Scott Herkert [Scott.Herkert@Strand.com]
Thursday, May 17, 2001 2:09 PM
Ti mMcEnroe@FluorBro.com
RE: Morgan Manufacturing
I have made the earliest appointment they had at Department of Commerce for May 29th. We can usually get a faxed
copy of the approval letter the day or so after. Is the only thing we need to revise on the plans the deletion of the wall
between the new addition and Building K?
Using 6" batt insulation on the walls and ceiling of building K should be fine.
Scott.
»> "Tim McEnroe" <TimMcEnroe@FluorBro.com> 05/17/01 10:27AM »>
Scott
I will have to commit to a schedule for resubmitting the Morgan drawings to
state. The bldg inspector is requiring a commitment befor he will issue a
temporary occupancy permit. Please suggest a date that I should pass on.
On a second matter, I am assuming that I should be looking at 6 in of
fiberglass in the walls and ceiling of Bldg K to meet the envelope
requirements. Do you agree? Thanks Tim