HomeMy WebLinkAbout06-08.doc
JANUARY 10,2006
06-08
RESOLUTION
(CARRIED 7 -0
LOST
LAID OVER
WITHDRAWN
PURPOSE:
CHANGE ORDER NO. 2/ PUBLIC WORKS CONTRACT NO. 05-05
INITIATED BY:
DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
VINTON CONSTRUCTION CO
PO Box 1987
Manitowoc, WI 54221-1987
Net increase to contract:
$147,192.20
PURPOSE: (See attached Change Order)
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Accl. No. 315-0410-7480-00000 - Street Improvement Fund Expenditures
Accl. No. 532-1040-7480-03305 - TIF #18 Storm
Accl. No. 541-1810-1799-00000 - Water Utility - Construction in Progress
Accl. No. 551-1910-1799-00000 - Sewer Utility - Construction in Progress
Accl. No. 561-2010-1799-00000 - Storm Water Utility - Construction in Progress
TO: VINTON CONSTRUCTION CO
P. O. BOX 1987
MANITOWOC, WI 54221-1987
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
PART I
NET INCREASE TO SECTION I - CONCRETE PAVING:
NET INCREASE TO SECTION 11- STORM SEWER:
NET INCREASE TO SECTION 111- SANITARY SEWER:
NET INCREASE TO SECTION IV - WATER MAIN:
NET INCREASE TO PART I :
PART II (Southwest Industrial Park. Global Parkway Extension)
NET INCREASE TO SECTION II - STORM SEWER:
NET INCREASE TO SECTION IV - STORMWATER MANAGEMENT:
NET INCREASE TO PART II :
TOTAL INCREASE TO CONTRACT 05-05 (PARTS I & II)
Recommended:
CHANGE ORDER # 2
DATED: 12/22/05
05-05
, is hereby amended
$16,433.96
$56,128.39
$18,065.53
$53,085.42
$143,713.30 '
$291.90
$3,187.00
$3,478.90
$147,192.20
CITY OF OSHKOSH
BY:
City Manager
City Clerk
Approved and accepted:
~þ~
. Contractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Approved as to form:
City Attorney
Comptroller
CONTRACT: 05-05 PART lAND PART II - CHANGE ORDER # 2
ADDITIONAL WORK REQUIRED: C.O. # 2. PART I. SECTION I. CONCRETE PAVING
CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
ITEM DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANT/TIES INCREASE DECREASE UNIT
PRICE ' PRICE
1 Provide and install 6.318
sq. yards Urban, Class I,
Type A, Erosion Mat, per
sa. vard. 6.318.00 6,318.00 $1.92 $12,130.56
2 Saw and remove 40 linear
feet concrete curb in three
(3) locations, per linear foot
40.00 40.00 $26.25 $1.050.00
3 Provide topsoil. fertilize.
seed and mulch 143 sq.
yards terrace area at north
side of Florida St. west of
Delaware, per sq. yard
143.00 143.00 $8.80 $1,258.40
4 Provide. setup and
maintain extra lane closure
on N. Main St. @ Irving
Ave., lumo sum 1.00 1.00 $389.00 $389.00
5 Regrade concrete
driveways at three (3)
locations. lumo sum 1.00 1.00 $343.00 $343.00
6 Extra cost for approx.
210.5 sq. yards of 8" non-
reinforced 9 bag concrete
pavement in lieu of 8" HES
concrete pavement,
including integral curb, 6"
base material and grading,
complete as specified, per
sa. yard. 210.50 210.50 $6.00 $1.263.00
ADDITIONAL WORK: C.O. # 2. (ITEMS 1 .6) . SUB-TOTAL
NET INCREASE TO PART I. SECTION 1 .
$16,433.96
$16,433.96
$0.00
ADDITIONAL WORK REQUIRED: C.O. # 2 . PART I . SECTION II . STORM SEWER
CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
ITEM DESCRIPTION CONTRACT CONTRACT
NUMBER QUANT/TIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
1 Remove and replace flat
top on existing box storm
manhole. W. South Park
Ave. and Georgia St., lump
sum (8/9/05) 1.00 1.00 $895.00 $895.00
Page 1
CONTRACT: 05-05 PART I AND PART II - CHANGE ORDER # 2
2 Pumping and removing
collapsing 36" storm sewer
pipe on Baldwin Ave., lump
sum (8/29/05) 1.00 1.00 $1,537.50 $1,537.50
3 Replace 72 linear feet of
36" RCP storm sewer on
Baldwin Ave. @ $178.00/ft.
