JANUARY 10,2006
06-06
RESOLUTION
(CARRIED 7 -0
LOST
LAID OVER
WITHDRAWN
PURPOSE:
CHANGE ORDER NO. 3/ PUBLIC WORKS CONTRACT NO. 03-03
INITIATED BY:
DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
MERIDIAN CONSULTING GROUP
Bonding Agent for James Cape & Sons Co.
40 Corbett Way
Eatontown, NJ 07724
Net decrease to contract:
($120,006.42)
PURPOSE: (See attached Change Order)
CHANGE ORDER # 3
DATED: December 1, 2005
TO: Meridian Consulting Group
Bonding Agent for James Cape & Sons Co.
40 Corbett Way
Eatontown, NJ 07724
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
03-03
, is hereby amended
NET DECREASE TO CONTRACT:
($120,006.42)
($120,006.42)
NET DECREASE TO SECTION I - CONCRETE PAVING:
CITY OF OSHKOSH
BY:
City Manager
Recommended:
City Clerk
Approved and accepted:
~þ~ YJ1~/-/ sll~
Bonding Agent for
James Cape & Sons Co.
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
~
C'
CONTRACT: 03-03 CHANGE ORDER # 3
ADJUSTMENT MADE DUE TO TIE BAR SPACING: C.O. # 3 SECTION I
ITEM CONTRACT INSTALLED NET NET INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE COST PER UNIT CONTRACT CONTRACT
PRICE PRICE
1 Deduct for non-compliance
with tie bar spacing,
various streets, per
contract documents,
lump sum 1.00 1.00 1($120,006.42) ($120,006.42)
NET DECREASE TO CONTRACT
($120,006.42)