HomeMy WebLinkAbout23-02 CO #1 (FINAL)_8-20-24TO: CARL BOWERS & SONS CONST CHANGE ORDER #1 ( FINAL)
N1844 MALONEY ROAD
KAUKAUNA, WI 54130
Your present contract with the City of Oshkosh, Contract No. 23-02, awarded February 28, 2023, is hereby amended
and changed as follows:
NET DECREASE TO SECTION I: ($67,311.79)
NET INCREASE TO ADDITIONAL WORK:$41,850.00
NET DECREASE TO CONTRACT ($25,461.79)
SECTION I TOTALS
BID TOTAL $4,036,254.95 $4,036,254.95
CO #1 ($25,461.79)($25,461.79)
CONTRACT TOTAL $4,010,793.16 $4,010,793.16
CITY OF OSHKOSH
BY:
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Approved as to form:
City Attorney
DATE: AUGUST 20, 2024
______________________________
Comptroller
______________________________
Contractor
______________________________
Approved and accepted:
______________________________
City Manager
City Clerk
______________________________
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
23-02
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
1011
Clearing; complete as
specified
Inch
Diameter 390.00 390.00 $38.00
1021
Grubbing; complete as
specified
Inch
Diameter 390.00 442.00 52.00 $20.00 $1,040.00
1050
Mobilization; complete as
specified
Lump
Sum 1.00 1.00 $140,000.00
1100
Removing pavement;
complete as specified
Square
Yards 1,430.00 1,552.70 122.70 $5.00 $613.50
1110
Removing curb and gutter;
complete as specified
Linear
Feet 4,700.00 4,608.20 -91.80 $3.00 ($275.40)
1120
Removing concrete and
asphalt sidewalk and
driveway; complete as
specified
Square
Feet 34,300.00 33,150.96 -1,149.04 $0.60 ($689.42)
1200
Unclassified excavation;
complete as specified
Cubic
Yards 4,400.00 4,328.80 -71.20 $16.00 ($1,139.20)
1220
Excavation special (paving);
complete as specified Tons 650.00 0.00 -650.00 $0.01 ($6.50)
1301
7" concrete pavment; with 5"
CABC and grading;
complete as specified
Square
Yards 7,300.00 7,118.10 -181.90 $46.60 ($8,476.54)
1303
7" concrete pavement HES;
with 5" CABC and grading;
complete as specified
Square
Yards 1,160.00 1,239.30 79.30 $50.60 $4,012.58
1309
7" concrete pavement HES
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
as specified
Square
Yards 470.00 459.80 -10.20 $99.50 ($1,014.90)
1313
8" concrete pavement HES;
with 6" CABC and grading;
complete as specified
Square
Yards 350.00 243.80 -106.20 $78.50 ($8,336.70)
1315
8" concrete pavement
doweled; HES; with 6" CABC
and grading; complete as
specified
Square
Yards 95.00 292.80 197.80 $82.50 $16,318.50
1319
8" concrete pavement HES
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
as specified
Square
Yards 295.00 279.00 -16.00 $130.30 ($2,084.80)
1334
Concrete pavement gaps;
complete as specified Each 3.00 3.00 $1,000.00
Page 2 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
1335
Concrete pavement
approach salb; HES
complete as specified
Square
Yards 110.00 80.90 -29.10 $230.00 ($6,693.00)
1340
Crushed aggregate base
course; complete as
specified Tons 1,290.00 0.00 -1,290.00 $15.00 ($19,350.00)
1350
Pavement ties; complete as
specified Each 130.00 114.00 -16.00 $8.00 ($128.00)
1352
Drilled dowel bars; 1";
complete as specified Each 63.00 44.00 -19.00 $13.00 ($247.00)
1354
Drilled dowel bars; 1 1/4";
complete as specified Each 82.00 60.00 -22.00 $17.00 ($374.00)
1360
Adjust manholes and inlets;
