PUBLIC SERVICE COMMISSION OF WISCONSIN
Application of American Transmission Company LLC, as an Electric 137-CE-208
Public Utility, for a Certificate of Public Convenience and Necessity to
Construct the Eldorado Substation and Associated Network Upgrades to
Lines G-111 and X-50 (Silver Maple Solar Interconnection Project)
Located Primarily in the Village of North Fond du Lac and Towns of
Eldorado and Friendship, Fond du Lac County, and the City of Oshkosh
and Town of Nekimi, Winnebago County, Wisconsin
ORDER TO CANCEL THE SCHEDULE OF FILINGS AND HEARINGS
This Order, pursuant to Wis. Admin. Code § PSC 2.04(1), based on the Applicant's
unopposed Silver Maple CPCN Notice of Withdrawal (PSC REF#: 521879) in which the
Applicant requested to withdraw the application, cancels the schedule of filings ordered in the
Scheduling Order (PSC REF#: 515435).
This Order also cancels the following hearings established in the Notice of Hearing PSC
REF#: 520059):
• Public Hearing Session: Wednesday, November 13, 2024 — 2:00p.m. and 6:00p.m. CT
at the Community Center Town of Eldorado N7664 County C Eldorado, Wisconsin
and on Zoom; and
• Party Hearing Session: Tuesday, December 3, 2024 - 10:00 AM CT on Zoom only.
This Order effects no disposal of this proceeding. Such action requires a Commission
decision under Wis. Admin. Code § PSC 2.04(2)(d).
Michael E. Newmark
Administrative Law Judge
MEN: : DL:02039202
G