72.00 72.00 $178.10 $12.823.20
4 Replace 424 feet of 36".
HDPE storm sewer on
Baldwin Ave. @ $89.20/ft. 424.00 424.00 $89.20 $37,820.80
5 Relay 6" storm lateral at
695 N. Main St., lump sum
(9/8/05) 1.00 1.00 $475.40 $475.40
6 Rebuild storm manhole
and relay 15" storm sewer .... '
at MH 10/285 in the W.
Irving Ave.lN. Main St
intersection, lump sum
10/12/05 - 10/14/05) 1.00 1.00 $2;576.49 $2,576.49
ADDITIONAL WORK: C.O. # 2 . (ITEMS 1 .6) . SUB.TOTAL
NET INCREASE TO PART I. SECTION II.
$56,128.39
$56,128.39
$0.00
ADDITIONAL WORK REQUIRED: C.O. # 2. PART 1- SECTION III. SANITARY SEWER
CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
ITEM DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
1 Install inside drop on
sanitary manhole FK 54 at ,
W. Irving Ave and
Frederick St., lump sum
(8/3/05) 1.00 1.00 $693.00 $693.00
2 Slurry required for ..
abandoning old 24"
sanitary on Franklin St.
and on W. Lincoln Ave..
lump sum, (8/19/05 &
8/24105) Vinton 1.00 1.00 $5.038.50 $5,038.50
3 Replace 32" section of
existing sanitary manhole
at Melvin Ave. & Frederick
St. to abandon old 24"
connection, lump sum
1(8/3/05) 1.00 1.00 $641.00 $641.00
4 Slurry required for
abandoning old 24"
sanitary on Franklin St.,
Scott St. and W. Lincoln
Ave.. lump sum
(8/18/05 - 8/31/05)
Four-Wav Constr. 1.00 1.00 $6.375.00 $6.375.00
Page 2
CONTRACT: 05-05 PART I AND PART II - CHANGE ORDER # 2
5 Provide extra stone for new
18" sanitary sewer on
Baldwin Ave. after
removing old concrete
cradle, lump sum
(9/1/05. 919/05) 1.00 1.00 $560.03 $560.03
6 Relay 6" sanitary lateral
with 8" sanitary lateral at
691 Franklin St., lump
sum, 8/5/05 1.00 1.00 $4,758.00 $4,758.00
ADDITIONAL WORK: C. O. #2. (ITEMS 1.6). SUB.TOTAL
$18,065.53
$0.00
NET INCREASE TO PART I . SECTION III .
$18,065.53
ADDITIONAL WORK REQUIRED: C.O. # 2 . PART I . SECTION IV. WATER MAIN
CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
ITEM DESCRIPTION CONTRACT CONTRACT
NUMBER QUANT/TIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
/".,
1 ADDITIONAL WORK REQUIRED FOR DEMPSEY TRAIL (ITEMS 1A - 18A)
1A Furnish and install 61.5
linear feet of 4" Water
Main, oer linear foot 61.50 61.50 $62.00 $3,813.00
1B Fumish and install 9 linear
feet of 6" Water Main. per
linear foot 9.00 9.00 $70.00 $630.00
1C Furnish and install 524.5
linear feet of 8" Water
Main, oer linear foot , 524.50 524.50 $60.70 $31,837.15
10 Furnish and install one (1)
4" valve. each 1.00 1.00 $354.00 $354.00
1E Furnish and install two (2)
6" Valves. each 2.00 2.00 $660.00 $1,320.00
1F Furnish and install two (2)
8" Valves. each 2.00 2.00 $870.00 $1"740.00
1G Furnish and install one (1)
4" sleeve, each 1.00 1.00 $81.60 $81.60
1H Fumish and install one (1)
6" sleeve, each 1.00 1.00 $110.40 $110.40
11 Furnish and install one (1)
8" x 4" Tee, each 1.00 1.00 $192.00 $192.00
1J Furnish and install one (1)
8" x 6" Tee,each 1.00 1.00 $271.00 $271.00
1K Furnish and install one (1)
4" 1/16 Bend, each 1.00 1.00 $78.00 $78.00
1L Furnish and install two (2)
4" 1/8 Bend. each 2.00 2.00 $80.40 $160.80
1M Furnish and install two (2)
81t 1/8 Bend. each 2.00 2.00 $230.00 $460.00
1N Furnish and install one (1)
8' x 6" Reducer, each 1.00 1.00 $150.00 $150.00
Page 3
CONTRACT: 05-05 PART I AND PART II - CHANGE ORDER # 2
10 Furnish and install one (1)
Hvdrant. each 1.00 1.00 $1,850.00 $1,850.00
1P Extra time to remove
existing 6" valve, extra
stone, lump sum .
