HomeMy WebLinkAboutItem II
PLAN COMMISSION STAFF REPORT AUGUST 6, 2024
ITEM II: SPECIFIC IMPLEMENTATION PLAN AMENDMENT FOR LOADING
DOCK ACCESS AT 3300 MEDALIST DRIVE
GENERAL INFORMATION
Applicant: Richard J Fisher
Property Owner: Gen2 Holdings LLC
Action(s) Requested:
The applicant requests approval of Specific Implementation Plan Amendment for loading dock
access.
Applicable Ordinance Provisions:
Planned Development standards are found in Section 30-387 of the Zoning Ordinance.
Property Location and Background Information:
The subject area involving this request consists of one developed industrial parcel totaling 17.05
acres. The property is located at the southeast corner of Medalist Drive and West 33rd Avenue.
Existing structures include an approximate 140,000 square foot manufacturing building, a
separate 19,500 square foot office building, three main off-street parking areas, and accessory
structures. Four personal storage facility buildings are also being constructed on the site, which
were included in a GDP/SIP approved by Common Council in 2023. The subject site as well as
the surrounding area are located in the Aviation Industrial Park and consist of industrial uses.
The 2040 Comprehensive Plan recommends industrial land use for the subject property as well
as the adjoining parcels.
Subject Site
Existing Land Use Zoning
Industrial HI-PD zone change
Adjacent Land Use and Zoning
Existing Uses Zoning
North Industrial Heavy Industrial (HI)
South Industrial Heavy Industrial (HI)
East Vacant Heavy Industrial (HI)
West Industrial Heavy Industrial (HI)
Recognized Neighborhood Organizations
N/A
Page 1
ITEM II - SIP Amendment – 3300 Medalist Dr.
Comprehensive Plan
Comprehensive Plan Land Use Recommendation Land Use
2040 Land Use Recommendation Industrial
ANALYSIS
Use
On June 13, 2023, Common Council approved a General Development Plan and Specific
Implementation Plan for construction of four personal storage buildings, in addition to the
existing buildings on-site. Lakeside Plastics has purchased a building on the site that was
formerly used as an office building occupied by Oshkosh Defense (401 West 33rd Avenue) and
intends to use it for a mix of office and manufacturing/warehousing. The proposed use of the
building is permitted in the HI district.
Site Design
The applicant plans to add a loading dock to the east side of the building along with additional
pavement for truck access to the loading dock. A cross-access agreement is required as the new
paved loading dock access will run through the neighboring property to the north (450 West
33rd Avenue). The applicant has provided documentation of the required easement agreement.
Page 2
ITEM II - SIP Amendment – 3300 Medalist Dr.
The additional pavement will result in 69.5% impervious surface ratio for the site, which will
remain under the maximum of 70% for the HI district. The applicant is requesting a base
standard modification (BSM) to allow reduced side yard setback for the new pavement to 10’,
where code requires a 20’ side setback.
According to the applicant, the reduced setback is needed to allow for truck maneuvering to the
loading dock. Staff does not have concerns with the reduced setback as it is abutting an
undevelopable area of the industrial site to the east that is used for stormwater ponds.
Lighting
The applicant has provided a photometric plan for the loading dock area which includes wall-
mounted fixtures along the loading dock. The plan shows 0.0 fc lighting level for most of the
new paved loading dock access. The applicant is requesting a BSM to allow 0.0 fc lighting level
for the vehicle circulation area where code requires a minimum of 0.4 fc for all vehicle
circulation areas.
According to the applicant, the required lighting is not needed for this area as it is only used for
truck maneuvering and the lighting of the trucks will be sufficient for accessing the loading
dock. Staff is supportive of the requested BSM as the subject area is isolated from all customer,
employee, and pedestrian areas and should not cause safety concerns related to vehicle and
pedestrian circulation.
Signage
No signage plans were submitted with this request.
Storm Water Management/Utilities
The Department of Public Works has noted that plans should indicate that connections will not
be in the public right-of-way. Final storm water management plans will be reviewed during the
Site Plan Review process.
Landscaping
An additional 45 paved area landscaping points are required for the added pavement. The
provided landscaping plan meets this point requirement. The applicant has provided three
arborvitae on the east side of the added pavement and is exceeding overall point requirements
for the site to offset the requested BSMs.
Page 3
ITEM II - SIP Amendment – 3300 Medalist Dr.
Design Standards
No changes are being proposed to the existing buildings, with the exception of two overhead
doors being added to the east side of the subject building (401 West 33rd Avenue). The new
overhead doors meet design standards requirements as the alteration is consistent with the
existing building design and materials.
Page 4
ITEM II - SIP Amendment – 3300 Medalist Dr.
