CITY OF OSHKOSH
DEPARTMENr OF PUBLIC WORKS
215 Church Aveuue
P.O. Box 1130
Oshkosh, Wisconsin
54903-1130
~
OfHKOfH
ONm,WA'"
(920) 236-5065
November 2,2005
Mr. Michael J. Welch, E.I.T.
Davel Engineering
1811 Racine Street
Menasha, WI 54952
Re: CS Smet Construction Corp Site (545 High Ave)/Drainage, Grading, & Erosion Control
Plan Review
Dear Mr. Welch:
The Drainage, Grading, and Erosion Control Plans (Date: November 1, 2005) for the proposed
CS Smet Construction Parking Lot Reconstruction at 545 High Avenue has been reviewed and
approved. The Contractor should note that if concrete pavement restoration is not completed
prior to the final paving date set by the City of Oshkosh, a temporary asphalt patch will need to
be installed through the winter and the Contractor will need to return in the spring to complete
the concrete pavement restoration.
Sincerely,
Jason Brown
Civil Engineer II
Cc: David C. Patek, Director of Public Works
Scott Erickson, Asst. Director of Public Works
Ed Potempa, Civil Engineer II