HomeMy WebLinkAbout04-365
SEPTEMBER 28, 2004
04-365
RESOLUTION
(CARRIED 7 -0
LOST
LAID OVER
WITHDRAWN
PURPOSE:
CHANGE ORDER NO.1, PUBLIC WORKS CONTRACT 03-16
INITIATED BY:
DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
FLUOR BROTHERS CONSTRUCTION CO.
203 Otter Ave.
PO Box 2326
Oshkosh, WI 54903-2326
Net decrease to contract:
($1,891.62)
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Accl. No.
561-2010-1799-00000, storm water utility-construction in progress
TO: Fluor Brothers Construction Co.
203 Otter Avenue
P. O. Box 2326 .
Oshkosh, WI 54903-2326
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
NET DECREASE TO SECTION 1- ASPHALT PAVING:
NET INCREASE TO SECTION III - STORM SEWER:
NET DECREASE TO CONTRACT:
Recommended:
Í') 'J ~,
_L c~," c., 1.'- ~/¿
Director of Public W rks
CHANGE ORDER # 1
DATED: September 7,2004
03-16
, is hereby amended
($2,342.49)
$450.87
($1,891.62)
CITY OF OSHKOSH
BY:
City Manager
City Clerk
Approved and accepted:
t- ¡L ¡J~- ß¿tðit 25Ar<.
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Approved as to form:
City Attorney
Comptroller
CONTRACT: 03-16 ASPHALT PARKING LOT - CHANGE ORDER # 1
SECTION I . ASPHALT PAVING
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
1: Approx. 45.55 square
yards of pavement
removal, complete as
specified, per square vard 45.55 64.00 18.45 $20.52 $378.59
2. Approx. 1 ,545 square feet
of sidewalk and driveway
removal, complete as
specified, per square foot 1,545.00 1,636.00 91.00 $1.89 $171.99
3. Abandon three (3) existing
Window Wells, complete'
as specified, lump sum 1.00 2.00 1.00 $684.00 $684.00
4. Remove approx. 45 linear
feet of Foundation Wall,
complete as specified, per
linear foot 45.00 7.00 -38.00 $13.68 ($519.84)
5. Approx. 1,070 cubic yards
of excavation, complete as
specified, per cubic yard
1,070.00 1,052.00 -18.00 $7.98 ($143.64)
6. Approx. 35 linear feet of
12" wide radius curb head,
complete as specified, per
linear foot 35.00 15.00 -20.00 $15.96 ($319.20)
7. Approx. 325 linear feet of
standard 18" curb & gutter,
complete as specified, per
linear foot 325.00 322.00 -3.00 $20.52 ($61.56)
8. Approx. 50 linear feet of
standard 30" curb & gutter,
complete as specified, per
linear foot 50.00 30.00 -20.00 $25.08 ($501.60)
9. Approx. 70 linear feet of 6"
x 12" curb, complete as
specified, per linear foot
70.00 66.00 -4.00 $13.68 ($54.72
10. Approx. 325 tons of
asphaltic concrete binder
material, complete as
specified, per ton 325.00 332.00 7.00 $48.68 $340.76
11. Approx. 260 tons of
asphaltic concrete surface
material, complete as
specified, per ton 260.00 262.00 2.00 $46.63 $93.26
12. Approx. 3,075 square feet
of 4" concrete sidewalk,
complete as specified, per
square foot 3,075.00 2,846.00 -229.00 $3.99 ($913.71)
Page 1
CONTRACT: 03-16 ASPHALT PARKING LOT - CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
13. Approx. 540 square feet of
6" concrete sidewalk &
driveway, complete as
specified, per square foot 540.00 573.00 33.00 $4.56 $150.48
14. Approx. 16 square yards of
7" non-reinforced concrete
pavement, including
integral curb and grading
and base, complete as
specified, per square yard 16.00 42.00 26.00 $35.91 $933.66
15. Furnish and install approx.
1,050 tons of crushed
stone base course,
complete as specified, per ($1,342.92\
ton 1,050.00 926.00 -124.00 $10.83
16. Approx. 290 linear feet of
sawing, complete as ($1,039.68)
specified, per linear foot 290.00 138.00 -152.00 $6.84
17. Furnish and install approx.
72 pavement ties,
complete as specified, ($198.36)
each 72.00 43.00 -29.00 $6.84
18. Construct approx. 84
square feet of concrete
Type "A" false curb Metal
Fencing, complete as
specified, lump sum 1.00 1.00 $3,183.04
19. Landscape work on Church
Avenue, complete as
specified, lump sum 1.00 1.00 $912.00
20. Provide $375.00 to the City
of Oshkosh for project
management
communications, complete
as specified, lump sum
1.00 1.00 $375.00
SECTION I- (BID ITEMS 1 - 20) - SUB-TOTALS
$2,752.74 ($5,095.23)
($2,342.49)
NET DECREASE TO SECTION I -
SECTION III - STORM SEWER
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
24. Furnish and install approx.
104 linear feet of 6" Storm
Sewer, complete as
specified, per linear foot
104.00 109.00 5.00 $47.31 $236.55
Page 2
CONTRACT: 03-16 ASPHALT PARKING LOT - CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
25. Furnish and install approx.
204 linear feet of 12" Storm
Sewer, complete as
specified, per linear foot
204.00 208.00 4.00 $53.58 $214.32
26. Furnish and install approx.
three (3) std. Inlets (Type
1, 30" Inside Diameter),
with castings, complete as
specified, each
3.00 3.00 $1,254.00
27. Abandon one (1) Inlet as
specified, each 1.00 1.00 $228.00
28. Provide $375.00 to the City
of Oshkosh for project
management
communications, complete
as specified, lump sum
1.00 1.00 $375.00
SECTION 111- (BID ITEMS 24 - 28) - SUB-TOTALS
$450.87
$0.00
$450.87
NET INCREASE TO SECTION III .
NET DECREASE TO SECTION I
NET INCREASE TO SECTION III
($2,342.49)
$450.87
($1,891.62)
NET DECREASE TO CONTRACT:
Page 3