HomeMy WebLinkAbout05-292.doc
SEPTEMBER 27, 2005
05-292
RESOLUTION
(CARRIED
6-0
LOST
LAID OVER
WITHDRAWN
PURPOSE:
APPROVE AGREEMENT WITH AT&T AND SPRINT I
ANCHORAGE BASIN PROJECT
INITIATED BY:
DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the attached
Proposals from AT&T and SPRINT for relocation of fiber optic cable required for the
Anchorage Basin Storm Water Improvements project are hereby approved and the proper
City officials are hereby authorized to execute an appropriate agreement and directed to
take those steps necessary to implement the terms and conditions of the Agreement.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 561-2010-1799-00000 - Storm Water Utility - Construction in Progress
City of Oshkosh, WI
Anchorage Basin Proj ect 2x 66" Casings under CNRR
Protection
Scope of Work
This work order provides protection to Sprint's fiber optic cable during the construction of 2x
66" steel casings being Jack and Bored under Canadian National RR Mile Post 196.5 by The
City of Oshkosh, WI for their Anchorage Basin Storm Project.
This work will require approximately 120' of direct buried Sprint fiber optic cable 42" deep in 1
W' Plow Con to be dug up and exposed. The existing cable will be lowered 2-5 feet and placed
in 60'of 4" split steel with Ix 1 W' inner duct and Ix 1 v,¡" split inner duct over the existing
cable where the Jack and Bore Machine will be placed over Sprint during the 2x 66" steel casing
installation. Sprint's 4" split steel protection will be a minimum of2' below the Jack and Bore
rigging in 100% compacted trench backfill.
This work order is necessary to protect Sprint's investment in facilities and to protect our
customers from service interruptions during The City of Oshkosh Anchorage Basin Storm
Project.
This work order is 100% billable to:
Attention:
Scott Erickson
City of Oshkosh
Assistant Director of Public Works
P.O. Box 1130
Oshkosh, WI 54903
Phone (Oft):920-236-5042
Phone (Fax):920-236-5068
The estimated Sprint Reimbursable costs are as follows:
Description I I QTY UNIT UNIT / COST TOTAL
Construction Contract (T & M Based) 11 ,200 LT $1.00 $11,200.00
CNRR Flagman 24 HR $75.00 $1,800.00
Sprint labor
Sprint Cable Proiect Enaineer / InsDector 32 HR $33.00 $1,056.00
Sprint Technician 8 HR $24.59 $196.72
Sprint Drafting 8 HR $17.28 $138.24
Sprint Labor Overhead 48 HR $32.55 $1,562.40
Total Estimate Cost of Work $15,953.36
G&A Overhead (á2 4.28% $682.80
Total Sprint Reimbursable Costs $16,636.16
James Burton
Sprint / Nextel
Sf. Cable Project Engineer
Central Region / Field Operations
File WO 92766108
September 6, 2005
Scope of Work
Appleton - Watertown Jet FT "A" Cable
II
City of Oshkosh Culvert Installation under CN Railroad
The Location:
This project is located along the CN Railroad in the city of Oshkosh, WI
The Work:
This work involves the exposing and lowering of approximately 140 feet of fiber cable in a 2" steel
pipe three feet deep and installing 40 feet of concrete cap for two proposed 48" culverts to be
installed over the top ofthe cable
THE WORK WILL CONSIST OF THE FOLLOWING:
1.
Install temporary shoring along the track at each end of the project area where the cable
ranges fÌ'om 9 feet to 12 feet fÌ'om the center of the track. .
Expose approximately 140 feet of existing AT&T fiber cable 85 feet of with 2" steel pipe on
it. .
Lower the existing AT&T fiber cable three feet lower than the existing depth at the two
proposed 48" culverts to be installed.
Install 40 feet of concrete cap at the, locations where the two new culverts are to be installed
and along the two existing culverts.
Install AT&T cable warning tape, backfill and mechanically compact all excavated areas.
. Clean up all disturbed areas along the route as good as or better condition and remove the
Temporary shoring.
2.
3.
4.
5.
6.
NOTE: Extreme caution will be used when working around the
existing AT&T fiber cable and no work will be done in the
existing AT&T right-of-way with out a AT&T technician on
site.
NOTE: All work will be completed as per the AT&T Specifications
for Outside Plant Construction and Maintenance.
,
, - r
2
September 6, 2005
Cost Estimate
Appleton - Watertown Jet FT "A" Cable
City of Oshkosh Culvert Installation under CN Railroad
Engineering - Consultant:
1. Investigation, Engineering,
2. Construction Inspection
3. Travel and lodging
TOTAL $ 5,464.00
Construction Cost: (Including Materials)
1. Mobilization
2. Vertical shift Duct to 6'
3. Vertical shift duct 6' to 8'
4. Install Concrete cap
5. Install and Remove Shoring
TOTAL $16,700.00
AT&T Cost:
1. AT&T Technician
2. AT&T Engineer
TOTAL $ 4,600.00
CN Railroad Cost:
1. CN Railroad Flagman
TOTAL $ 4,000.00
TOTAL COST ESTIMATE:
1. Consultant
2. Construction
3. AT&T Cost
4. CN Railroad Cost
GRAND TOTAL
$ 30.764.00