HomeMy WebLinkAbout23-17 CO #1 (FINAL)_1-14-25TO: VINTON CONST COMPANY CHANGE ORDER #1 (FINAL)
1322 33RD STREET
TWO RIVERS, WI 54241
Your present contract with the City of Oshkosh, Contract No. 23-17, awarded August 22, 2023, is hereby amended
and changed as follows:
NET DECREASE TO SECTION I: ($26,537.87)
NET DECREASE TO ADDITIONAL WORK:$0.00
NET DECREASE TO CONTRACT ($26,537.87)
SECTION I TOTALS
BID TOTAL $1,183,361.75 $1,183,361.75
CO #1 ($26,537.87)($26,537.87)
CONTRACT TOTAL $1,156,823.88 $1,156,823.88
CITY OF OSHKOSH
BY:
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Approved as to form:
City Attorney
DATE: JANUARY 14, 2025
______________________________
Comptroller
______________________________
Contractor
______________________________
Approved and accepted:
______________________________
City Manager
City Clerk
______________________________
Docusign Envelope ID: 74916E77-1F85-4ABB-AACB-9EE52E2B307F
CONTRACT 23-17 CHANGE ORDER #1 (FINAL)
23-17
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
1050
Mobilization; complete as
specified
Lump
Sum 1.00 1.00 $152,000.00
1100
Removing pavement;
complete as specified
Square
Yards 60.00 0.00 -60.00 $20.00 ($1,200.00)
1120
Removing concrete and
asphalt sidewalk and
driveway; complete as
specified
Square
Feet 125.00 371.00 246.00 $2.50 $615.00
1311
8" concrete pavement; with
6" CABC and grading;
complete as specified
Square
Yards 60.00 0.00 -60.00 $85.00 ($5,100.00)
1350
Pavement ties; complete as
specified Each 10.00 0.00 -10.00 $10.00 ($100.00)
1354
Drilled dowel bars; 1 1/4";
complete as specified Each 10.00 0.00 -10.00 $16.50 ($165.00)
1500
4" concrete sidewalk with 3"
CABC and grading;
complete as specified
Square
Feet 125.00 210.00 85.00 $15.00 $1,275.00
1550
No. 4 reinforcing rods -
deformed; epoxy-coated;
complete as specified
Linear
Feet 25.00 42.00 17.00 $2.00 $34.00
1560
Drilled No. 4 sidewalk tie
bars - deformed; epoxy-
coated; complete as
specified Each 4.00 4.00 $7.00
1650
Locate existing property
monuments; complete as
specified Each 18.00 10.00 -8.00 $140.00 ($1,120.00)
1652
Replace existing property
monuments; complete as
specified Each 18.00 0.00 -18.00 $25.00 ($450.00)
1700
Sawing existing pavement;
complete as specified
Linear
Feet 10.00 10.00 $5.00
1710
Sawing concrete pavement
full depth; complete as
specified
Linear
Feet 37.00 0.00 -37.00 $5.00 ($185.00)
2001
Furnish and install 8" storm
sewer; complete as specified
Linear
Feet 117.00 117.50 0.50 $69.00 $34.50
2015
Furnish and install 24" storm
sewer; complete as specified
Linear
Feet 175.40 159.50 -15.90 $184.00 ($2,925.60)
2057
Furnish and install 43" x 68"
HERCP Class III storm
sewer; complete as specified
Linear
Feet 120.60 120.50 -0.10 $381.00 ($38.10)
2120
Furnish and install gravel
trench with underdrain;
complete as specified
Lump
Sum 1.00 1.00 $14,174.00
Page 2 of 5
Docusign Envelope ID: 74916E77-1F85-4ABB-AACB-9EE52E2B307F
CONTRACT 23-17 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
2144
Furnish and install 24" RCP
Class III apron endwall with
joint ties; complete as
specified Each 1.00 1.00 $2,785.00
2160
Furnish and install 43" x 68"
RCP Class III apron endwall
with joint ties; complete as
specified Each 1.00 1.00 $7,420.00
2201
Furnish and install standard
storm sewer manhole (4'
diameter); complete as
specified
Vertical
Feet 15.80 16.64 0.84 $807.00 $677.88
2208
Furnish and install standard
storm sewer manhole (5' x 5'
box); complete as specified
Vertical
Feet 8.60 7.73 -0.87 $1,940.00 ($1,687.80)
2226
Furnish and install storm
sewer outlet structure M-1;
complete as specified Each 1.00 1.00 $22,825.00
2502
Furnish; install; maintain;
and remove Type B inlet
