HomeMy WebLinkAbout25-08 CO #1 (FINAL)_1-20-25TO: DORNER INC. CHANGE ORDER #1 (FINAL)
E506 LUXEMBURG ROAD
LUXEMBURG, WI 54217
Your present contract with the City of Oshkosh, Contract No.25-08, awarded December 10, 2024, is hereby amended
and changed as follows:
NET DECREASE TO SECTION I: ($180,620.18)
NET INCREASE TO ADDITIONAL WORK:$6,668.93
NET DECREASE TO CONTRACT ($173,951.25)
SECTION I TOTALS
BID TOTAL $2,502,349.20 $2,502,349.20
CO #1 ($173,951.25)($173,951.25)
CONTRACT TOTAL $2,328,397.95 $2,328,397.95
CITY OF OSHKOSH
BY:
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Approved as to form:
City Attorney
DATE: JANUARY 20, 2026
______________________________
Comptroller
______________________________
Contractor
______________________________
Approved and accepted:
______________________________
City Manager
City Clerk
______________________________
Docusign Envelope ID: 6D99D7F9-EBD2-4463-9438-58643845DDBD
25-08 CHANGE ORDER #1 (FINAL)
25-08
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
1011
Clearing; complete as
specified
Inch
Diameter 294.00 294.00 $32.50
1021
Grubbing; complete as
specified
Inch
Diameter 294.00 294.00 $25.40
1050
Mobilization; complete as
specified
Lump
Sum 1.00 1.00 $66,357.00
1100
Removing pavement;
complete as specified
Square
Yards 6,700.00 6,796.35 96.35 $3.80 $366.13
1110
Removing curb and gutter;
complete as specified
Linear
Feet 170.00 157.15 -12.85 $2.80 ($35.98)
1120
Removing concrete and
asphalt sidewalk and
driveway; complete as
specified
Square
Feet 26,000.00 25,542.87 -457.13 $0.70 ($319.99)
1200
Unclassified excavation;
complete as specified
Cubic
Yards 2,400.00 2,356.61 -43.39 $20.20 ($876.48)
1220
Excavation special (paving);
complete as specified Tons 360.00 0.00 -360.00 $16.00 ($5,760.00)
1301
7" concrete pavement; with
5" CABC and grading;
complete as specified
Square
Yards 6,000.00 5,859.17 -140.83 $57.10 ($8,041.39)
1303
7" concrete pavement HES;
with 5" CABC and grading;
complete as specified
Square
Yards 1,070.00 1,319.78 249.78 $61.20 $15,286.54
1313
8" concrete pavement HES;
with 6" CABC and grading;
complete as specified
Square
Yards 24.00 31.62 7.62 $94.40 $719.33
1334
Concrete pavement gaps;
complete as specified Each 1.00 1.00 $1,015.00
1340
Crushed aggregate base
course; complete as
specified Tons 110.00 0.00 -110.00 $17.40 ($1,914.00)
1350
Pavement ties; complete as
specified Each 57.00 58.00 1.00 $10.20 $10.20
1352
Drilled dowel bars; 1";
complete as specified Each 154.00 114.00 -40.00 $15.20 ($608.00)
1354
Drilled dowel bars; 1 1/4";
complete as specified Each 25.00 0.00 -25.00 $17.30 ($432.50)
1360
Adjust manholes and inlets;
complete as specified Each 48.00 43.00 -5.00 $406.00 ($2,030.00)
1370
Turf restoration; complete as
specified
Square
Yards 3,500.00 3,163.92 -336.08 $9.10 ($3,058.33)
1372
Restore gravel driveway/
apron; complete as specified
Square
Yards 10.00 9.62 -0.38 $36.90 ($14.02)
Page 2 of 11
Docusign Envelope ID: 6D99D7F9-EBD2-4463-9438-58643845DDBD
25-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
1380
Cold weather covering
(concrete pavement) - single
visquine; complete as
specified
Square
Yards 700.00 0.00 -700.00 $0.01 ($7.00)
1390
Up-charge for late season
cold weather concrete
pavement; complete as
specified
Cubic
Yards 140.00 0.00 -140.00 $0.01 ($1.40)
1410
12" radius curb with 6"
CABC and grading;
complete as specified
