Loading...
HomeMy WebLinkAbout24-20 CO #1 (FINAL)_3-17-25TO: HIGHWAY LANDSCAPERS, INC. CHANGE ORDER #1 (FINAL) 1650 EAST ELM DRIVE LITTLE CHUTE, WI 54140 Your present contract with the City of Oshkosh, Contract No. 24-20, awarded June 25, 2024, is hereby amended and changed as follows: NET DECREASE TO SECTION I: ($85,337.49) $6,471.29 NET DECREASE TO CONTRACT ($78,866.20) SECTION I TOTALS BID TOTAL $495,855.00 $495,855.00 CO #1 ($78,866.20)($78,866.20) CONTRACT TOTAL $416,988.80 $416,988.80 CITY OF OSHKOSH BY: I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. Approved as to form: City Attorney DATE: MARCH 17, 2025 ______________________________ Comptroller ______________________________ Contractor ______________________________ Approved and accepted: ______________________________ City Manager City Clerk ______________________________ NET INCREASE TO ADDITIONAL WORK: Docusign Envelope ID: 780067EF-6F06-4BBB-8895-9CC7A3260211 CONTRACT 24-20 CHANGE ORDER #1 (FINAL) 24-20 ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1010 Clearing; complete as specified Stations 1.00 1.00 $4,500.00 1011 Clearing; complete as specified Inch Diameter 36.00 36.00 $75.00 1020 Grubbing; complete as specified Stations 1.00 1.00 $1,500.00 1021 Grubbing; complete as specified Inch Diameter 36.00 36.00 $75.00 1050 Mobilization; complete as specified Lump Sum 1.00 1.00 $36,000.00 1120 Removing concrete and asphalt sidewalk and driveway; complete as specified Square Feet 1,400.00 1,066.32 -333.68 $8.00 ($2,669.44) 1226 Dredge material; load; transport; and dispose of dewatered sediment; complete as specified Cubic Yards 200.00 9.00 -191.00 $75.00 ($14,325.00) 1308 7" concrete pavement removal and replacement; including sawing; pavement ties; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete as specified Square Yards 420.00 405.37 -14.63 $150.00 ($2,194.50) 1319 8" concrete pavement HES removal and replacement; including sawing; pavement ties; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete as specified Square Yards 210.00 201.55 -8.45 $160.00 ($1,352.00) 1370 Turf restoration; complete as specified Square Yards 1,600.00 1,027.65 -572.35 $9.00 ($5,151.15) 1448 30" concrete curb and gutter removal and replacement; including sawing; pavement ties; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete as specified Linear Feet 15.00 40.00 25.00 $130.00 $3,250.00 1500 4" concrete sidewalk with 3" CABC and grading; complete as specified Square Feet 850.00 607.50 -242.50 $12.00 ($2,910.00) Page 2 of 6 Docusign Envelope ID: 780067EF-6F06-4BBB-8895-9CC7A3260211 CONTRACT 24-20 CHANGE ORDER #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1510 6" concrete sidewalk/ driveway/ramp with 3" CABC and grading; complete as specified Square Feet 350.00 318.92 -31.08 $14.00 ($435.12) 1514 6" concrete sidewalk/ driveway/ramp (HES) with 3" CABC and grading; complete as specified Square Feet 175.00 139.90 -35.10 $16.00 ($561.60) 1550 No. 4 reinforcing rods - deformed; epoxy-coated; complete as specified Linear Feet 550.00 164.00 -386.00 $5.00 ($1,930.00) 1560 Drilled No. 4 sidewalk tie bars - deformed; epoxy-coated; complete as specified Each 75.00 79.00 4.00 $8.00 $32.00 1650 Locate existing property monuments; complete as specified Each 1.00 1.00 $750.00 1652 Replace existing property monuments; complete as specified Each 1.00 1.00 $1,000.00 1904 Remove and replace HMA pavement; including sawing; fine grading; turf restoration; and traffic control; complete as specified Square Yards 80.00 75.80 -4.20 $100.00 ($420.00) 2000 Furnish and install 6" storm sewer; complete as specified Linear Feet 125.00 83.00 -42.00 $65.00 ($2,730.00) 2001 Furnish and install 8" storm sewer; complete as specified Linear Feet 125.00 111.60 -13.40 $75.00 ($1,005.00) 2003 Furnish and install 12" storm sewer; complete as specified Linear Feet 300.00 279.50 -20.50 $85.00 ($1,742.50) 2009 Furnish and install 18" storm sewer; complete as specified Linear Feet 110.00 93.60 -16.40 $105.00 ($1,722.00) 2015 Furnish and install 24" storm sewer; complete as specified Linear Feet 210.00 177.50 -32.50 $125.00 ($4,062.50) 2021 Furnish and install 30" storm sewer; complete as specified Linear Feet 45.00 23.00 -22.00 $155.00 ($3,410.00) 2142 Furnish and install 18" RCP Class III apron endwall with joint ties; complete as specified Each 1.00 1.00 $1,500.00 2144 Furnish and install 24" RCP Class III apron endwall with joint ties; complete as specified Each 1.00 1.00 $2,000.00 2146 Furnish and install 30" RCP Class III apron endwall with joint ties; complete