complete as specified Each 93.00 97.00 4.00 $375.00 $1,500.00
1370
Turf restoration; complete as
specified
Square
Yards 4,300.00 4,581.07 281.07 $9.00 $2,529.63
1372
Restore gravel driveway/
apron; complete as specified
Square
Yards 230.00 232.00 2.00 $20.00 $40.00
1380
Cold weather covering
(concrete pavement) - single
visquine; complete as
specified
Square
Yards 1,430.00 0.00 -1,430.00 $0.01 ($14.30)
1390
Up-charge for late season
cold weather concrete
pavement; complete as
specified
Cubic
Yards 280.00 0.00 -280.00 $0.01 ($2.80)
1410
12" radius curb with 6"
CABC and grading;
complete as specified
Linear
Feet 800.00 820.40 20.40 $15.00 $306.00
1440
30" curb and gutter; 7": with
5" CABC and grading;
complete as specified
Linear
Feet 300.00 287.60 -12.40 $48.00 ($595.20)
1460
Sidewalk curb; complete as
specified
Linear
Feet 320.00 334.78 14.78 $45.00 $665.10
1500
4" concrete sidewalk with 3"
CABC and grading;
complete as specified
Square
Feet 15,900.00 15,686.43 -213.57 $6.80 ($1,452.27)
1510
6" concrete sidewalk/
driveway/ramp with 3" CABC
and grading; complete as
specified
Square
Feet 15,500.00 14,496.98 -1,003.02 $7.80 ($7,823.55)
1514
6" concrete sidewalk/
driveway/ramp (HES) with 3"
CABC and grading;
complete as specified
Square
Feet 480.00 1,351.40 871.40 $8.15 $7,101.91
1520
8" concrete sidewalk
/driveway/ramp with 3"
CABC and grading;
complete as specified
Square
Feet 730.00 204.40 -525.60 $8.45 ($4,441.32)
Page 3 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
1524
8" concrete sidewalk/
driveway/ramp (HES) with 3"
CABC and grading;
complete as specified
Square
Feet 350.00 797.40 447.40 $9.15 $4,093.71
1530
6" concrete step; complete
as specified
Square
Feet 510.00 441.20 -68.80 $70.00 ($4,816.00)
1540
Curb ramp detectable
warning field (natural/
non-painted); complete as
specified
Square
Feet 480.00 470.10 -9.90 $32.00 ($316.80)
1550
No. 4 reinforcing rods -
deformed; epoxy-coated;
complete as specified
Linear
Feet 4,320.00 3,840.00 -480.00 $2.00 ($960.00)
1560
Drilled No. 4 sidewalk tie
bars - deformed; epoxy-
coated; complete as
specified Each 290.00 124.00 -166.00 $7.00 ($1,162.00)
1580
Cold weather covering
(sidewalk) - single visquine;
complete as specified
Square
Feet 5,100.00 1,184.30 -3,915.70 $0.01 ($39.16)
1582
Cold weather covering
(sidewalk) - double visquine;
complete as specified
Square
Feet 1,800.00 0.00 -1,800.00 $0.01 ($18.00)
1584
Cold weather covering
(sidewalk) - double visquine
with 6" hay; complete as
specified
Square
Feet 1,800.00 0.00 -1,800.00 $0.01 ($18.00)
1590
Up-charge for late cold
weather concrete sidewalk;
complete as specified
Cubic
Yards 95.00 18.80 -76.20 $0.01 ($0.76)
1600
Furnish and install tree;
complete as specified Each 19.00 8.00 -11.00 $550.00 ($6,050.00)
1650
Locate existing property
monuments; complete as
specified Each 18.00 23.00 5.00 $150.00 $750.00
1652
Replace existing property
monuments; complete as
specified Each 18.00 23.00 5.00 $50.00 $250.00
1700
Sawing existing pavement;
complete as specified
Linear
Feet 1,230.00 1,296.40 66.40 $2.00 $132.80
1710
Sawing concrete pavement
full depth; complete as
specified
Linear
Feet 460.00 554.10 94.10 $3.00 $282.30
1900
Tack coat; complete as
specified Gallons 45.00 0.00 -45.00 $8.00 ($360.00)
1906
4" asphaltic pavement LT
with 10" CABC and grading;
