HomeMy WebLinkAboutPW CNT 04-06/Cng Ord #1 , *' : ;" CHANGE ORDER # 1 Dated: November 10,2004 TO: Fischer-Ulman Construction, Inc. 1115 S. Theodore Street Appleton, WI 54915 Your present contract with the City of Oshkosh, Contract No. 04-06, is hereby amended and changed as follows: NET INCREASE TO SECTION 1- SIDEWALK REHAB $22,923.42 NET INCREASE TO CONTRACT: $22,923.42 CITY OF OSHKOSH u ~k- l' Recommended: llv:cl (,. ~ Director of Publi Works Approved and accepted: -~~þu~ Contractor I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. ~av~ Comptroller A~proveä;t~l: ~" .~ - City Attorney }' , .f CONTRACT: 04-06 CHANGE ORDER #1 SECTION I - SIDEWALK REHAB DESCRIPTION INCREASE IN COST PER UNIT CONTRACT PRICE DECREASE IN CONTRACT PRICE 1 Approx. 74,000 square feet of sidewalk removal & driveway removal, complete as specified, per square foot 74,000.00 85,515.14 11,515.14 $0.30 $3,454.54 2 Approx. 3,000 linear feet of concrete/asphalt sawing, complete as specified, per linear foot 3,000.00 4,347.40 1,347.40 $2.00 $2,694.80 3 Construct approx. 86,000 square feet of 4" thick concrete sidewalk in various locations in the City of Oshkosh, complete as specified, per square foot 86,000.00 83,518.91 -2,481.09 $2.25 ($5,582.45) 4 Approx. 18,000 square feet of 4" thick concrete sidewalk 7' wide (Jackson Street/Pearl Avenue), per square foot 18,000.00 4,067.00 -13,933.00 $1.95 ($27,169.35) 5 Construct approx. 11,000 square feet of 6" thick concrete sidewalk in various locations in the City of Oshkosh, complete as specified, per square foot 11,000.00 15,649.15 4,649.15 $2.86 $13,296.57 6 Construct approx. 2,500 square feet of 6" thick textured concrete wheel chair ramps, complete as specified, per square foot 2,500.00 2,282.71 -217.29 $3.20 ($695.33) Page 1 , r , CONTRACT: 04-06 CHANGE ORDER #1 ITEM CONTRACT INSTALLED NET NET INCREASE IN DECREASE IN DESCRIPTION COST PER UNIT CONTRACT NUMBER QUANTITIES QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE 7 Approx. 1 ,500 square feet of three (3") inch asphalt replacement, complete as specified, per square foot 1,500.00 3,262.45 1,762.45 $2.60 $4,582.37 8 Approx. 250 linear feet of curb and gutter removal, complete as specified, per linear foot 250.00 316.50 66.50 $3.00 $199.50 9 Approx. 300 linear feet of 30" curb and gutter, complete as specified, per linear foot 300.00 474.40 174.40 $14.20 $2,476.48 10 Approx. 300 square yards of terrace restoration, including seed, fertilize, and mulch, complete as specified, per square yard 300.00 603.40 303.40 $3.10 $940.54 11 Furnish and install approx. 50 pavement ties, complete as specified, each 50.00 78.00 28.00 $7.00 $196.00 12 Construct approx. 3,000 square feet of 4" thick concrete sidewalk in Water Dept. repair locations at approx. 40 sites, complete as specified, per square foot 3,000.00 3,891.29 891.29 $3.30 $2,941.26 13 Construct approx. 1,000 square feet of 6" thick concrete sidewalk in Water Dept. repair locations at approx. 20 sites, complete as specified, per square foot 1,000.00 1,188.00 188.00 $3.70 $695.60 Page 2 " CONTRACT: 04-06 CHANGE ORDER #1 ITEM CONTRACT INSTALLED NET NET INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE COST PER UNIT CONTRACT CONTRACT PRICE PRICE 14 Approx. 100 square yards of 7" non-reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, complete as specified, per square yard 100.00 -100.00 $34.55 ($3,455.00) 15 Approx. 1,200 square yards of 8" non-reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, complete as specified, per square yard 1,200.00 1,084.58 -115.42 $34.00 ($3,924.28) 16 Approx. 500 square yards of 8" special High Early Strength, non-reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb and grading, terracing and traffic control, complete as specified, per square yard 500.00 284.49 -215.51 $37.00 ($7,973.87) '/A 17 Approx. 250 tons extra crushed stone base, complete as specified, per ton 250.00 225.47 -24.53 $10.00 ($245.30) Page 3 ".. CONTRACT: 04-06 CHANGE ORDER #1 ITEM CONTRACT INSTALLED NET NET INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE COST PER UNIT CONTRACT CONTRACT PRICE PRICE 18 Approx. 1,200 linear feet of No.4 epoxy- coated reinforcement rods, installed as specified, per lin. ft. 1,200.00 961.00 -239.00 $1.50 ($358.50) 19 Provide $1,500 to the City of Oshkosh for project management communications, complete as specified, lump sum 1.00 1.00 $1,500.00 SECTION 1- (BID ITEMS 1 -19) - SUB-TOTALS $31,477.66 ($49,404.08) ADDITONAL WORK REQUIRED: C.O. # 1 - SECTION I - CONCRETE PAVING ITEM CONTRACT INSTALLED NET NET INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE COST PER UNIT CONTRACT CONTRACT PRICE PRICE 1 9" non-reinforced concrete pavement removal and replacement, including sawing, pavement ties, ;:; integral curb & grading, terracing & traffic control, complete as specified, per square yard 232.59 232.59 $37.50 $8,722.13 2 9" 7-bag non- reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, complete as specified, per square yard 78.32 78.32 $39.00 $3,054.48 Page 4 .~ . ", CONTRACT: 04-06 CHANGE ORDER #1 ITEM CONTRACT INSTALLED NET NET INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE COST PER UNIT CONTRACT CONTRACT PRICE PRICE 3 9" 9-bag non- reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, complete as specified, per square yard 112.89 112.89 $40.50 $4,572.05 4 8" 7-bag non- reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, complete as specified, per square yard 445.88 445.88 $36.00 $16,051.68 5 9" thick concrete sidewalk in Water Dept. repair location, complete as specified, per square foot 443.75 443.75 $4.40 $1,952.50 6 Miscellaneous extras (Le. brick, mortar, clean out inlet), lump sum $350.00 $350.00 7 Installation of modular block walls on Sawyer Street (includes block w/top cap, backfill, topsoil, seed, fertilizer, mulch <; and traffic control), lump sum $6,147.00 $6,147.00 ADDITIONAL WORK: C.O. # 1 - (ITEMS 1 - 6) - SUB-TOTAL $40,849.84 $0.00 $22,923.42 NET INCREASE TO SECTION I - Page 5 . ,.'. !>. , ITEM NUMBER DESCRIPTION CONTRACT: 04-06 CHANGE ORDER #1 INSTALLED QUANTITIES NET INCREASE IN DECREASE COST PER UNIT CONTRACT PRICE NET INCREASE NET INCREASE TO SECTIONS I, II, III, IV NET DECREASE TO SECTIONS I, II, III, IV $72,327.50 ($49,404.08) NET INCREASE TO CONTRACT: $22,923.42 Page 6 DECREASE IN CONTRACT PRICE