Loading...
HomeMy WebLinkAbout04-365 SEPTEMBER 28, 2004 04-365 RESOLUTION (CARRIED 7 -0 LOST LAID OVER WITHDRAWN PURPOSE: CHANGE ORDER NO.1, PUBLIC WORKS CONTRACT 03-16 INITIATED BY: DEPARTMENT OF PUBLIC WORKS BE IT RESOLVED by the Common Council of the City of Oshkosh that the following Change Order, a copy of which is attached, is hereby approved: FLUOR BROTHERS CONSTRUCTION CO. 203 Otter Ave. PO Box 2326 Oshkosh, WI 54903-2326 Net decrease to contract: ($1,891.62) PURPOSE: See attached Change Order. BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated from: Accl. No. 561-2010-1799-00000, storm water utility-construction in progress TO: Fluor Brothers Construction Co. 203 Otter Avenue P. O. Box 2326 . Oshkosh, WI 54903-2326 Your present contract with the City of Oshkosh, Contract No. and changed as follows: NET DECREASE TO SECTION 1- ASPHALT PAVING: NET INCREASE TO SECTION III - STORM SEWER: NET DECREASE TO CONTRACT: Recommended: Í') 'J ~, _L c~," c., 1.'- ~/¿ Director of Public W rks CHANGE ORDER # 1 DATED: September 7,2004 03-16 , is hereby amended ($2,342.49) $450.87 ($1,891.62) CITY OF OSHKOSH BY: City Manager City Clerk Approved and accepted: t- ¡L ¡J~- ß¿tðit 25Ar<. Contractor I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. Approved as to form: City Attorney Comptroller CONTRACT: 03-16 ASPHALT PARKING LOT - CHANGE ORDER # 1 SECTION I . ASPHALT PAVING ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 1: Approx. 45.55 square yards of pavement removal, complete as specified, per square vard 45.55 64.00 18.45 $20.52 $378.59 2. Approx. 1 ,545 square feet of sidewalk and driveway removal, complete as specified, per square foot 1,545.00 1,636.00 91.00 $1.89 $171.99 3. Abandon three (3) existing Window Wells, complete' as specified, lump sum 1.00 2.00 1.00 $684.00 $684.00 4. Remove approx. 45 linear feet of Foundation Wall, complete as specified, per linear foot 45.00 7.00 -38.00 $13.68 ($519.84) 5. Approx. 1,070 cubic yards of excavation, complete as specified, per cubic yard 1,070.00 1,052.00 -18.00 $7.98 ($143.64) 6. Approx. 35 linear feet of 12" wide radius curb head, complete as specified, per linear foot 35.00 15.00 -20.00 $15.96 ($319.20) 7. Approx. 325 linear feet of standard 18" curb & gutter, complete as specified, per linear foot 325.00 322.00 -3.00 $20.52 ($61.56) 8. Approx. 50 linear feet of standard 30" curb & gutter, complete as specified, per linear foot 50.00 30.00 -20.00 $25.08 ($501.60) 9. Approx. 70 linear feet of 6" x 12" curb, complete as specified, per linear foot 70.00 66.00 -4.00 $13.68 ($54.72 10. Approx. 325 tons of asphaltic concrete binder material, complete as specified, per ton 325.00 332.00 7.00 $48.68 $340.76 11. Approx. 260 tons of asphaltic concrete surface material, complete as specified, per ton 260.00 262.00 2.00 $46.63 $93.26 12. Approx. 3,075 square feet of 4" concrete sidewalk, complete as specified, per square foot 3,075.00 2,846.00 -229.00 $3.99 ($913.71) Page 1 CONTRACT: 03-16 ASPHALT PARKING LOT - CHANGE ORDER # 1 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 13. Approx. 540 square feet of 6" concrete sidewalk & driveway, complete as specified, per square foot 540.00 573.00 33.00 $4.56 $150.48 14. Approx. 16 square yards of 7" non-reinforced concrete pavement, including integral curb and grading and base, complete as specified, per square yard 16.00 42.00 26.00 $35.91 $933.66 15. Furnish and install approx. 1,050 tons of crushed stone base course, complete as specified, per ($1,342.92\ ton 1,050.00 926.00 -124.00 $10.83 16. Approx. 290 linear feet of sawing, complete as ($1,039.68) specified, per linear foot 290.00 138.00 -152.00 $6.84 17. Furnish and install approx. 72 pavement ties, complete as specified, ($198.36) each 72.00 43.00 -29.00 $6.84 18. Construct approx. 84 square feet of concrete Type "A" false curb Metal Fencing, complete as specified, lump sum 1.00 1.00 $3,183.04 19. Landscape work on Church Avenue, complete as specified, lump sum 1.00 1.00 $912.00 20. Provide $375.00 to the City of Oshkosh for project management communications, complete as specified, lump sum 1.00 1.00 $375.00 SECTION I- (BID ITEMS 1 - 20) - SUB-TOTALS $2,752.74 ($5,095.23) ($2,342.49) NET DECREASE TO SECTION I - SECTION III - STORM SEWER ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 24. Furnish and install approx. 104 linear feet of 6" Storm Sewer, complete as specified, per linear foot 104.00 109.00 5.00 $47.31 $236.55 Page 2 CONTRACT: 03-16 ASPHALT PARKING LOT - CHANGE ORDER # 1 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN DESCRIPTION CONTRACT CONTRACT NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 25. Furnish and install approx. 204 linear feet of 12" Storm Sewer, complete as specified, per linear foot 204.00 208.00 4.00 $53.58 $214.32 26. Furnish and install approx. three (3) std. Inlets (Type 1, 30" Inside Diameter), with castings, complete as specified, each 3.00 3.00 $1,254.00 27. Abandon one (1) Inlet as specified, each 1.00 1.00 $228.00 28. Provide $375.00 to the City of Oshkosh for project management communications, complete as specified, lump sum 1.00 1.00 $375.00 SECTION 111- (BID ITEMS 24 - 28) - SUB-TOTALS $450.87 $0.00 $450.87 NET INCREASE TO SECTION III . NET DECREASE TO SECTION I NET INCREASE TO SECTION III ($2,342.49) $450.87 ($1,891.62) NET DECREASE TO CONTRACT: Page 3