HomeMy WebLinkAbout23-20 CO #1 (FINAL)_8-14-24TO: WOOD SEWER & EXCAVATING CHANGE ORDER #1 (FINAL)
E9238 COUNTY RD X
NEW LONDON, WI 54961
Your present contract with the City of Oshkosh, Contract No. 23-20, awarded May 9, 2023, is hereby amended
and changed as follows:
NET DECREASE TO SECTION I: ($62,666.49)
$13,200.95
NET DECREASE TO CONTRACT ($49,465.54)
SECTION I TOTALS
BID TOTAL $830,256.73 $830,256.73
CO #1 ($49,465.54)($49,465.54)
CONTRACT TOTAL $780,791.19 $780,791.19
CITY OF OSHKOSH
BY:
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Approved as to form:
City Attorney
DATE: AUGUST 14, 2024
______________________________
Comptroller
______________________________
Contractor
______________________________
Approved and accepted:
______________________________
City Manager
City Clerk
______________________________
NET INCREASE TO ADDITIONAL WORK:
Docusign Envelope ID: 0FA2116C-171C-4CA8-B7BD-9FBDE9904771
CONTRACT 23-20 CHANGE ORDER #1 (FINAL)
23-20
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
1010
Clearing; complete as
specified Stations 1.85 1.85 $1,600.00
1020
Grubbing; complete as
specified Stations 1.85 1.85 $1,600.00
1100
Removing pavement;
complete as specified
Square
Yards 813.00 923.67 110.67 $7.00 $774.69
1120
Removing concrete and
asphalt sidewalk and
driveway; complete as
specified
Square
Feet 2,110.00 1,293.46 -816.54 $1.40 ($1,143.16)
1226
Dredge material; load;
transport; and dispose of
dewatered sediment;
complete as specified
Cubic
Yards 25.00 0.00 -25.00 $77.50 ($1,937.50)
1308
7" concrete pavement
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and fine
grading; turf restoration; and
traffic control; complete as
specified
Square
Yards 1,597.00 1,318.98 -278.02 $101.00 ($28,080.02)
1318
8" concrete pavement
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and fine
grading; turf restoration; and
traffic control; complete as
specified
Square
Yards 33.00 237.04 204.04 $107.00 $21,832.28
1319
8" concrete pavement HES
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and fine
grading; turf restoration; and
traffic control; complete as
specified
Square
Yards 119.00 118.31 -0.69 $112.00 ($77.28)
1360
Adjust manholes and inlets;
complete as specified Each 4.00 3.00 -1.00 $1,411.00 ($1,411.00)
1370
Turf restoration; complete as
specified
Square
Yards 649.90 474.89 -175.01 $9.50 ($1,662.60)
1500
4" concrete sidewalk with 3"
CABC and grading; complete
as specified
Square
Feet 1,525.00 978.14 -546.86 $9.00 ($4,921.74)
1510
6" concrete sidewalk/
driveway/ramp with 3" CABC
and grading; complete as
specified
Square
Feet 460.00 236.00 -224.00 $10.00 ($2,240.00)
Page 2 of 5
Docusign Envelope ID: 0FA2116C-171C-4CA8-B7BD-9FBDE9904771
CONTRACT 23-20 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
1550
No. 4 reinforcing rods -
deformed; epoxy-coated;
complete as specified
Linear
Feet 895.00 200.00 -695.00 $2.40 ($1,668.00)
1560
Drilled No. 4 sidewalk tie bars
- deformed; epoxy-coated;
complete as specified Each 124.00 129.00 5.00 $9.70 $48.50
1700
Sawing existing pavement;
complete as specified
Linear
Feet 885.00 775.50 -109.50 $2.80 ($306.60)
1900
Tack coat; complete as
specified Gallons 57.00 64.60 7.60 $7.90 $60.04
1906
4" asphaltic pavement LT with
10" CABC and grading;
complete as specified
Square
Yards 858.00 923.67 65.67 $61.00 $4,005.87
2001
Furnish and install 8" storm
sewer; complete as specified
Linear
Feet 40.00 37.60 -2.40 $77.00 ($184.80)
2003
Furnish and install 12" storm
sewer; complete as specified
Linear
Feet 825.00 438.50 -386.50 $80.50 ($31,113.25)
2004
Furnish and install 12" RCP
Class III storm sewer;
complete as specified
Linear
Feet 210.00 507.00 297.00 $89.50 $26,581.50
2006
Furnish and install 15" storm
sewer; complete as specified
Linear
Feet 577.00 426.60 -150.40 $87.00 ($13,084.80)
2007
Furnish and install 15" RCP
Class III storm sewer;
complete as specified
Linear
Feet 121.00 134.50 13.50 $91.50 $1,235.25
2009
Furnish and install 18" storm
sewer; complete as specified
Linear
Feet 190.00 158.00 -32.00 $515.00 ($16,480.00)
2016
Furnish and install 24" RCP
Class III storm sewer;
complete as specified
Linear
Feet 63.00 48.00 -15.00 $342.00 ($5,130.00)
2140
Furnish and install 12" RCP
Class III apron endwall with
joint ties; complete as
specified Each 1.00 1.00 $2,872.00
2142