protection; complete as
specified Each 1.00 0.00 -1.00 $72.24 ($72.24)
2508
Furnish; install; maintain;
and remove Type D modified
inlet protection; complete as
specified Each 7.00 10.00 3.00 $116.88 $350.64
2510
Sediment removal - Type D
modified inlet protection;
complete as specified Each 7.00 0.00 -7.00 $11.00 ($77.00)
2512
Furnish; install; maintain;
and remove stone tracking
pad; complete as specified Each 1.00 1.00 $8,500.00
2514
Furnish; install; maintain;
and remove silt fence;
complete as specified
Linear
Feet 1,953.00 1,050.30 -902.70 $3.16 ($2,852.53)
2602
Install salvaged topsoil 6"
depth; complete as specified
Square
Yards 7,224.00 6,831.00 -393.00 $3.00 ($1,179.00)
2610
Furnish and install native
seeding; complete as
specified
Square
Yards 1,780.00 1,726.00 -54.00 $1.35 ($72.90)
2612
Furnish and install native
seeding; complete as
specified
Square
Yards 2,641.00 2,552.00 -89.00 $1.28 ($113.92)
2620
Furnish and install turf grass;
complete as specified
Square
Yards 173.00 173.00 $1.27
2622
Furnish and install no-mow
fescue; complete as
specified
Square
Yards 2,772.00 2,346.00 -426.00 $0.89 ($379.14)
2630
Furnish and install Class I;
Type A erosion control mat;
complete as specified
Square
Yards 4,421.00 4,278.00 -143.00 $1.56 ($223.08)
Page 3 of 5
Docusign Envelope ID: 74916E77-1F85-4ABB-AACB-9EE52E2B307F
CONTRACT 23-17 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
2632
Furnish and install Class I;
Urban; Type A erosion
control mat; complete as
specified
Square
Yards 2,945.00 2,519.00 -426.00 $1.82 ($775.32)
2638
Furnish and install turf
reinforcement mat system;
complete as specified
Square
Yards 511.00 422.00 -89.00 $6.94 ($617.66)
2648
Furnish and install medium
rip-rap with filter fabric;
complete as specified
Square
Yards 61.00 64.50 3.50 $64.60 $226.10
2813
Furnish and install storm
sewer bulkhead in 43" x 68"
storm sewer line; complete
as specified Each 1.00 1.00 $1,500.00
2850
Connect to existing storm
sewer main; complete as
specified Each 1.00 1.00 $3,955.00
2902
Strip and stockpile topsoil;
complete as specified
Square
Yards 7,745.00 7,400.00 -345.00 $1.50 ($517.50)
2906
Clear trees; complete as
specified
Lump
Sum 1.00 1.00 $5,500.00
2907
Remove limbs from trees;
complete as specified
Lump
Sum 1.00 1.00 $1,000.00
2912
Grub stumps; complete as
specified
Lump
Sum 1.00 1.00 $5,500.00
2930
General excavation;
complete as specified
Lump
Sum 1.00 1.00 $269,000.00
2931
Excavation below subgrade -
detention basin; complete as
specified
Cubic
Yards 900.00 0.00 -900.00 $10.00 ($9,000.00)
2936
Construct clay berms and
emergency spillway;
complete as specified
Lump
Sum 1.00 1.00 $3,500.00
2937
Construct clay plug;
complete as specified Each 2.00 2.00 $1,060.00
2944
Furnish and install concrete
retaining wall; complete as
specified
Linear
Feet 1,272.00 1,272.00 $358.00
2956
Flag protection; complete as
specified Day 20.00 0.00 -20.00 $0.01 ($0.20)
3650
Crack and damage survey;
complete as specified Each 16.00 15.00 -1.00 $899.00 ($899.00)
SECTION I (BID ITEMS 1050 - 3991) - SUBTOTAL: $3,213.12 ($29,750.99)
NET DECREASE TO SECTION I: ($26,537.87)
Page 4 of 5
Docusign Envelope ID: 74916E77-1F85-4ABB-AACB-9EE52E2B307F
CONTRACT 23-17 CHANGE ORDER #1 (FINAL)
SECTION 2: ALTERNATE 1
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
2944-1
Furnish and install strain for
concrete retaining wall;
complete as specified
Square
Feet 2,550.00 2,550.00 $3.30
$0.00 $0.00
$0.00
($26,537.87)
$0.00
NET DECREASE TO CONTRACT: ($26,537.87)
SECTION 2: ALTERNATE 1 (ITEM 2944-1) SUBTOTAL:
NET DECREASE:
NET DECREASE TO SECTION 2:
NET DECREASE TO SECTION I:
Page 5 of 5
Docusign Envelope ID: 74916E77-1F85-4ABB-AACB-9EE52E2B307F