FINDINGS/RECOMMENDATION/CONDITIONS
In its review and recommendation to the Common Council on an application for a Planned
Development district, staff recommends the Plan Commission make the following findings
based on the criteria established by Chapter 30-387 (C)(6):
(a) The proposed Planned Development project is consistent with the overall purpose
and intent of this Chapter.
(c) The proposed architecture and character of the proposed Planned Development
project is compatible with adjacent/nearby development.
(d) The proposed Planned Development project will positively contribute to and not
detract from the physical appearance and functional arrangement of development in the
area.
Staff recommends approval of the Specific Implementation Plan Amendment as proposed with
the findings listed above and the following conditions:
1. Cross access agreement for shared driveway access shall be filed with the Winnebago
County Register of Deeds.
2. Base Standard Modification (BSM) for reduced side yard setback for new pavement to
10’.
3. BSM for reduced lighting level of paved loading dock access to 0.0 fc.
4. Except as specifically modified by this Specific Implementation Plan Amendment, the
terms and conditions of the original Specific Implementation Plan dated June 13, 2023
(Resolution 23-294) remain in full force and effect.
Page 5
Sign_______ Staff ________ Date Rec’d ________
City of Oshkosh
Planned Development Application
For General Development Plan or Specific Implementation Plan
**PLEASE TYPE OR PRINT USING BLACK INK**
APPLICANT INFORMATION
Petitioner: _________________________________________________________________________________ Date: ____________
Petitioner’s Address: ________________________________________ City: ______________________ State: _____ Zip: ________
Telephone #: ( ) _________________ Email: _______________________ Contact preference: Phone Email
Status of Petitioner (Please Check): Owner Representative Tenant Prospective Buyer
Petitioner’s Signature (required): _______________________________________________________________ Date: ____________
OWNER INFORMATION
Owner(s): __________________________________________________________________________________ Date: ____________
Owner(s) Address: __________________________________________ City: ______________________ State: _____ Zip: ________
Telephone #: ( ) _________________ Email: _______________________ Contact preference: Phone Email
Ownership Status (Please Check): Individual Trust Partnership Corporation
Property Owner Consent: (required)
By signature hereon, I/We acknowledge that City officials and/or employees may, in the performance of their functions, enter
upon the property to inspect or gather other information necessary to process this application. I also understand that all
meeting dates are tentative and may be postponed by the Planning Services Division for incomplete submissions or other
administrative reasons.
Property Owner’s Signature: ___________________________________________________________________ Date: ____________
TYPE OF REQUEST:
General Development Plan (GDP) General Development Plan (GDP) Amendment
Specific Implementation Plan (SIP) Specific Implementation Plan (SIP) Amendment
SITE INFORMATION
Address/Location of Proposed Project: __________________________________________________________________________
Proposed Project Type: ________________________________________________________________________________________
Estimated Cost: _______________________________________________________________________________________________
Current Use of Property: ________________________________________________________________Zoning: ________________
Land Uses Surrounding Your Site: North: _________________________________________________________________________
South: _________________________________________________________________________
East: _________________________________________________________________________
West: _________________________________________________________________________
It is recommended that the applicant meet with Planning Services staff prior to submittal to discuss the proposal.
Application fees are due at time of submittal. Make check payable to City of Oshkosh.
Please refer to the fee schedule for appropriate fee. FEE IS NON-REFUNDABLE
For more information please visit the City’s website at www.ci.oshkosh.wi.us/Community_Development/Planning.htm
SUBMIT TO: Dept. of Community Development
215 Church Ave., P.O. Box 1130 Oshkosh, WI 54901
PHONE: (920) 236-5059
W13654 Balsam Lake Road Crivitz WI 54114
920-376-0007 rfisher@fisherandassociatesllc.com
x
6/20/24
450 W 33RD AVe Oshkosh WI 54902
920-235-3620
6/20/24
xx
401 W 33rd Ave
Manufactureing and vacant land H1 Heavy Industrial
H1 Heavy Industrial
H1 Heavy Industrial
H1 Heavy Industrial
H1 Heavy Industrial
GEN2 HOLDINGS LLC Jeff Seibold
jseibold@lakesideplastics.net
Richard J Fisher
Page 6
2
SUBMITTAL REQUIREMENTS – Must accompany the application to be complete.
(Submit only digital files. Please note at the discretion of Community Development staff may request a hard copy)
The following information must be provided in order for the application to be considered complete and able to
be scheduled for Plan Commission Review. Please use the checklist below to determine the required information
to be submitted at the time of application. If all information below cannot be provided at the time of application,
please request a waiver in writing to the Division’s Director or designee.
A General Development Plan (GDP) submittal, per Section 30-387(C)(4), shall include the following items
(Submit only digital files. Please note at the discretion of Community Development staff may request a hard copy):
General location map of the subject site depicting:
All lands for which the Planned Development is proposed and other lands within 100 feet of the
boundaries of the subject property.