Linear
Feet 390.00 355.71 -34.29 $17.10 ($586.36)
1440
30" curb and gutter; 7"; with
5" CABC and grading;
complete as specified
Linear
Feet 115.00 109.88 -5.12 $50.80 ($260.10)
1460
Sidewalk curb; complete as
specified
Linear
Feet 235.00 103.90 -131.10 $66.00 ($8,652.60)
1500
4" concrete sidewalk with 3"
CABC and grading;
complete as specified
Square
Feet 15,100.00 14,971.86 -128.14 $6.60 ($845.72)
1510
6" concrete
sidewalk/driveway/ ramp
with 3" CABC and grading;
complete as specified
Square
Feet 8,100.00 7,866.58 -233.42 $6.80 ($1,587.26)
1514
6" concrete sidewalk/
driveway/ramp (HES) with 3"
CABC and grading;
complete as specified
Square
Feet 2,300.00 2,139.67 -160.33 $7.10 ($1,138.34)
1530
6" concrete step; complete
as specified
Square
Feet 270.00 255.00 -15.00 $76.10 ($1,141.50)
1540
Curb ramp detectable
warning field (natural/non-
painted); complete as
specified
Square
Feet 260.00 260.00 $40.60
1550
No. 4 reinforcing rods -
deformed; epoxy-coated;
complete as specified
Linear
Feet 3,000.00 2,610.00 -390.00 $2.00 ($780.00)
1560
Drilled No. 4 sidewalk tie
bars - deformed; epoxy-
coated; complete as
specified Each 110.00 175.00 65.00 $8.10 $526.50
1580
Cold weather covering
(sidewalk) - single visquine;
complete as specified
Square
Feet 2,600.00 0.00 -2,600.00 $0.01 ($26.00)
1582
Cold weather covering
(sidewalk) - double visquine;
complete as specified
Square
Feet 2,600.00 0.00 -2,600.00 $0.01 ($26.00)
1590
Up-charge for late season
cold weather concrete
sidewalk; complete as
specified
Cubic
Yards 38.00 0.00 -38.00 $15.20 ($577.60)
Page 3 of 11
Docusign Envelope ID: 6D99D7F9-EBD2-4463-9438-58643845DDBD
25-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
1600
Furnish and install tree;
complete as specified Each 14.00 0.00 -14.00 $634.00 ($8,876.00)
1650
Locate existing property
monuments; complete as
specified Each 21.00 25.00 4.00 $50.80 $203.20
1652
Replace existing property
monuments; complete as
specified Each 21.00 20.00 -1.00 $52.80 ($52.80)
1700
Sawing existing pavement;
complete as specified
Linear
Feet 700.00 684.36 -15.64 $2.10 ($32.84)
1710
Sawing concrete pavement
full depth; complete as
specified
Linear
Feet 410.00 364.48 -45.52 $3.90 ($177.53)
1900
Tack coat; complete as
specified Gallons 18.00 0.00 -18.00 $9.10 ($163.80)
1911
4" asphaltic transition LT
with 10" CABC and grading;
complete as specified
Square
Yards 200.00 190.73 -9.27 $58.50 ($542.30)
1916
4" asphaltic surface LT with
6" CABC and grading;
complete as specified
Square
Yards 70.00 40.90 -29.10 $78.00 ($2,269.80)
1917
2" asphaltic surface LT with
6" CABC and grading;
complete as specified
Square
Yards 50.00 0.00 -50.00 $79.90 ($3,995.00)
2003
Furnish and install 12" storm
sewer; complete as specified
Linear
Feet 325.00 274.50 -50.50 $62.00 ($3,131.00)
2009
Furnish and install 18" storm
sewer; complete as specified
Linear
Feet 660.00 648.50 -11.50 $76.00 ($874.00)
2015
Furnish and install 24" storm
sewer; complete as specified
Linear
Feet 875.00 859.50 -15.50 $101.00 ($1,565.50)
2021
Furnish and install 30" storm
sewer; complete as specified
Linear
Feet 20.00 0.00 -20.00 $188.00 ($3,760.00)
2201
Furnish and install standard
storm sewer manhole (4'
diameter); complete as
specified
Vertical
Feet 59.00 56.86 -2.14 $761.00 ($1,628.53)
2202
Furnish and install standard
storm sewer manhole (5'
diameter); complete as
specified
Vertical