complete as specified
Square
Yards 50.00 109.20 59.20 $60.00 $3,552.00
1911
4" asphaltic transition LT
with 10" CABC and grading
complete as specified
Square
Yards 580.00 824.00 244.00 $56.00 $13,664.00
Page 4 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
1916
4" asphaltic surface LT with
6" CABC and grading;
complete as specified
Square
Yards 115.00 126.70 11.70 $54.00 $631.80
1917
2" asphaltic surface LT with
6" CABC and grading;
complete as specified
Square
Yards 100.00 15.50 -84.50 $54.00 ($4,563.00)
1918
Asphaltic cold weather
paving; complete as
specified
Square
Yards 125.00 0.00 -125.00 $0.01 ($1.25)
2002
Furnish and install 10" storm
sewer; complete as specified
Linear
Feet 32.00 90.00 58.00 $83.00 $4,814.00
2003
Furnish and install 12" storm
sewer; complete as specified
Linear
Feet 659.40 631.00 -28.40 $75.00 ($2,130.00)
2006
Furnish and install 15" storm
sewer; complete as specified
Linear
Feet 307.90 299.50 -8.40 $80.00 ($672.00)
2009
Furnish and install 18" storm
sewer; complete as specified
Linear
Feet 289.20 278.00 -11.20 $85.00 ($952.00)
2015
Furnish and install 24" storm
sewer; complete as specified
Linear
Feet 158.00 151.00 -7.00 $110.00 ($770.00)
2018
Furnish and install 27" storm
sewer; complete as specified
Linear
Feet 140.00 97.00 -43.00 $113.00 ($4,859.00)
2024
Furnish and install 36" storm
sewer; complete as specified
Linear
Feet 178.90 162.00 -16.90 $162.00 ($2,737.80)
2027
Furnish and install 42" storm
sewer; complete as specified
Linear
Feet 197.60 180.00 -17.60 $185.00 ($3,256.00)
2030
Furnish and install 48" storm
sewer; complete as specified
Linear
Feet 926.90 881.00 -45.90 $240.00 ($11,016.00)
2049
Furnish and install 24" x 38"
HERCP Class III storm
sewer; complete as specified
Linear
Feet 331.40 308.00 -23.40 $170.00 ($3,978.00)
2200
Furnish and install standard
sanitary sewer manhole (2'
diameter); complete as
specified
Vertical
Feet 3.29 3.43 0.14 $600.00 $84.00
2201
Furnish and install standard
storm sewer manhole (4'
diameter); complete as
specified
Vertical
Feet 53.95 53.96 0.01 $500.00 $5.00
2202
Furnish and install standard
storm sewer manhole (5'
diameter); complete as
specified
Vertical
Feet 1.00 0.00 -1.00 $850.00 ($850.00)
Page 5 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
2203
Furnish and install standard
storm sewer manhole (6'
diameter); complete as
specified
Vertical
Feet 32.76 33.16 0.40 $1,100.00 $440.00
2204
Furnish and install standard
storm sewer manhole (7'
diameter); complete as
specified
Vertical
Feet 28.76 29.23 0.47 $1,350.00 $634.50
2205
Furnish and install standard
storm sewer manhole (8'
diameter); complete as
specified
Vertical
Feet 7.56 6.70 -0.86 $1,700.00 ($1,462.00)
2213
Furnish and install standard
storm sewer inlet manhole
(4' diameter); complete as
spcified
Vertical
Feet 19.43 16.97 -2.46 $600.00 ($1,476.00)
2237
Furnish and install Type 3
inlet (with 18" sump);
complete as specified Each 41.00 40.00 -1.00 $2,700.00 ($2,700.00)
2400
Furnish and install 6" storm
sewer lateral; complete as
specified
Linear
Feet 1,258.00 1,218.10 -39.90 $64.00 ($2,553.60)
2402
Furnish and install 8" storm
sewer lateral; complete as
specified
Linear
Feet 74.00 131.00 57.00 $72.00 $4,104.00
2404
Furnish and install storm
sewer marker balls;
complete as specified Each 86.00 85.00 -1.00 $30.00 ($30.00)