Current zoning of the subject site and abutting properties, and the jurisdiction(s) that maintains that
control.
A graphic scale and north arrow.
Generalized site plan showing the pattern or proposed land uses, including:
General size, shape, and arrangement of lots and specific use areas.
Basic street pattern and pattern of internal drives.
General site grading plan showing preliminary road grades.
Basic storm drainage pattern, including proposed on-site stormwater detention.
General location of recreational and open space areas, including designation of any such areas to
be classified as common open space.
Statistical data, including:
Minimum lot sizes in the development.
Approximate areas of all lots.
Density/intensity of various parts of the development.
Building coverage.
Landscaping surface area ratio of all land uses.
Expected staging.
Conceptual landscaping plan.
General signage plan.
General outline of property owners association, covenants, easements, and deed restrictions.
A written description of the proposed Planned Development, including:
General project themes and images.
The general mix of dwelling unit types and/or land uses.
Approximate residential densities and nonresidential intensities.
General treatment of natural features.
General relationship to nearby properties and public streets.
General relationship of the project to the Comprehensive Plan or other area plans.
Proposed exceptions from the requirements of the Zoning Ordinance.
Traffic Impact Analysis (TIA), if deemed necessary by the Director of Planning Services, or designee.
A Specific Implementation Plan (SIP) submittal, per Section 30-387(C)(5), shall include the following items.
Note that the area included in an SIP may be only a portion of the area included in a previously approved GDP
(Submit only digital files. Please note at the discretion of Community Development staff may request a hard copy):
An existing conditions map of the subject site depicting the following:
All lands for which the Planned Development is proposed and other lands within 100 feet of the
boundaries of the subject site.
Current zoning of the subject property and all abutting properties, and the jurisdiction(s) that
maintains that control.
Existing utilities and recorded easements.
All lot dimensions of the subject site.
A graphic scale and a north arrow.
An SIP map of the proposed site showing at least the following:
Lot layout and the arrangements of buildings.
Public and private roads, driveways, walkways, and parking facilities.
Specific treatment and location of recreational and open space areas, including designation of
any such areas to be classified as common open space.
x
x
x
x
x
x
xx
x
x
x
N/A future
Page 7
3
Proposed grading plan.
Specific landscaping plan for the subject site, specifying the location, species, and installation size of
plantings. The landscaping plans shall include a table summarizing all proposed species.
Architectural plans for any nonresidential buildings, multi-family structures, or building clusters, other than
conventional single-family or two-family homes on individual lots, in sufficient detail to indicate the floor
area, bulk, and visual character of such buildings.
Engineering plans for all water and sewer systems, stormwater systems, roads, parking areas, and
walkways.
Signage plan for the project, including all project identification signs, concepts for public fixtures and signs,
and group development signage themes that may or may not vary from City standards or common
practices.
Specific written description of the proposed SIP including:
Specific project themes and images.
Specific mix of dwelling unit types and/or land uses.
Specific residential densities and nonresidential intensities as described by dwelling units per acre,
and landscaping surface area ratio and/or other appropriate measures of density and intensity.
Specific treatment of natural features, including parkland.
Specific relationship to nearby properties and public streets.
Statistical data on minimum lot sizes in the development, the precise areas of all development lots
and pads; density/intensity of various parts of the development; building coverage, and
landscaping surface area ratio of all land uses; proposed staging; and any other plans required by
Plan Commission.
A statement of rationale as to why PD zoning is proposed. This statement shall list the standard
zoning requirements that, in the applicant’s opinion, would inhibit the development project and the
opportunities for community betterment that are available through the proposed PD project.
A complete list of zoning standards that would not be met by the proposed SIP and the location(s)
in which such exceptions/base standard modifications would occur.
Phasing schedule, if more than one development phase is intended.
Agreements, bylaws, covenants, and other documents relative to the operational regulations of the
development and particularly providing for the permanent preservation and maintenance of common
open areas and amenities.
A written description that demonstrates how the SIP is consistent with the approved GDP and any and all
differences between the requirements of the approved GDP and the proposed SIP.
I hereby certify that to the best of my knowledge all required application materials are included with this
application. I am aware that failure to submit the required completed application materials may result in denial or
delay of the application request.