Feet 10.40 10.43 0.03 $1,029.00 $30.87
2203
Furnish and install standard
storm sewer manhole (6'
diameter); complete as
specified
Vertical
Feet 7.25 0.00 -7.25 $1,310.00 ($9,497.50)
2235
Furnish and install Type 1
inlet (with 18" sump);
complete as specified Each 1.00 2.00 1.00 $3,461.00 $3,461.00
Page 4 of 11
Docusign Envelope ID: 6D99D7F9-EBD2-4463-9438-58643845DDBD
25-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
2237
Furnish and install Type 3
inlet (with 18" sump);
complete as specified Each 20.00 18.00 -2.00 $3,172.00 ($6,344.00)
2400
Furnish and install 6" storm
sewer lateral; complete as
specified
Linear
Feet 1,200.00 1,047.50 -152.50 $55.00 ($8,387.50)
2402
Furnish and install 8" storm
sewer lateral; complete as
specified
Linear
Feet 50.00 0.00 -50.00 $62.00 ($3,100.00)
2404
Furnish and install storm
sewer marker balls;
complete as specified Each 70.00 66.00 -4.00 $29.00 ($116.00)
2406
Furnish and install storm
sewer clay dams; complete
as specified Each 35.00 32.00 -3.00 $122.00 ($366.00)
2408
Furnish and install storm
sewer lateral inlet; complete
as specified Each 32.00 31.00 -1.00 $1,420.00 ($1,420.00)
2414
Storm lateral inlet
adjustments; complete as
specified Each 32.00 1.00 -31.00 $122.00 ($3,782.00)
2508
Furnish; install; maintain;
and remove Type D modified
inlet protection; complete as
specified Each 45.00 45.00 $115.00
2510
Sediment removal - Type D
modified inlet protection;
complete as specified Each 45.00 0.00 -45.00 $10.00 ($450.00)
2512
Furnish; install; maintain;
and remove stone tracking
pad; complete as specified Each 3.00 0.00 -3.00 $500.00 ($1,500.00)
2516
Furnish; install; maintain;
and remove stone bag;
complete as specified Each 45.00 0.00 -45.00 $15.00 ($675.00)
2518
Furnish; install; maintain;
and remove 12" diameter
sediment logs; complete as
specified
Linear
Feet 100.00 0.00 -100.00 $12.00 ($1,200.00)
2524
Furnish; install; maintain;
and remove dewatering tank
system; complete as
specified Each 1.00 0.00 -1.00 $3,000.00 ($3,000.00)
2800
Abandon 8" - 12" storm
sewer; complete as specified
Linear
Feet 30.00 25.00 -5.00 $15.00 ($75.00)
2802
Abandon 15" and larger
storm sewer; complete as
specified
Linear
Feet 30.00 0.00 -30.00 $30.00 ($900.00)
2804
Remove 30" and smaller
storm sewer; complete as
specified
Linear
Feet 400.00 371.00 -29.00 $27.00 ($783.00)
Page 5 of 11
Docusign Envelope ID: 6D99D7F9-EBD2-4463-9438-58643845DDBD
25-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
2810
Abandon storm sewer
manholes and inlets;
complete as specified Each 2.00 2.00 $410.00
2812
Remove storm sewer
manholes and inlets;
complete as specified Each 12.00 12.00 $559.00
2850
Connect to existing storm
sewer main; complete as
specified Each 5.00 1.00 -4.00 $1,870.00 ($7,480.00)
2852
Connect to existing storm
sewer lateral; complete as
specified Each 4.00 0.00 -4.00 $410.00 ($1,640.00)
2856
Connect to existing storm
sewer manhole; complete as
specified Each 1.00 2.00 1.00 $1,377.00 $1,377.00
2858
Connect to existing storm
sewer inlet; complete as
specified Each 1.00 0.00 -1.00 $1,195.00 ($1,195.00)
2914
Storm sewer utility line
opening (ULO); complete as
specified Each 5.00 0.00 -5.00 $1,476.00 ($7,380.00)
2950
Excavation special (storm);
complete as specified Tons 50.00 0.00 -50.00 $21.00 ($1,050.00)
3000
Furnish and install 8"
sanitary sewer (relay);
complete as specified
Linear