'9/22105) 1.00 1.00 $504.05 $504.05
10 Extra time to excavate with
smaller backhoe around
relocated water, Jump sum
(9/23/05) ,
1.00 1.00 $667.00 $667.00
1R Repair unknown 8" storm
sewer. lump sum
1(9/26/05) 1.00 1.00 $334.80 $334.80
ADDITIONAL WORK FOR DEMPSEY TRAIL (ITEMS 1A -1R) SUB.TOTAL
$44,553.80
$0.00
2 Relay 1 1/2" water service
to Wesley Methodist
Church (761 Florida Ave.),
lumo sum (7/6/05) 1.00 1.00 $1,519.00 $1,519.00
3 Repair unknown water
service in Franklin St. and
W. Lincoln Ave.
intersection serving
multiple houses on W.
Lincoln Ave., lump sum
(7/25/05) 1.00 1.00 $476.00 $476.00
4 Repair existing collapsed
24" sanitary sewer on
FranklinSt. due to close
proximity to new 8" water
main,lumo sum (7/25/05) 1.00 1.00 $794.70 $794.70
5 Remove existing tee to
west at Otter St. and
Rosalia Ave. per Jim Wolf,
lumo sum (9/22/05) 1.00 1.00 $579.20 $579.20
6 Insulate existing water
main on Florida Avenue,
lumo sum 1.00 1.00 $5,162.72 $5.162.72
ADDITIONAL WORK: C.O. # 2 (ITEMS 2 - 6) - SUB-TOTAL
NET INCREASE TO PART I . SECTION IV.
$8,531.62 '
$53,085.42
$0.00
NET INCREASE TO PART I . SECTIONS I, II, III, IV
NET DECREASE TO PART 1- SECTIONS I,ll, III, IV
$143,713.30
. $0.00
NET INCREASE TO CONTRACTO5-05 PART I:
$143,713.30
Page 4
CONTRACT: 05-05 PART I AND PART II - CHANGE ORDER # 2
PART II - SOUTHWEST INDUSTRIAL PARK - GLOBAL PARKWAY EXTENSION
ADDITIONAL WORK REQUIRED: C.O. # 2. PART II . SECTION II . STORM SEWER
CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
ITEM DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
1 Delay time when building
storm manhole 05-04 due
to changed finish height
condition. lump sum 1.00 1.00 $291.90 $291.90
ADDITIONAL WORK: C.O. # 2 - (ITEM 1) . SUB-TOTAL
$291.90
$0.00
NET INCREASE TO PART II. SECTION II.
$291.90
ADDITIONAL WORK REQUIRED: C.O. 2. PART II. SECTION IV. STORMWATER MANAGEMENT
CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
ITEM DESCRIPTION CONTRACT CONTRACT
NUMBER QUANT/TIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
1 Furnish, install and
maintain 1,401.5 linear feet
of silt fence erosion
control, complete as
soecified, oer linear foot 1,401.50 1,401.50 $2.00 $2,803.00
2 Furnish. install and
maintain 32 erosion control
bales, complete as
specified, each 32.00 32.00 $12.00 $384.00
ADDITIONAL WORK: C.O. # 2 (ITEMS 1-2) - SUB-TOTAL
NET INCREASE TO PART II- SECTION IV.
$3,187.00
$3,187.00
$0.00
NET INCREASE TO PART 11- SECTIONS I, II, III, IV
NET DECRÈASE TO PART II- SECTIONS I, II, III, IV
$3,478.90
$0.00
NET INCREASE TO CONTRACT 05-05 PART II:
$3,478.90
NET INCREASE TO CONTRACT 05-05 (PARTS I AND II)
$147,192.20
Page 5