2406
Furnish and install storm
sewer clay dams; complete
as specified Each 43.00 42.00 -1.00 $100.00 ($100.00)
2408
Furnish and install storm
sewer lateral inlet; complete
as specified Each 42.00 40.00 -2.00 $900.00 ($1,800.00)
2414
Storm lateral inlet
adjustments; complete as
specified Each 9.00 0.00 -9.00 $150.00 ($1,350.00)
2508
Furnish; install; maintain;
and remove Type D modified
inlet protection; complete as
specified Each 67.00 67.00 $100.00
2510
Sediment removal - Type D
modified inlet protection;
complete as specified Each 4.00 0.00 -4.00 $10.00 ($40.00)
2516
Furnish; install; maintain;
and remove stone bag;
complete as specified Each 130.00 0.00 -130.00 $10.00 ($1,300.00)
2750
Rock excavation; complete
as specified
Cubic
Yards 10.00 0.00 -10.00 $0.01 ($0.10)
2800
Abandon 8" - 12" storm
sewer; complete as specified
Linear
Feet 169.00 170.00 1.00 $15.00 $15.00
Page 6 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
2802
Abandon 15" and larger
storm sewer; complete as
specified
Linear
Feet 10.00 0.00 -10.00 $20.00 ($200.00)
2804
Remove 30" and smaller
storm sewer; complete as
specified
Linear
Feet 786.50 860.00 73.50 $25.00 $1,837.50
2810
Abandon storm sewer
manholes and inlets;
complete as specified Each 1.00 0.00 -1.00 $400.00 ($400.00)
2812
Remove storm sewer
manholes and inlets;
complete as specified Each 22.00 22.00 $500.00
2850
Connect to existing storm
sewer main; complete as
specified Each 12.00 12.00 $800.00
2852
Connect to existing storm
sewer lateral; complete as
specified Each 4.00 2.00 -2.00 $200.00 ($400.00)
2856
Connect to existing storm
sewer manhole; complete as
specified Each 3.00 4.00 1.00 $500.00 $500.00
2914
Storm sewer utility line
opening (ULO); complete as
specified Each 3.00 1.00 -2.00 $600.00 ($1,200.00)
2950
Excavation special (storm);
complete as specified Tons 25.00 0.00 -25.00 $15.00 ($375.00)
3000
Furnish and install 8"
sanitary sewer (relay);
complete as specified
Linear
Feet 1,675.00 1,664.00 -11.00 $170.00 ($1,870.00)
3002
Furnish and install 10"
sanitary sewer (relay);
complete as specified
Linear
Feet 570.00 589.00 19.00 $240.00 $4,560.00
3004
Furnish and install 12"
sanitary sewer (relay);
complete as specified
Linear
Feet 30.00 24.00 -6.00 $260.00 ($1,560.00)
3012
Furnish and install 24"
sanitary sewer (relay);
complete as specified
Linear
Feet 20.00 9.50 -10.50 $300.00 ($3,150.00)
3060
Furnish and install 8"
sanitary sewer drop;
complete as specified
Vertical
Feet 30.50 30.12 -0.38 $500.00 ($190.00)
3062
Furnish and install 10"
sanitary sewer drop;
complete as specified
Vertical
Feet 6.00 5.21 -0.79 $550.00 ($434.50)
3100
Furnish and install standard
sanitary sewer manhole (4'
diameter); complete as
specified
Vertical
Feet 195.00 193.94 -1.06 $450.00 ($477.00)
3114
Furnish and install external
sanitary sewer manhole
chimney seal; complete as
specified Each 15.00 18.00 3.00 $450.00 $1,350.00
Page 7 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
3116
Furnish and install external
sanitary sewer manhole
chimney seal extension;
complete as specified Each 2.00 0.00 -2.00 $425.00 ($850.00)
3136
Rebuild sanitary sewer
manhole (4' diameter);
complete as specified
Vertical
Feet 9.00 8.33 -0.67 $500.00 ($335.00)
3160
Pour and reshape manhole
bench; complete as
