($12,334.00) NET DECREASE TO CONTRACT: $4,499.46 Page 7