HomeMy WebLinkAbout05-99.doc
APRIL 12, 2005
05-99
RESOLUTION
(CARRIED
7-0
LOST
LAID OVER
WITHDRAWN
PURPOSE:
CHANGE ORDER NO. 1/ PUBLIC WORKS CONTRACT NO. 04-19
INITIATED BY:
DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
JOSSART BROTHERS, INC.
1682 Swan Road
DePere, WI 54115
Net Increase to contract
$28,825.74
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Accl. No. 528-1040-7480-03302 - TIF 19 - Sewer
Accl. No. 528-1040-7480-03303 -- TIF 19 - Water
TO: Jossart Brothers, Inc.
1682 Swan Road
DePere, WI 54115
Your present contract with the City of Oshko$h, Contract No.
and changed as follows:
PART 1
NET INCREASE TO SECTION I - SANITARY SEWER:
NET INCREASE TO SECTION 11- WATER MAIN:
CHANGE ORDER # 1
DATED: March 11, 2005
04-19
, is hereby amended
$27,127.85 .
$5,555.05
$32,682.90
PART 2
NET INCREASE TO SECTION II - STORM SEWER:
NET DECREASE TO SECTION 111- SANITARY SEWER:
NET DECREASE TO SECTION IV - WATER MAIN:
NET DECREASE TO SECTION V - EROSION CONTROLISTORMWATER:
NET INCREASE TO CONTRACT:
Recommended:
~c..~
Director of Public orks
$386.76
($86.42)
($2,877.50)
($1,280.00)
($3,857.16)
$28,825.74
CITY OF OSHKOSH
BY:
City Manager
/3Iêc)Í7/i?
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Approved as to form:
City Attorney
Comptroller
CONTRACT: 04-19 PART 1 AND 04-19 PART 2 CHANGE ORDER # 1
PART 1
SECTION I-SANITARY SEWER
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
1. Furnish and install approx.
20 linear feet of 8" Sanitary
Sewer Relay, complete as
specified, per linear foot
20.00 25.00 5.00 $75.00 $375.00
2. Furnish and install approx.
40 vertical feet of 8"
Sanitary Sewer Drop,
complete as specified, per
vertical foot 40.00 39.50 -0.50 $325.00 ($162.50)
3. F!lrnish and install approx.
290 linear feet of 15"
Sanitary Sewer Relay with
aravel backfill (Fountain
Avenue), complete as
specified, per linear foot 290.00 288.42 -1.58 $195.00 ($308.10)
4. Furnish and install approx.
1,380 linear feet of 15"
New Sanitary Sewer,
complete as specified, with
natural backfill. per linear
foot 1,380.00 1,383.45 3.45 $71.00 $244.95
5. Furnish and install one (1)
6" Sanitary Riser (1738
Fountain Avenue),
complete as specified,
lump sum 1.00 1.00 $700.00
6. Furnish and install approx.
117 vertical feet of std.
Sanitary Manhole (4' Inside
Diameter), complete as
specified, in five (5)
locations without castings,
Ipervertical foot 117.00 117.00 $100.00
7. Remove and salvage
approx. 265 linear feet of
chain link fencing as
specified, per lin. f1. 265.00 132.50 -132.50 $2.00 ($265.00)
8. Furnish, install and
maintain approx. 800 linear
feet of Silt Fence Erosion
Control, per linear foot 800.00 629.00 -171.00 $1.50 ($256.50)
9. Provide $375.00 to the City
of Oshkosh for project
management
communications, complete
as specified, lump sum
1.00 1.00 $375.00
SECTION I . (BID ITEMS 1 .9) - SUB-TOTALS
$619.95
($992.10)
Page 1
CONTRACT: 04-19 PART 1 AND 04-19 PART 2 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
ADDITIONAL WORK REQUIRED: C.O. # 1 . SECTION I
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
1 Extra costs to bypass the
existing 16" water main on
Fountain Avenue to insure
maintenance of water
service and to provide a
safer construction zone,
and extra costs to provide
large scale pumping of
ground water at the existing
lift station to dewater the
existing trench along
Fountain Avenue, lump
sum 1.00 1.00 $27,500.00 $27,500.00
ADDITIONAL WORK: C.O. # 1 . (ITEM 1) - SUB-TOTAL
$27,500.00
.$0.00
$27,127.85
NET INCREASE TO SECTION (-(PART 1)
