HomeMy WebLinkAbout05-304.doc
OCTOBER 11, 2005
05-304
RESOLUTION
(CARRIED 7 -0 LOST
LAID OVER
WITHDRAWN
PURPOSE:
APPROVE AGREEMENT WITH WISCONSIN PUBLIC SERVICE
TO EXTEND UTILITIES IN SOUTHWEST INDUSTRIAL PARK
INITIATED BY:
DEPARTMENT OF COMMUNITY DEVELOPMENT
BE IT RESOLVED by the Common Council of the City of Oshkosh that the
attached Agreement with Wisconsin Public Service Corporation for the installation I
extension of utilities within the Southwest Industrial Park is hereby approved and the
proper City officials are hereby authorized to execute and deliver the agreement in
substantially the same form as attached hereto, any changes in the execution copy
being deemed approved by their respective signatures, and said City officials are
authorized and directed to take those steps necessary to implement the terms and
conditions of the Agreement.
Money for this purpose is hereby appropriated from:
Account No. 532-1040-6466-00000 --TIF 18 Southwest Industrial Park.
Wisconsin Public Service
DISTRIBUTION FACILITIES INSTALLATION AGREEMENT
District: 40
Project No: 0052005066
This contract is for the installation of Electric and Gas facilities entered into on September 13.2005 (Contract Date) between CITY
OF OSHKOSH (Customer) and Wisconsin Public Service Corporation (WPSC).
Site Address / Description / Location: S W INDUSTRIAL PARK in the CITY OF OSHKOSH, County of WINNEBAGO, State of
WI. .
WPSC agrees to install facilities and provide service in accordance with all appropriate regulations and tariffs as filed with the Public
Service Commission of Wisconsin (PSCW) and lor Michigan Public Service Commission (MPSC). WPSC furthermore agrees to
render service to the Customer at such point on the premise as has been mutually determined and agreed upon. The Customer agrees
to comply with all terms and conditions as stated on Page 2 of this contract, including the commencement date of Minimum Charges,
and all appropriate WPSC tariffs on file with PSCW and lor MPSc.
Type of Electric Service:
Standard System Facility Costs (Refundable)
Allowances .
Special System Facilities Costs (Refundable)
Refundable Sub Total
Special Facilities Costs Non Refundable:
System
Service
Temporary Service
Non Refundable Sub Total
Electric and Gas Total:
-Electric-
$162,605.32
-Gas-
$32,627.85
$162,605.32
$32,627.85
$0.00
$162,605.32
$0.00
$32,627.85
*This agreement Ddoes IZIdoes not include the cost of the service(s) to the meter. When it does not, additional charges may be forthcoming.
T Ota! Cost
$195,233.17
Applicable refunds will be made to: IZIContracting Developer [JProperty Owner [JOther-
Allowances and refunds are determined by WPSC's extension rule policies that have been approved by the PSCW and lor MPSC.
These rules are subject to change pending approval by the PSCW or MPSC. A 5 year development period will .begin from the date this
facility/project is energized for the electric facility and pressurized for gas facility. Applicable refunds will be made during this time
period.
Refund amounts shall equal the allowance applicable to customer additions based on the current extension allowance or the
allowances in effect when the addition occurs, whichever is greater, less the added investment in distribution system facilities
required. After the development period, the Customer agrees to reimburse WPSC for all allowances received on this contract that did
not result in customers taking service by the expiration of the development period.
A
tabulation of said allowance(s) is as follows:
Customer Name / Lot # Address / Plat Ext. Allowance Amount
I have read, understand and agree to the terms and conditions of this contract
Customer Signature: Date:
Mailing Address: PO BOX 1130 OSHKOSH, WI 54903-1130
WPSC Signature:
Date:
Work Request/Revision: 132603-1
Account# Energized Date
CIS Order # 7666782-05
Page 1 of2