specified Each 1.00 1.00 $1,000.00
3210
Furnish and install 8" x 6"
sanitary sewer factory wyes
or tees; complete as
specified Each 36.00 35.00 -1.00 $300.00 ($300.00)
3212
Furnish and install 10" x 6"
sanitary sewer factory wyes
or tees; complete as
specified Each 8.00 9.00 1.00 $350.00 $350.00
3214
Furnish and install 12" x 6"
sanitary sewer factory wyes
or tees; complete as
specified Each 1.00 1.00 $500.00
3222
Furnish and install 6"
sanitary sewer "Insert-A-
Tee" or "Kor-N-Tee";
complete as specified Each 3.00 3.00 $1,200.00
3232
Furnish and install 6"
sanitary sewer laterals
(new); complete as specified
Linear
Feet 35.00 34.50 -0.50 $104.00 ($52.00)
3233
Furnish and install 6"
sanitary sewer riser (new);
complete as specified
Linear
Feet 9.00 6.50 -2.50 $110.00 ($275.00)
3234
Furnish and install 4"/6"
sanitary sewer lateral (relay);
complete as specified
Linear
Feet 1,529.00 1,525.00 -4.00 $100.00 ($400.00)
3235
Furnish and install 4"/6"
sanitary sewer riser (relay);
complete as specified
Linear
Feet 201.00 137.40 -63.60 $106.00 ($6,741.60)
3236
Furnish and install sanitary
sewer lateral marker balls;
complete as specified Each 98.00 95.00 -3.00 $30.00 ($90.00)
3238
Furnish and install clay
dams; complete as specified Each 49.00 46.00 -3.00 $100.00 ($300.00)
3302
Furnish and install
connection to existing 10"
sanitary sewer mains;
complete as specified Each 1.00 2.00 1.00 $1,600.00 $1,600.00
3304
Furnish and install
connection to existing 12"
sanitary sewer mains;
complete as specified Each 3.00 2.00 -1.00 $1,800.00 ($1,800.00)
Page 8 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
3312
Furnish and install
connection to existing 24"
sanitary sewer mains;
complete as specified Each 2.00 2.00 $2,500.00
3330
Furnish and install sanitary
sewer concrete collars;
complete as specified Each 1.00 0.00 -1.00 $500.00 ($500.00)
3402
Furnish and install 8"
sanitary sewer open cut
casing pipes; complete as
specified
Linear
Feet 110.00 100.00 -10.00 $150.00 ($1,500.00)
3600
Rock excavation; complete
as specified
Cubic
Yards 25.00 0.00 -25.00 $150.00 ($3,750.00)
3700
Closed circuit televising;
complete as specified
Linear
Feet 2,275.00 2,275.00 $2.00
3710
Closed circuit televising -
using push camera;
complete as specified Each 4.00 1.00 -3.00 $250.00 ($750.00)
3800
Abandon sanitary sewer
manholes; complete as
specified Each 2.00 0.00 -2.00 $400.00 ($800.00)
3806
Abandon 12" sanitary sewer;
complete as specified
Linear
Feet 1,008.00 730.00 -278.00 $30.00 ($8,340.00)
3852
Remove sanitary sewer
manholes; complete as
specified Each 7.00 7.00 $800.00
3854
Remove sanitary sewer;
complete as specified
Linear
Feet 380.00 380.00 $30.00
3890
Sanitary sewer utility line
opening (ULO); complete as
specified Each 2.00 0.00 -2.00 $600.00 ($1,200.00)
4000
Furnish and install 4" ductile
iron water main (relay) with
polywrap; complete as
specified
Linear
Feet 30.00 29.50 -0.50 $126.00 ($63.00)
4002
Furnish and install 6" ductile
iron water main (relay) with
polywrap; complete as
specified
Linear
Feet 215.00 511.00 296.00 $155.00 $45,880.00
4004
Furnish and install 8" ductile
iron water main (relay) with
polywrap; complete as
specified
Linear
Feet 2,570.00 2,525.00 -45.00 $125.00 ($5,625.00)
4008
Furnish and install 12"
ductile iron wtaer main
(relay) with polywrap;
