CHANGE ORDER NO. 2/ PUBLIC WORKS CONTRACT NO. 04-13
INITIATED BY:
DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
NORTHEAST ASPHALT INC.
W6380 Design Drive
Greenville, WI 54942
Net Decrease to contract:
($21,810.21 )
PURPOSE: See attached Change Order.
, ,
CHANGE ORDER #
DATED: 11/01/05
2
TO: NORTHEAST ASPHALT INC
W6380 DESIGN DRIVE
GREENVILLE, WI 54942
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
04-13
, is hereby amended
NET DECREASE TO SECTION 1- ASPHALT PAVING:
NET INCREASE TO SECTION 1\ - STORM SEWER:
NET INCREASE TO SECTION 111- SANITARY SEWER:
($21,810.21)
$0.00
$0.00
($21,810.21)
NET DECREASE TO CONTRACT:
CITY OF OSHKOSH
BY:
City Manager
Recommended:
j)-i c ti~
Director of Pu lic Works
City Clerk
~
ntractor
J .\ U -<-tV) "b ~ I PrY
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 04-13 CHANGE ORDER # 2
SECTION I . ASPHALT PAVING
ITEM CONTRACT INSTALLED NET NET COSTPER INCREASE IN DECREASEIN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNlT CONTRACT CONTRACT
PRICE PRICE
1. Approx. 240 square yards
of pavement removal,
complete as specified, per
square yard 240.00 104.00 -136.00 $6.00 ($816.00)
2. Approx. 5,650 square feet
of sidewalk and driveway
removal, complete as
specified, per square foot 5,650.00 10,179.00 4,529.00 $0.52 $2,355.08
3. Approx. 1,370 cubic yards
of excavation, complete as
specified, per cubic yard
1,370.00 592.00 -778.00 $5.40 ($4,201.20)
4. Approx. 10,400 square
yards of asphaltic
pavement milling, complete
as specified, per square
yard 10,400.00 10,929.00 529.00 $2.10 $1,110.90
5. Approx. 1,440 tons of
asphaltic concrete binder
material, complete as
specified, per ton 1,440.00 1,238.00 -202.00 $31.60 ($6,383.20)
6. Approx. 1,330 tons of
asphaltic concrete surface
material, complete as
specified, per ton 1,330.00 1,339.00 9.00 $34.80 $313.20
7. Approx. 200 square yards
of 5" asphaltic concrete
patch including sawing,
pavement removal,
excavation, grading and
traffic controll, complete as
specified, per square yard
200.00 150.00 -50.00 $34.90 ($1,745.00)
8. Approx. one (1) asphaltic
concrete speed hump,
complete as specified,
lump sum 1.00 1.00 $2,260.00
9. Approx. 60 gallons of tack
or prime coat, complete as
specified per aallon 60.00 150.00 90.00 $2.00 $180.00
10. Approx. 180 linear feet of
30" curb & gutter removal
and replacement, complete
as specified, per linear foot
180.00 185.00 5.00 $19.75 $98.75
11. Approx. 100 linear feet of
standard 30" curb & gutter,
complete as specified, per
linear foot 100.00 104.00 4.00 $16.75 $67.00
Page 1
CONTRACT: 04-13 CHANGE ORDER # 2
ITEM 'CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
12. Approx. 200 square yards
of 7" concrete
base course, complete as
specified, per square yard
200.00 17.00 -183.00 $20.00 ($3,660.00)
13. Approx. 3,500 square feet
of 4"
concrete sidewalk,
complete as specified, per
square foot 3,500.00 3,490.00 -10.00 $2.62 ($26.20)
14. Approx. 4,600 square feet
of 6"
concrete sidewalk &
driveway, complete as
specified, per square foot 4,600.00 4,788.00 188.00 $3.02 $567.76
15. Furnish and install approx.
1 ,900 tons of crushed
stone base course,
complete as specified, per
ton 1,900.00 609.00 -1,291.00 $6.80 ($8,778.80)
16. Approx. 1,150 linear feet of
sawing, complete as
specified, per linear foot 1,150.00 725.00 -425.00 $2.10 ($892.50)
17. Adjust approx. 40 '
manholes and inlets,
complete as specified,
each 40.00 40.00 $215.00
18. Preparation of foundation
for asphalt paving on
Congress Avenue,
complete as specified,
lump sum 1.00 1.00 $4,350.00
19. Preparation of foundation
for asphalt paving on Reed
Avenue, complete as
specified, lump sum 1.00 1.00 $3,900.00
20. Preparation of foundation
for asphalt paving on
Lamar Avenue, complete
as specified, lump sum 1.00 1.00 $3,900.00
21. Preparation of foundation
for asphalt paving on
Stevens Court, complete
as specified, lump sum 1.00 1.00 $3,100.00
22. Preparation of foundation
for asphalt paving on Titan
Court, complete as
specified, lump sum 1.00 1.00 ' $3,500.00
23. Preparation of foundation
for asphalt paving on W.
17th Avenue, complete as
specified, lump sum 1.00 1.00 $2,600.00
Page 2
CONTRACT: 04-13 CHANGE ORDER # 2
CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
ITEM DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE ,UNIT PRICE PRICE
24. Preparation of foundation
for asphalt paving on W.
Parkway Avenue, complete
as specified, lump sum
1.00 1.00 $2,400.00
25. Preparation of foundation
for asphalt paving on Alley
(east of Ohio Street),
complete as specified,
lump sum 1.00 1.00 $4,100.00
26. Preparation of foundation
for asphalt paving on Alley
(west of S. Main Street),
complete as specified,
lump sum 1.00 1.00 $2,900.00
27. Terrace work on Alley (east
of Ohio Street), complete
as specified, lump sum
1.00 1.00 $1,436.00 ,,'
28. Terrace work on Alley
(west of S.
Main Street), complete as
specified, lump sum 1.00 1.00 $1,055.00
29. Provide $375.00 to the City
of Oshkosh for project
management
communications, complete
as specified, lump sum
1.00 1.00 $375.00
SECTION I- (BID ITEMS 1 - 29) - SUB-TOTALS
NET DECREASE TO SECTION I -
$4,692.69 ($26,502.90)
($21,810.21)
NET INCREASE TO SECTION I
NET DECREASE TO SECTION I
NET DECREASE TO CONTRACT:
Page 3
$4,692.69
($26,502.90)