PART 1
SECTION II- WATER MAIN
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
10. Furnish and install approx.
60 linear feet of 6" Ductile
Iron Water Main wfpoly
wrap, complete as
specified (fittings not
included), per linear foot 60.00 54.00 -6.00 $38.00 ($228.00)
11. Furnish and install approx.
30 linear feet of 8" Ductile
Iron Water Main w/poly
wrap, complete as
specified (fittings not
included), oer linear foot 30.00 14.00 -16.00 $40.00 ($640.00)
12. Fumish and install approx.
1,380 linear feet of 16"
Ductile Iron Water Main
w/poly wrap, complete as
specified, (fittings not
included), per linear foot 1,380.00 1,380.50 0.50 $64.00 $32.00
13. Furnish and install approx.
four (4), 6" Valves,
complete as specified,
each 4.00 4.00 $700.00
Page 2
CONTRACT: 04-19 PART 1 AND 04-19 PART 2 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
14. Furnish and install approx.
one (1), 8" Valve,
complete as specified,
each 1.00 1.00 $900.00
15. Furnish and install approx.
two. (2), 16" Valves in std.
Water Valve Manhole,
complete as specified with
castings, each 2.00 3.00 1.00 $3,800.00 $3,800.00
16. Furnish and install approx.
one (1),16" x 16" Tapping
Valve and Sleeve in std.
Water Valve Manhole,
complete as specified with
casting, each 1.00 0.00 -1.00 $14,000.00 ($14,000.00)
17. Furnish and install approx.
four (4),16" x 6" Tees,
complete as specified,
each 4.00 4.00 $750.00
18. Furnish and install approx.
one (1), 16" x 8" Tee, -
complete as specified,
each 1.00 1.00 $750.00
19. Furnish and install approx.
one (1), 8" x 6"
Reducer, complete as
soecified, each 1.00 1.00 $175.00
20. Fumish and install approx.
one (1), 8", 1/8 Bend,
complete as specified,
each 1.00 1.00 $250.00
21. Furnish and install approx.
one (1), 6" Plug, complete
as specified, each 1.00 1.00 $50.00
22. Furnish and install approx.
one (1),16" Plug, complete
as specified, each 1.00 1.00 $300.00
23. Remove approx. 138 1.0.
of trees and stumps,
complete as specified, per
inch diameter 138.00 17 4.00 36.00 $10.00 $360.00
24. Furnish and install approx.
three (3) Hydrants,
complete as specified,
each 3.00 4.00 1.00 $1,750.00 $1,750.00
25. Provide $375.00 to the City
of Oshkosh for project
management
communications, complete
as specified, lump sum
1.00 1.00 $375.00
SECTION II. (BID ITEMS 10.25). SUB-TOTALS
$5,942.00 ($14,868.00)
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION \I
Page 3
CONTRACT: 04-19 PART 1 AND 04-19 PART 2 CHANGE ORDER # 1
CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
ITEM DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
ITEM DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
1 Relocate existing 16" water
main along Fountain
Avenue, 12/10/04 -
12/23/04, lump sum 1.00 1.00 $11,751.39 $11,751.39
2 Extra costs to lower new
main under existing 8"
sanitary in Future Street,
1/16/05 lump sum 1.00 1.00 $1,886.23 $1,886.23
3 Furnish and install 16" X
16" tea, lump sum 1.00 1.00 $843.43 $843.43
ADDITIONAL WORK: C.O. # 1 . (ITEMS 1 .2) - SUB.TOTAL
$14,481.05
$0.00
NET INCREASE TO SECTION II. (PART 1)
$5,555.05
NET INCREASE TO SECTIONS I, II- (PART 1)
NET DECREASE TO SECTIONS I, II - (PART 1)
$48,543.00
($15,860.10)
NET INCREASE TO CONTRACT 04.19 - (PART 1)
$32,682.90
PART 2
SECTION II . STORM SEWER
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
5 Furnish and Install 12"
RCP CL III or PVC
w/Gravel Backfill, per linear
foot 84.00 95.66 11.66 $36.00 $419.76
6 Furnish and Install 18"
RCP CL III or PVC
w/Gravel Backfill, per linear
foot 57.00 56.25 -0.75 $44.00 ($33.00)
7 Furnish and Install Type 3
Std. Inlet, each 3.00 3.00 $900.00
8 Remove 18" Storm Sewer,
per linear foot 8.00 8.00 $10.00
9 Remove Type 3 Standard
Inlet, each 1.00 1.00 $100.00
SECTION II . (BID ITEMS 5 .9). SUB.TOTAlS
$419.76
($33.00)
$386.76
NET INCREASE TO SECTION II- (PART 2)
Page 4
CONTRACT: 04-19 PART 1 AND 04-19 PART 2 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASEIN DECREASEIN
DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
,
PART 2
SECTION III. SANITARY SEWER
ITEM GONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCReASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
.