complete as specified
Linear
Feet 12.00 8.00 -4.00 $200.00 ($800.00)
4036
Furnish and install 1" water
service (relay); complete as
specified
Linear
Feet 1,227.00 1,223.00 -4.00 $80.00 ($320.00)
4037
Furnish and install 1 1/4"
water service (relay);
complete as specified
Linear
Feet 70.00 63.00 -7.00 $86.00 ($602.00)
Page 9 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
4040
Furnish and install 2" water
service (relay); complete as
specified
Linear
Feet 28.00 15.00 -13.00 $100.00 ($1,300.00)
4048
Furnish and install 1"
corporation and stop box;
complete as specified Each 40.00 32.00 -8.00 $600.00 ($4,800.00)
4050
Furnish and install 1 1/4"
corporation and stop box;
complete as specified Each 2.00 2.00 $1,200.00
4053
Furnish and install 2"
corporation and stop box;
complete as specified Each 1.00 1.00 $1,800.00
4055
Furnish and install water
service clay dams; complete
as specified Each 43.00 35.00 -8.00 $100.00 ($800.00)
4056
Furnish and install
connections to existing 4"
water main; complete as
specified Each 1.00 1.00 $1,800.00
4058
Furnish and install
connections to existing 6"
water main; complete as
specified Each 6.00 6.00 $1,800.00
4060
Furnish and install
connections to existing 8"
water main; complete as
specified Each 2.00 2.00 $2,000.00
4064
Furnish and install
connections to existing 12"
water main; complete as
specified Each 2.00 1.00 -1.00 $2,800.00 ($2,800.00)
4101
Furnish and install 6" x 6"
water main tee; complete as
specified Each 1.00 1.00 $530.00
4110
Furnish and install 8" x 6"
water main tee; complete as
specified Each 4.00 5.00 1.00 $720.00 $720.00
4111
Furnish and install 8" x 8"
water main tee; complete as
specified Each 2.00 2.00 $735.00
4129
Furnish and install 12" x 8"
water main tee; complete as
specified Each 1.00 1.00 $1,150.00
4189
Furnish and install 8" x 8"
water main cross; complete
as specified Each 3.00 3.00 $1,000.00
4219
Furnish and install 8" 11 1/4
degree water main bend;
complete as specified Each 1.00 1.00 $450.00
4228
Furnish and install 8" 22 1/2
degree water main bend;
complete as specified Each 2.00 0.00 -2.00 $470.00 ($940.00)
Page 10 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
4235
Furnish and install 4" 45
degree water main bend;
complete as specified Each 5.00 4.00 -1.00 $250.00 ($250.00)
4236
Furnish and install 6" 45
degree water main bend;
complete as specified Each 28.00 22.00 -6.00 $330.00 ($1,980.00)
4237
Furnish and install 8" 45
degree water main bend;
complete as specified Each 10.00 8.00 -2.00 $420.00 ($840.00)
4255
Furnish and install 8" water
main cap; complete as
specified Each 1.00 1.00 $275.00
4263
Furnish and install 8" x 4"
water main reducer;
complete as specified Each 1.00 1.00 $400.00
4264
Furnish and install 8" x 6"
water main reducer;
complete as specified Each 6.00 6.00 $420.00
4350
Cut and cap existing 4"
water main; complete as
specified Each 2.00 2.00 $800.00
4352
Cut and cap existing 6"
water main; complete as
specified Each 2.00 8.00 6.00 $800.00 $4,800.00
4354
Cut and cap existing 8"
water main; complete as
specified Each 2.00 0.00 -2.00 $900.00 ($1,800.00)
4401
Furnish and install 6" water
main gate valve; complete
as specified Each 5.00 7.00 2.00 $2,050.00 $4,100.00
4402
Furnish and install 8" water
main gate valve; complete