Furnish and install 18" RCP
Class III apron endwall with
joint ties; complete as
specified Each 1.00 1.00 $2,598.00
2201
Furnish and install standard
storm sewer manhole (4'
diameter); complete as
specified
Vertical
Feet 46.07 42.95 -3.12 $974.00 ($3,038.88)
2203
Furnish and install standard
storm sewer manhole (6'
diameter); complete as
specified
Vertical
Feet 4.29 3.12 -1.17 $1,720.00 ($2,012.40)
2237
Furnish and install Type 3
inlet (with 18" sump);
complete as specified Each 4.00 3.00 -1.00 $3,692.00 ($3,692.00)
Page 3 of 5
Docusign Envelope ID: 0FA2116C-171C-4CA8-B7BD-9FBDE9904771
CONTRACT 23-20 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
2400
Furnish and install 6" storm
sewer lateral; complete as
specified
Linear
Feet 1,261.00 1,261.50 0.50 $100.00 $50.00
2404
Furnish and install storm
sewer marker balls; complete
as specified Each 80.00 83.00 3.00 $40.00 $120.00
2406
Furnish and install storm
sewer clay dams; complete
as specified Each 41.00 42.00 1.00 $110.00 $110.00
2408
Furnish and install storm
sewer lateral inlet; complete
as specified Each 15.00 19.00 4.00 $1,129.00 $4,516.00
2508
Furnish; install; maintain; and
remove Type D modified inlet
protection; complete as
specified Each 65.00 24.00 -41.00 $85.00 ($3,485.00)
2516
Furnish; install; maintain; and
remove stone bag; complete
as specified Each 49.00 22.00 -27.00 $12.00 ($324.00)
2518
Furnish; install; maintain; and
remove 12" diameter
sediment logs; complete as
specified
Linear
Feet 65.00 80.00 15.00 $18.00 $270.00
2524
Furnish; install; maintain; and
remove dewatering tank
system; complete as
specified Each 2.00 0.00 -2.00 $1,822.00 ($3,644.00)
2526
Furnish; install; maintain; and
remove turbidity barrier;
complete as specified Each 3.00 3.00 $4,980.00
2632
Furnish and install Class I;
Urban; Type A erosion control
mat; complete as specified
Square
Yards 308.00 381.28 73.28 $6.10 $447.01
2650
Furnish and install heavy rip-
rap with filter fabric; complete
as specified
Square
Yards 35.00 20.00 -15.00 $99.00 ($1,485.00)
2800
Abandon 8" - 12" storm
sewer; complete as specified
Linear
Feet 159.00 56.00 -103.00 $5.70 ($587.10)
2804
Remove 30" and smaller
storm sewer; complete as
specified
Linear
Feet 36.00 81.00 45.00 $32.50 $1,462.50
2810
Abandon storm sewer
manholes and inlets;
complete as specified Each 2.00 2.00 $911.00
2850
Connect to existing storm
sewer main; complete as
specified Each 27.00 35.00 8.00 $486.00 $3,888.00
2852
Connect to existing storm
sewer main; complete as
specified Each 2.00 6.00 4.00 $425.00 $1,700.00
Page 4 of 5
Docusign Envelope ID: 0FA2116C-171C-4CA8-B7BD-9FBDE9904771
CONTRACT 23-20 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
2856
Connect to existing storm
sewer manhole; complete as
specified Each 4.00 3.00 -1.00 $618.00 ($618.00)
2858
Connect to existing storm
sewer inlet; complete as
specified Each 5.00 4.00 -1.00 $414.00 ($414.00)
3114
Furnish and install sanitary
sewer external manhole
chimney seal; complete as
specified Each 1.00 0.00 -1.00 $1,027.00 ($1,027.00)
SECTION I (BID ITEMS 1010 - 3114) - SUBTOTAL: $67,101.64 ($129,768.13)
NET DECREASE TO SECTION I: ($62,666.49)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
1-1200
Unclassified excavation;
complete as specified
Cubic
Yards 0.00 22.40 22.40 $41.40 $927.36
1-1440
30" curb and gutter; complete
as specified
Linear
Feet 0.00 31.00 31.00 $75.00 $2,325.00
1-1801
Base aggregate dense; 1
1/4"; complete as specified Ton 0.00 44.80 44.80 $29.95 $1,341.76
1-2010
Furnish and install 18" RCP
Class III storm sewer;
complete as specified
Linear
Feet 0.00 25.00 25.00 $114.75 $2,868.75
1-2047
Furnish and install 19" x 30"
HERCP Class III storm
sewer; complete as specified
Linear
Feet 0.00 6.00 6.00 $194.75 $1,168.50
1-3120
Furnish and install sanitary
sewer internal chimney seal;
complete as specified Each 0.00 2.00 2.00 $1,225.00 $2,450.00
1-10000
Central Street additional work
(mobilization/lateral inlet);
complete as specified
Lump
Sum 0.00 1.00 1.00 $2,119.58 $2,119.58
$13,200.95 $0.00
$13,200.95
($62,666.49)
$13,200.95
($49,465.54)NET DECREASE TO CONTRACT:
ADDITIONAL WORK REQUIRED: CO #1
ADDITIONAL WORK REQUIRED: CO #1 SUBTOTAL:
NET INCREASE:
NET DECREASE TO SECTION I:
NET INCREASE TO ADDITIONAL WORK:
Page 5 of 5
Docusign Envelope ID: 0FA2116C-171C-4CA8-B7BD-9FBDE9904771