Feet 1,650.00 1,627.50 -22.50 $118.00 ($2,655.00)
3100
Furnish and install standard
sanitary sewer manhole (4'
diameter); complete as
specified
Vertical
Feet 58.00 56.14 -1.86 $693.00 ($1,288.98)
3114
Furnish and install sanitary
sewer external manhole
chimney seal; complete as
specified Each 8.00 7.00 -1.00 $558.00 ($558.00)
3116
Furnish and install sanitary
sewer external manhole
chimney seal extension;
complete as specified Each 2.00 0.00 -2.00 $508.00 ($1,016.00)
3200
Furnish and install 8" x 4"
sanitary sewer factory wyes
or tees; complete as
specified Each 3.00 5.00 2.00 $166.00 $332.00
3210
Furnish and install 8" x 6"
sanitary sewer factory wyes
or tees; complete as
specified Each 35.00 28.00 -7.00 $223.00 ($1,561.00)
3230
Furnish and install 4"
sanitary sewer laterals
(new); complete as specified
Linear
Feet 80.00 25.00 -55.00 $76.00 ($4,180.00)
Page 6 of 11
Docusign Envelope ID: 6D99D7F9-EBD2-4463-9438-58643845DDBD
25-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
3232
Furnish and install 6"
sanitary sewer laterals
(new); complete as specified
Linear
Feet 30.00 0.00 -30.00 $80.00 ($2,400.00)
3234
Furnish and install 4"/6"
sanitary sewer lateral (relay);
complete as specified
Linear
Feet 1,250.00 1,060.00 -190.00 $81.00 ($15,390.00)
3235
Furnish and install 4"/6"
sanitary sewer riser (relay);
complete as specified
Linear
Feet 45.00 0.00 -45.00 $101.00 ($4,545.00)
3236
Furnish and install sanitary
sewer lateral marker balls;
complete as specified Each 77.00 65.00 -12.00 $29.00 ($348.00)
3238
Furnish and install clay
dams; complete as specified Each 37.00 30.00 -7.00 $122.00 ($854.00)
3300
Furnish and install
connection to existing 8"
sanitary sewer mains;
complete as specified Each 5.00 5.00 $2,051.00
3330
Furnish and install sanitary
sewer concrete collars;
complete as specified Each 2.00 0.00 -2.00 $745.00 ($1,490.00)
3600
Rock excavation; complete
as specified
Cubic
Yards 50.00 0.00 -50.00 $0.01 ($0.50)
3700
Closed circuit televising;
complete as specified
Linear
Feet 1,650.00 1,797.20 147.20 $2.00 $294.40
3710
Closed circuit televising -
using push camera;
complete as specified Each 4.00 0.00 -4.00 $243.00 ($972.00)
3800
Abandon sanitary sewer
manholes; complete as
specified Each 1.00 1.00 $476.00
3802
Abandon 8" sanitary sewer;
complete as specified
Linear
Feet 40.00 0.00 -40.00 $6.00 ($240.00)
3852
Remove sanitary sewer
manholes; complete as
specified Each 3.00 3.00 $400.00
3854
Remove sanitary sewer;
complete as specified
Linear
Feet 80.00 83.50 3.50 $277.00 $969.50
3890
Sanitary sewer utility line
opening (ULO); complete as
specified Each 2.00 0.00 -2.00 $2,221.00 ($4,442.00)
3892
Excavation special
(sanitary); complete as
specified Tons 20.00 0.00 -20.00 $21.00 ($420.00)
4000
Furnish and install 4" ductile
iron water main (relay) with
polywrap; complete as
specified
Linear
Feet 40.00 2.00 -38.00 $137.00 ($5,206.00)
Page 7 of 11
Docusign Envelope ID: 6D99D7F9-EBD2-4463-9438-58643845DDBD
25-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
4002
Furnish and install 6" ductile
iron water main (relay) with
polywrap; complete as
specified
Linear
Feet 125.00 114.00 -11.00 $119.00 ($1,309.00)
4004
Furnish and install 8" ductile
iron water main (relay) with
polywrap; complete as
specified
Linear
Feet 1,880.00 1,858.00 -22.00 $130.00 ($2,860.00)
4008
Furnish and install 12"
ductile iron wtaer main