as specified Each 20.00 22.00 2.00 $2,900.00 $5,800.00
4404
Furnish and install 12" water
main gate valve; complete
as specified Each 2.00 1.00 -1.00 $5,000.00 ($5,000.00)
4500
Furnish and install hydrant;
complete as specified Each 4.00 5.00 1.00 $5,800.00 $5,800.00
4712
Furnish and install 2" water
main casing pipe; complete
as specified
Linear
Feet 110.00 110.00 $125.00
4800
Rock excavation; complete
as specified
Cubic
Yards 25.00 0.00 -25.00 $0.10 ($2.50)
4920
Remove water main;
complete as specified
Linear
Feet 602.00 602.00 $25.00
5013
Furnish and install pull box
(non-conductive); 18" x 36";
complete as specified Each 23.00 21.00 -2.00 $1,750.00 ($3,500.00)
5019
Furnish and install pull box
non-conductive; 24" x 42";
complete as specified Each 12.00 7.00 -5.00 $1,850.00 ($9,250.00)
Page 11 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
5025
Adjust pull box; complete as
specified Each 33.00 28.00 -5.00 $5.00 ($25.00)
5051
Install CITY-supplied lighting
control cabinet; complete as
specified Each 1.00 1.00 $2,000.00
5053
Install CITY-supplied fully-
actuated 8-phase traffic
signal control cabinet;
complete as specified Each 1.00 1.00 $2,000.00
5054
Install electrical service;
complete as specified Each 2.00 2.00 $2,250.00
5056
Remove and preserve light
poles; bases; and lighting
fixtures; complete as
specified
Lump
Sum 1.00 1.00 $7,500.00
5120
Furnish and install 2"
Schedule 40 PVC; complete
as specified
Linear
Feet 65.00 11.00 -54.00 $10.00 ($540.00)
5130
Furnish and install 3"
Schedule 40 PVC; complete
as specified
Linear
Feet 3,285.00 3,259.00 -26.00 $14.00 ($364.00)
5170
3" Schedule 40 PVC bore;
including bore pits and utility
line openings; complete as
specified
Linear
Feet 640.00 596.00 -44.00 $35.00 ($1,540.00)
5240
Furnish and install 6' gauge
red-coated wire; complete a
specified
Linear
Feet 3,800.00 3,669.00 -131.00 $1.40 ($183.40)
5241
Furnish and install 6 gauge
black-coated wire; complete
as specified
Linear
Feet 3,800.00 3,669.00 -131.00 $1.40 ($183.40)
5252
Furnish and install 8 gauge
green-coated wire; complete
as specified
Linear
Feet 3,200.00 3,148.00 -52.00 $1.50 ($78.00)
5260
Furnish and install 10 gauge
red-coated wire; complete as
specified
Linear
Feet 250.00 212.00 -38.00 $0.90 ($34.20)
5261
Furnish and install 10 gauge
black-coated wire; complete
as specified
Linear
Feet 250.00 212.00 -38.00 $0.90 ($34.20)
5262
Furnish and install 10 gauge
green-coated wire; complete
as specified
Linear
Feet 800.00 732.00 -68.00 $0.90 ($61.20)
5270
Furnish and install 12 gauge
red-coated wire; complete as
specified
Linear
Feet 860.00 780.00 -80.00 $0.80 ($64.00)
5271
Furnish and install 12 gauge
black-coated wire; complete
as specified
Linear
Feet 860.00 780.00 -80.00 $0.80 ($64.00)
5272
Furnish and install 12 gauge
green-coated wire; complete
as specified
Linear
Feet 860.00 780.00 -80.00 $0.80 ($64.00)
Page 12 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
5282
Furnish and install 14 gauge
green-coated wire; complete
as specified
Linear
Feet 150.00 130.00 -20.00 $1.00 ($20.00)
5300
Furnish and install 4 pair
shielded CAT5; complete as
specified
Linear
Feet 350.00 257.00 -93.00 $2.00 ($186.00)
5356
Furnish and install 14 gauge
stranded single pair twisted
with shield; complete as
specified
Linear
Feet 875.00 889.00 14.00 $1.75 $24.50