10 Furnish and Install 8" PVC
Sanitary Sewer wIG ravel
Backfill, per linear foot
400.00 398.30 -1.70 $40.25 ($68.42)
11 Furnish and Install 4'
Diameter Standard
Manhole, per vertical foot 10.70 10.60 -0.10 $140.00 ($14.00'
12 Furnish and Install 4' .
Diameter Standard
Manhole Over Existing 8"
PVC Sanitary Sewer, per
vertical foot 10.70 10.68 -0.02 $200.00 ($4.00)
13 N/A
SECTION III. (BID ITEMS 10-13) - SUB.TOTAlS
$0.00
($86.42)
NET DECREASE TO SECTION III. (PART 2)
($86.42)
PART 2
SECTION IV - WATER MAIN
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
14 Furnish and Install 6"
Ductile Iron Water Main
w/Gravel Backfill and
Polvwrao, ner linear foot 49.00 44.00 -5.00 $35.00 ($175.00)
15 Furnish and Install 8" DI
Water Main w/Gravel
Backfill and Polywrap, per
linear foot 790.00 725.00 -65.00 $38.50 ($2,502.50)
16 Furnish and Install 16" x 8"
Tapping Tee wNalve,each
1.00 1.00 $3,000.00
17 Furnish and Install 5' dia,
Air Release Manhole with
8" Valve, each 1.00 1.00 $2,500.00
18 Furnish and Install 8"x6"
Tee,each 2.00 2.00 $200.00
19 Furnish and Install 8" - 45
Dearee Bend, each 2.00 3.00 1.00 $200.00 $200.00
20 Furnish and Install 8" -
22% Dearee Bend,each 3.00 1.00 -2.00 $200.00 ($400.00)
21 Furnish and Install 6"
Valve, each 2.00 2.00 $700.00
Page 5
~
CONTRACT: 04-19 PART 1 AND 04-19 PART 2 CHANGE ORDER# 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
22 Furnish and Install 8"
Valve, each 1.00 1.00 $900.00
23 Furnish and Install 8" x 6"
Reducer, each 1.00 1.00 $125.00
24 Furnish and Install Fire .
Hydrant, each 3.00 3.00 $1,600.00
25 N/A
SECTION IV. (BID ITEMS 14 - 25) . SUB.TOT AlS
$200.00
($3,077.50)
NET DECREASE TO SECTION IV. (PART 2)
($2,877.50)
PART 2
SECTION V - EROSION CONTROllSTORMWATER MANAGEMENT
26 Furnish, Install, and
Maintain Silt Fence Erosion
Control, per linear foot
520.00 0 -520.00 $1.50 ($780.00\
27 Furnish, Install and
Maintain Inlet Erosion
Control, Tvpe A, each 7.00 3 -4.00 $100.00 ($400.00'
28 Furnish, Install and
Maintain Inlet Erosion
Control, Tvoe C, each 2.00 0 -2.00 $50.00 ($100.00)
29 N/A
SECTION V . (BID ITEMS 26 - 29) . SUB-TOTAL
NET DECREASE TO SECTION V . (PART 2)
$0.00
($1,280.00)
($1,280.00)
NET INCREASE TO SECTIONS I, II, III, IV, V - PART 2
NET DECREASE TO SECTIONS I, II, III, IV,V . PART 2
$619.76
($4,476.92)
NET DECREASE TO CONTRACT 04-19- (PART 2)
($3,857.16)
NET INCREASE TO CONTRACT 04.19 - (PART 1)
NET DECREASE TO CONTRACT 04-19 - (PART 2)
NET INCREASE TO CONTRACT 04-19 . (PARTS 1 & 2)
$32,682.90
($3,857.16)
$28,825.74
Page 6