(relay) with polywrap;
complete as specified
Linear
Feet 20.00 45.00 25.00 $196.00 $4,900.00
4036
Furnish and install 1" water
service (relay); complete as
specified
Linear
Feet 1,100.00 977.60 -122.40 $76.00 ($9,302.40)
4037
Furnish and install 1-1/4"
water service (relay);
complete as specified
Linear
Feet 50.00 0.00 -50.00 $82.00 ($4,100.00)
4042
Furnish and install 1" water
service (new); complete as
specified
Linear
Feet 50.00 2.00 -48.00 $76.00 ($3,648.00)
4046
Furnish and install 2" water
service (new); complete as
specified
Linear
Feet 50.00 77.20 27.20 $92.00 $2,502.40
4048
Furnish and install 1"
corporation and stop box;
complete as specified Each 33.00 32.00 -1.00 $566.00 ($566.00)
4050
Furnish and install 1-1/4"
corporation and stop box;
complete as specified Each 2.00 0.00 -2.00 $1,082.00 ($2,164.00)
4054
Furnish and install 2" stop
box and rod only; complete
as specified Each 1.00 2.00 1.00 $1,584.00 $1,584.00
4055
Furnish and install water
service clay dams; complete
as specified Each 34.00 32.00 -2.00 $183.00 ($366.00)
4056
Furnish and install
connections to existing 4"
water main; complete as
specified Each 1.00 1.00 $2,389.00
4058
Furnish and install
connections to existing 6"
water main; complete as
specified Each 4.00 3.00 -1.00 $2,655.00 ($2,655.00)
4060
Furnish and install
connections to existing 8"
water main; complete as
specified Each 1.00 1.00 $3,026.00
4064
Furnish and install
connections to existing 12"
water main; complete as
specified Each 2.00 4.00 2.00 $3,676.00 $7,352.00
Page 8 of 11
Docusign Envelope ID: 6D99D7F9-EBD2-4463-9438-58643845DDBD
25-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
4080
Temporary water main;
complete as specified Each 1.00 1.00 $8,887.00
4109
Furnish and install 8" x 4"
water main tee; complete as
specified Each 1.00 0.00 -1.00 $786.00 ($786.00)
4110
Furnish and install 8" x 6"
water main tee; complete as
specified Each 4.00 4.00 $885.00
4111
Furnish and install 8" x 8"
water main tee; complete as
specified Each 1.00 1.00 $983.00
4129
Furnish and install 12" x 8"
water main tee; complete as
specified Each 1.00 2.00 1.00 $1,458.00 $1,458.00
4189
Furnish and install 8" x 8"
water main cross; complete
as specified Each 1.00 1.00 $1,143.00
4236
Furnish and install 6" 45
degree water main bend;
complete as specified Each 16.00 12.00 -4.00 $443.00 ($1,772.00)
4237
Furnish and install 8" 45
degree water main bend;
complete as specified Each 10.00 10.00 $586.00
4262
Furnish and install 6" x 4"
water main reducer;
complete as specified Each 1.00 1.00 $383.00
4264
Furnish and install 8" x 6"
water main reducer;
complete as specified Each 4.00 4.00 $525.00
4350
Cut and cap existing 4"
water main; complete as
specified Each 1.00 1.00 $1,308.00
4352
Cut and cap existing 6"
water main; complete as
specified Each 2.00 2.00 $1,363.00
4354
Cut and cap existing 8"
water main; complete as
specified Each 2.00 2.00 $1,623.00
4400
Furnish and install 4" water
main gate valve; complete
as specified Each 1.00 0.00 -1.00 $1,756.00 ($1,756.00)
4401
Furnish and install 6" water
main gate valve; complete
as specified Each 6.00 6.00 $2,051.00
4402
Furnish and install 8" water
main gate valve; complete
as specified Each 12.00 12.00 $2,852.00
4404
Furnish and install 12" water
main gate valve; complete
as specified Each 2.00 2.00 $4,968.00
Page 9 of 11
Docusign Envelope ID: 6D99D7F9-EBD2-4463-9438-58643845DDBD