5360
Furnish and install 14 AWG
solid 3 conductor; complete
as specified
Linear
Feet 150.00 120.00 -30.00 $2.00 ($60.00)
5362
Furnish and install 14 AWG
solid 5 conductor; complete
as specified
Linear
Feet 420.00 370.00 -50.00 $2.50 ($125.00)
5372
Furnish and install 14 AWG
solid 21 conductor; complete
as specified
Linear
Feet 1,600.00 1,471.00 -129.00 $4.75 ($612.75)
5380
Furnish and install fuse
holder; complete as
specified Each 42.00 34.00 -8.00 $55.00 ($440.00)
5386
Furnish and install 2A fuse;
complete as specified Each 42.00 34.00 -8.00 $5.00 ($40.00)
5420
Install CITY-supplied 10'
traffic signal pole with a
pedestal base; complete as
specified Each 8.00 6.00 -2.00 $250.00 ($500.00)
5421
Install CITY-supplied 13'
traffic signal pole with a
decorative base; complete
as specified Each 4.00 5.00 1.00 $250.00 $250.00
5424
Install CITY-supplied 20'
traffic signal pole with a
pedestal base; complete as
specified Each 1.00 2.00 1.00 $550.00 $550.00
5426
Install CITY-supplied 30'
traffic signal pole with a
transformer base; complete
as specified Each 3.00 3.00 $750.00
5431
Install CITY-supplied 25'
trombone arm; complete as
specified Each 3.00 4.00 1.00 $750.00 $750.00
5434
Install CITY-supplied three-
section traffic signal head;
back plate; and LED
modules; complete as
specified Each 12.00 13.00 1.00 $550.00 $550.00
5438
Install CITY-supplied
pedestrian signal head with
countdown timer; complete
as specified Each 8.00 8.00 $350.00
Page 13 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02
CONTRACT 23-02 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
5440
Install CITY-supplied
pedestrian push button;
complete as specified Each 8.00 11.00 3.00 $200.00 $600.00
5452
Install CITY-supplied 20'
tapered pole with
transformer base; complete
as specified Each 19.00 17.00 -2.00 $550.00 ($1,100.00)
5458
Install CITY-supplied 10'
truss-type luminaire arm;
complete as specified Each 22.00 20.00 -2.00 $350.00 ($700.00)
5470
Install CITY-supplied cobra
head luminaire; complete as
specified Each 21.00 19.00 -2.00 $200.00 ($400.00)
5502
Furnish and install TYPE 2
base; complete as specified Each 16.00 15.00 -1.00 $1,150.00 ($1,150.00)
5504
Furnish and install TYPE 5
base; complete as specified Each 20.00 18.00 -2.00 $975.00 ($1,950.00)
5506
Furnish and install TYPE 9
base; complete as specified Each 2.00 2.00 $2,000.00
SECTION I (BID ITEMS 1011 - 5506) - SUBTOTAL: $147,602.33 ($214,914.12)
NET DECREASE TO SECTION I: ($67,311.79)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT PRICE
DECREASE IN
CONTRACT PRICE
1-20000
Downtime to dig around
UWO geothermal lines that
were not located properly;
complete as specified Each 0.00 4.50 4.50 $1,740.00 $7,830.00
1-30000
Stone & dumping 4' x 10' x
311'; complete as specified
Lump
Sum 0.00 1.00 1.00 $19,020.00 $19,020.00
1-40000
McKinley Street temporary
water set up and installation;
ten (10) laterals; complete
as specified
Lump
Sum 0.00 1.00 1.00 $15,000.00 $15,000.00
$41,850.00 $0.00
$41,850.00
NET DECREASE TO SECTION I: ($67,311.79)
$41,850.00
NET DECREASE TO CONTRACT: ($25,461.79)
ADDITIONAL WORK REQUIRED: CO #1
NET INCREASE TO ADDITIONAL WORK:
NET INCREASE:
ADDITIONAL WORK REQUIRED: CO #1 (ITEMS 1-20000 - 1-40000) SUBTOTAL:
Page 14 of 14
Docusign Envelope ID: 180EDADD-58C3-4A36-8B5D-63FCFB382B02