HVAC PERMIT - APPLICATION AND RECORD
Job Address 2251 BADGER AVE
Owner
CURWOOD INC
Create Date 06/01/2005
Contractor BASSETT MECHANICAL
1 1 Gas 1 1 Oil
Fuel
1,(1 New 1
System
U Forced Air U Radiant
1 1 Electric 1 1 Hot Water
Chimney Type () Chimney A 0 Chimney B
Heat Loss 10 As Approved 0 Existing
BTU Rate 10 As Per Plan 0 Variable
Category 520 - Ind. & Comm-Other
1,(1 Electric
Plan Not Req Per AD
1 1 Solar
1 1 Solid
1
1 1 Other
1 l..j Vent
1
1 1 Replace
U Steam
1 1 Suppl.
U A/C
1 1 Con. Burner
0 Direct Vent
. Not Applicable
. Not Applicable
. Other
Value
0
Value
Use/Nature IND/ Installation of (2) 40,000 CFM RTU - mounted on steel structures to provide heat relief in the plant per letter addressed to Allyn Dannhoff
of Work dated 5/23/05.
Fees: Valuation
$150,000.00
Plan Approval
$0.00
Permit Fee Paid
$930.00
Issued By:
Date 06/03/2005
U Permit Voided 1
Parcelld # 1325000000
In the performance of this work, I agree to perform all work pursuant to rules governing the described construction.
While the City of Oshkosh has no authority to enforce easement restrictions of which it is not a party, if you perform the work
described in this permit application within an easement, the City strongly urges the permit applicant to contact the easement
holder(s) and to secure any necessary approvals before starting such activity.
Signature
Date
Agent/Owner
Address
PO BOX 7000
KAUKAUNA
WI 54130 - 7000
Telephone Number
800-236-2500
---
To schedule inspections please call the Inspection Request line at 236-5128 noting the Address, Permit Number, Type of
Inspection (i.e. Footing, Service, Final, etc.), Access into Building if Secure (how do we gain entry), your Name and Phone
Number. Unless specified otherwise, we will assume the project is ready at the time the request is received. Work may
continue if the inspection is not performed within two business days from the time the project is ready.
If you have any questions, please contact me at (920) 759-252 ext. 509.
S{n4re'~
,-\J'~
~o~n. Ter es, P.E., CEM.
\é~ect Engineer
¡rl;;;~- JNT/dms
.irhr -~C: Mike Brosch - Curwood
. (j - '-; Jeff Beyersdorf
.
M~~~~
1215 Hyland Avenue
po. Box 7000
Kaukauna, WI 54130
920.759-2500
800-236-2500
FAX 920-759-2525
~w.b"'etlm"h";"'."m
May 23, 2005
Allyn Dannhoff
City of Oshkosh
215 Church Avenue
Oshkosh, WI 54902-1130
MAY 2 6 2005
RE:
CSF Plant Ventilation
Dear Allyn,
Attached you will find the HVAC permit application with the check in the amount of
$1,010.50. Below is a description of the existing plant HVAC system and the proposed
ventilation addition.
Existinq HVAC Svstem:
Exhaust fan summary
EF-1
1250 CFM
4200 CFM
4200 CFM
4200 CFM
25000 CFM
18500 CFM
4300 CFM
61650 CFM
Toilet Room
Ink Mixing
Ink Mixing
Ink Mixing
Coater General Exhaust
Press Exhaust to Incinerator
EF-2
EF-3
EF-4
EF-5
Incinerator
EF-6
Total Exhaust
Make-up air
(2) make-up air units. King model DCFOC-230B, 80/20 units with building
pressure controls. Capacity of these units are 60,000 CFM each, 6,050
MBH each, The purpose of these units are to maintain a slight positive
building pressure in reference to the outdoors.
There are existing gas fired unit heaters located along the perimeter of the
facility to offset building heat loss.
New Ventilation Svstem:
Provide (2) 40,000 CFM roof mounted air handling units. These units will be mounted on a
structure steel platform. The platform is provided by CR Meyer. Each unit weighs 9,352 Ibs.
The air handling units will contain: mixing box, 2" thick 30% efficient filters, chilled water
coils and a supply fan section.
The chilled water coils will not be piped at this time and will remain inactive. The main
purpose of the units at this time is to provide heat relief in the plant in spring, summer and
fall. A control panel will be provided. A remote bulb senses space temperature and
modulates the mixed air dampers. A low limit discharge controller will not permit the
discharge temperature to drop below 60°F. A freeze thermostat will de-energize the unit and
close the outside air dampers if the mixed air temperature drops below 45°F.
As you mentioned, plans do not have to be submitted for this project. This letter, along with