HomeMy WebLinkAbout05-60.doc
MARCH 8, 2005
05-60
RESOLUTION
(CARRIED 7 -0
LOST
LAID OVER
WITHDRAWN
PURPOSE:
CHANGE ORDER NO.1 I PUBLIC WORKS CONTRACT 04-13
INITIATED BY:
DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
NORTHEAST ASPHALT INC.
W6380 DESIGN DR.
GREENVILLE WI 54942
Net Increase to contract:
$1,136.00
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Accl. No. 561-2010-1799-00000 - Storm Water Utility - Construction in Progress
,.
'"
CHANGE ORDER # 1
DATED: February 24,2005
TO: Northeast Asphalt Inc
W6380 Design Drive
Greenville, WI 54942
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
04-13
, is hereby amended
NET INCREASE TO SECTION II - STORM SEWER:
$1,136.00
$1,136.00
NET INCREASE TO CONTRACT:
CITY OF OSHKOSH
BY:
City Manager
Recommended:
~ \)...;J c..~
Director of Public orks
City Clerk
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
~,
CONTRACT: 04-13 CHANGE ORDER # 1
SECTION II - STORM SEWER
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
30. Furnish and install approx.
60 linear feet of 12" RCP
Class III Storm Sewer,
complete as specified, per ($134.00\
linear foot 60.00 58.00 -2.00 $67.00
31. Furnish and install approx.
two (2) Std. type I inlets
(30" inside diameter with
18" sump) without
castings, complete as
specified, each 2.00 2.00 $1,075.00
32. Rebuild approx. four (4)
std. type I inlet with base,
complete as specified,
each 4.00 4.00 $850.00
33. Repair approx. nine (9) std.
type I inlet, complete as
specified, each 9.00 9.00 $750.00
34. Rebuild approx. two (2)
std. storm manhole with
base, complete as '
specified, each 2.00 2.00 $2,200.00
35. Core 2' diameter opening
in approx. two (2)
locations, through top of
existing 10" reinforced
concrete box culvert,
complete as specified, ($1,040.00)
each 2.00 -2.00 $520.00
36. Provide $375.00 to the City
of Oshkosh for project
management
communications, complete
as specified, lump sum 1.00 1.00 $375.00
SECTION II- (BID ITEMS 30 - 36) - SUB-TOTALS
ADDITIONAL WORK ReQUIRED,; C.O. # 1 - SECTION II
$0.00 ($1,174.00)
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
1 Furnish and install 6" PVC
Storm Sewer, per linear ft. 10.00 10.00 $30.00 $300.00
2 Furnish and install 8" PVC
Storm Sewer, per linear ft. 24.00 24.00 $40.00 $960.00
Page 1
~
4'
CONTRACT: 04-13 CHANGE ORDER # 1
3 Furnish and install Std.
Type I Inlet (24" inside
diameter) without casting, '
each 1.00 1.00 $1,050.00 $1,050.00
NET INCREASE TO SECTION II -
$2,310.00
$1,136.00
$0.00
ADDITIONAL WORK: C.O. # 1 . (ITEMS 1 - 3) . SUB-TOTAL
$1,136.00
NET INCREASE TO CONTRACT:
Page 2