25-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
4447
Furnish and install 12" x 8"
tapping valve and sleeve;
complete as specified Each 1.00 0.00 -1.00 $7,333.00 ($7,333.00)
4500
Furnish and install hydrant;
complete as specified Each 4.00 4.00 $6,412.00
4800
Rock excavation; complete
as specified
Cubic
Yards 20.00 0.00 -20.00 $0.01 ($0.20)
4900
Abandon water main on
STREET NAME; complete
as specified
Lump
Sum 1.00 1.00 $2,677.00
4920
Remove water main;
complete as specified
Linear
Feet 600.00 618.00 18.00 $38.00 $684.00
4990
Excavation special (water);
complete as specified Tons 20.00 0.00 -20.00 $21.00 ($420.00)
5012
Furnish and install pull box
(steel); 18" x 36"; complete
as specified Each 15.00 13.00 -2.00 $1,167.00 ($2,334.00)
5025
Adjust pull box; complete as
specified Each 15.00 13.00 -2.00 $107.10 ($214.20)
5130
Furnish and install 3"
Schedule 40 PVC; complete
as specified
Linear
Feet 2,250.00 2,178.00 -72.00 $13.20 ($950.40)
5170
3" Schedule 40 PVC bore;
including bore pits and utility
line openings; complete as
specified
Linear
Feet 84.00 79.00 -5.00 $81.10 ($405.50)
5180
Connect to existing pull box;
complete as specified Each 1.00 1.00 $305.00
5230
Furnish and install 4 gauge
red-coated wire; complete as
specified
Linear
Feet 3,650.00 3,502.00 -148.00 $2.50 ($370.00)
5231
Furnish and install 4 gauge
black-coated wire; complete
as specified
Linear
Feet 3,650.00 3,502.00 -148.00 $2.50 ($370.00)
5262
Furnish and install 10 gauge
green-coated wire; complete
as specified
Linear
Feet 2,650.00 2,518.00 -132.00 $1.00 ($132.00)
5270
Furnish and install 12 gauge
red-coated wire; complete as
specified
Linear
Feet 560.00 490.00 -70.00 $0.80 ($56.00)
5271
Furnish and install 12 gauge
black-coated wire; complete
as specified
Linear
Feet 560.00 490.00 -70.00 $0.80 ($56.00)
5272
Furnish and install 12 gauge
green-coated wire; complete
as specified
Linear
Feet 560.00 490.00 -70.00 $0.80 ($56.00)
5380
Furnish and install fuse
holder; complete as
specified Each 32.00 28.00 -4.00 $51.00 ($204.00)
Page 10 of 11
Docusign Envelope ID: 6D99D7F9-EBD2-4463-9438-58643845DDBD
25-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
5386
Furnish and install 2A fuse;
complete as specified Each 32.00 28.00 -4.00 $5.60 ($22.40)
5454
Install CITY-supplied 10?
truss-type luminaire arm;
complete as specified Each 16.00 14.00 -2.00 $254.00 ($508.00)
5460
Install CITY-supplied cobra
head luminaire; complete as
specified Each 16.00 14.00 -2.00 $203.00 ($406.00)
5494
Install CITY-supplied 20'
tapered pole with
transformer base; complete
as specified Each 16.00 14.00 -2.00 $812.00 ($1,624.00)
5504
Furnish and install Type 5
base; complete as specified Each 16.00 14.00 -2.00 $1,117.00 ($2,234.00)
SECTION I (BID ITEMS 1011 - 5504) - SUBTOTAL: $42,057.07 ($222,677.25)
NET DECREASE TO SECTION I: ($180,620.18)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
1-20000
Storm metal plate
cover;complete as specified
Lump
Sum 0.00 1.00 1.00 $3,200.00 $3,200.00
1-20001
N31 Structure (structure not
used); complete as specified
Lump
Sum 0.00 1.00 1.00 $3,468.93 $3,468.93
$6,668.93 $0.00
$6,668.93
($180,620.18)
$6,668.93
NET DECREASE TO CONTRACT: ($173,951.25)
ADDITIONAL WORK REQUIRED: FUTURE CO #1
ADDITIONAL WORK (ITEMS ) SUBTOTAL:
NET INCREASE:
NET INCREASE TO ADDITIONAL WORK:
NET DECREASE TO SECTION I:
Page 11 of 11