as specified Each 1.00 1.00 $2,500.00 Page 3 of 6 Docusign Envelope ID: 780067EF-6F06-4BBB-8895-9CC7A3260211 CONTRACT 24-20 CHANGE ORDER #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 2201 Furnish and install standard storm sewer manhole (4' diameter); complete as specified Vertical Feet 3.15 6.78 3.63 $900.00 $3,267.00 2202 Furnish and install standard storm sewer manhole (5' diameter); complete as specified Vertical Feet 7.25 7.16 -0.09 $1,000.00 ($90.00) 2213 Furnish and install standard storm sewer inlet manhole (4' diameter); complete as specified Vertical Feet 7.10 3.32 -3.78 $900.00 ($3,402.00) 2235 Furnish and install Type 1 inlet (with 18" sump); complete as specified Each 1.00 1.00 $3,300.00 2237 Furnish and install Type 3 inlet (with 18" sump); complete as specified Each 5.00 1.00 -4.00 $3,700.00 ($14,800.00) 2400 Furnish and install 6" storm sewer lateral; complete as specified Linear Feet 500.00 457.00 -43.00 $55.00 ($2,365.00) 2404 Furnish and install storm sewer marker balls; complete as specified Each 40.00 37.00 -3.00 $100.00 ($300.00) 2406 Furnish and install storm sewer clay dams; complete as specified Each 20.00 19.00 -1.00 $750.00 ($750.00) 2408 Furnish and install storm sewer lateral inlet; complete as specified Each 5.00 3.00 -2.00 $1,250.00 ($2,500.00) 2414 Storm lateral inlet adjustments; complete as specified Each 5.00 3.00 -2.00 $950.00 ($1,900.00) 2418 Cleanouts; complete as specified Each 5.00 4.00 -1.00 $850.00 ($850.00) 2500 Furnish; install; maintain; and remove Type A inlet protection; complete as specified Each 50.00 5.00 -45.00 $150.00 ($6,750.00) 2516 Furnish; install; maintain; and remove stone bag; complete as specified Each 60.00 0.00 -60.00 $12.50 ($750.00) 2518 Furnish; install; maintain; and remove 12" diameter sediment logs; complete as specified Linear Feet 100.00 30.00 -70.00 $12.00 ($840.00) 2524 Furnish; install; maintain; and remove dewatering tank system; complete as specified Each 3.00 3.00 $12,500.00 Page 4 of 6 Docusign Envelope ID: 780067EF-6F06-4BBB-8895-9CC7A3260211 CONTRACT 24-20 CHANGE ORDER #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 2526 Furnish; install; maintain; and remove turbidity barrier; complete as specified Each 3.00 3.00 $3,000.00 2632 Furnish and install Class I; Urban; Type A erosion control mat; complete as specified Square Yards 460.00 790.44 330.44 $3.00 $991.32 2800 Abandon 8" - 12" storm sewer; complete as specified Linear Feet 25.00 13.00 -12.00 $5.00 ($60.00) 2802 Abandon 15" and larger storm sewer; complete as specified Linear Feet 100.00 65.00 -35.00 $10.00 ($350.00) 2810 Abandon storm sewer manholes and inlets; complete as specified Each 3.00 2.00 -1.00 $750.00 ($750.00) 2850 Connect to existing storm sewer main; complete as specified Each 4.00 2.00 -2.00 $750.00 ($1,500.00) 2852 Connect to existing storm sewer main; complete as specified Each 3.00 2.00 -1.00 $550.00 ($550.00) 2854 Connect lateral to existing storm sewer main; complete as specified Each 10.00 9.00 -1.00 $750.00 ($750.00) 2856 Connect to existing storm sewer manhole; complete as specified Each 2.00 1.00 -1.00 $750.00 ($750.00) 2858 Connect to existing storm sewer inlet; complete as specified Each 4.00 4.00 $750.00 2914 Storm sewer utility line opening (ULO); complete as specified Each 5.00 0.00 -5.00 $1,000.00 ($5,000.00) 2950 Excavation special (storm); complete as specified Tons 50.00 0.00 -50.00 $25.00 ($1,250.00) 5800 Furnish and install guard posts; complete as specified Each 1.00 1.00 $900.00 SECTION I (BID ITEMS 1010 - 5800) - SUBTOTAL: $7,540.32 ($92,877.81) NET DECREASE TO SECTION I: ($85,337.49) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1-20000 Waste Management dumping fee; complete as specified Lump Sum 0.00 1.00 1.00 $751.29 $751.29 ADDITIONAL WORK REQUIRED: CO #1 Page 5 of 6 Docusign Envelope ID: 780067EF-6F06-4BBB-8895-9CC7A3260211 CONTRACT 24-20 CHANGE ORDER #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1-20001 Re-mobilize and install lateral inlet on Witzel; complete as specified Lump Sum 0.00 1.00 1.00 $1,500.00 $1,500.00 1-20002 Pavement markings on Witzel Avenue; complete as specified Lump Sum 0.00 1.00 1.00 $3,845.00 $3,845.00 1-20003 Repair inlet on Locust Street; complete as specified Lump Sum 0.00 1.00 1.00 $375.00 $375.00 $6,471.29 $0.00 $6,471.29 ($85,337.49) $6,471.29 ($78,866.20)NET DECREASE TO CONTRACT: ADDITIONAL WORK REQUIRED: CO #1 SUBTOTAL: NET INCREASE: NET DECREASE TO SECTION I: NET INCREASE TO ADDITIONAL WORK: Page 6 of 6 Docusign Envelope ID: 780067EF-6F06-4BBB-8895-9CC7A3260211