Applicant’s Signature (required): _________________________________ Date: _____________________
Grading plan update pending
x
x
x
N/A future
x
Page 8
FISHER & ASSOCIATES, LLC
Architects/Planners W13654 Balsam Lake Road Crivitz, WI 54114 Ph: 920-376-0007
City of Oshkosh (revised) June 29, 2024 Community Development Department 215 Church Ave
Oshkosh, WI 54903
Attention: Community Development Department
RE: Planned Development application for 3300 Medalist Drive and 401 W 33rd Ave., City of Oshkosh, WI To whom it may concern: This is a request for and alteration to a previously approved Planned development the is a condominium plat This property is currently an industrial site that has self-storage buildings and two other industrial use buildings. Lakeside Plastics has purchased one of the buildings located at 401 W 33rd Ave. the former use of this building was an office building occupied by Oshkosh Defense. There planned us is a mix of office and manufacturing / warehousing. The proposed alteration is to add a loading dock to the east side of the existing building that is accessed through their existing site. The tenants will be able to access their units any time via a secure gate system. The property is owned by : Marmax Holdings LLC W229 N2512 Duplainville Rd. Waukesha, WI 53188 And GEN2 HOLDINGS LLC 450 W 33RD Ave OSHKOSH, WI 54902 This project is compatible with the other land use’s surrounding property. This property and all abutting properties are zoned H1 heavy industrial with industrial buildings, storm water ponds or outdoor storage of military vehicles. The intensity of use will be low because the vehicles will be an extension of the existing Lakeside plastics operation and the new loading dock will be accessed from the existing lakeside plastics sit and not 33rd Ave.
The newly paved area will drain to the existing storm water management system that was engineered for this amount of development on this site. The overall site meets the floor area ratio, paved areas and green space requirements. The zoning standards that are requested to be modified for this project. • We are requesting that the paving setback for the truck maneuvering be reduced from 20’-0” to 10’-0” per the attached plan. This updated plan has been revised to narrow the maneuvering lane to 20’ vs 30’-0” and the edge of paving has been moved away from the property line to 10;-0” If you need additional information, please contact me or the owners’ agent Brian Fisher at 262-613-4015.
Sincerely,
Richard J. Fisher, A.I.A. Senior Project Architect
Page 9
Page 10
SIP AMENDMENT
3300 MEDALIST DR
PC: 8.6.2024
OSHKOSH CORP
OSHKOSH DEFENSE LLC
PO BOX 2566
OSHKOSH WI 54903-2566
MARVEL REAL ESTATE CO LLC
AMADA MARVEL INC
3501 MARVEL DR
OSHKOSH WI 54902-7115
ARROWHEAD SYSTEMS INC
124 N COLUMBUS ST
RANDOLPH WI 53956-1204
ARROWHEAD SYSTEMS INC
124 N COLUMBUS ST
RANDOLPH WI 53956-1204
DAHL PROPERTIES LLC
PO BOX 2944
OSHKOSH WI 54903-2944
3345 MEDALIST DRIVE LLC
3345 MEDALIST DR
OSHKOSH WI 54902-7125
ARDON LLC
BADGER MILL SUPPLY
3250 MEDALIST DR
OSHKOSH WI 54902-7124
GEN2 HOLDINGS LLC
450 W 33RD AVE
OSHKOSH WI 54902-7164
MARMAX HOLDINGS LLC
W229N2512 DUPLAINVILLE RD
WAUKESHA WI 53186-1004
TOWN OF BLACK WOLF
380 E BLACK WOLF AVE
OSHKOSH WI 54902-9139
TOWN OF NEKIMI
3790 PICKETT RD
OSHKOSH WI 54904-6208
WINNEBAGO COUNTY AIRPORT
525 W 20TH AVE
OSHKOSH WI 54902-6871
Page 11
W 34TH AV
MARVEL DR
MEDALIST DR W 33RD AV
J:\GIS\Planning\Plan Commission Site Plan Map Template\2023 Plan Commission Site Plan Map Template.mxd User: katrinam
Prepared by: City of Oshkosh, WI
Printing Date: 7/11/2024
1 in = 220 ft1 in = 0.04 mi¯3300 MEDALIST DR
City of Oshkosh maps and data are intended to be used for general identification purposes only, and the City of Oshkoshassumes no liability for the accuracy of the information. Those using the information are responsible for verifying accuracy. Forfull disclaimer please go to www.ci.oshkosh.wi.us/GISdisclaimer
Page 12
W 35TH AV
W 29TH AV
W 33RD AV
MEDALIST DR
MARVEL DR
W WAUKAU AV
OREGON ST
HUGHES ST
Oshkosh
Oshkosh
City Limit
City Limit
Os hk os hOshkoshCity L i m itCity Li m i t
Oshkosh City
Oshkosh City
LimitLimit
OshkoshOshkoshCity LimitCity LimitOshkosh City Limit
Oshkosh City Limit
Oshkosh City LimitOshkosh City Limit
HI
HI
HI
HI-PD
HI-PD
I
I
I
I-PD
SR-5
SR-5
SR-5-PD
J:\GIS\Planning\Plan Commission Site Plan Map Template\2023 Plan Commission Site Plan Map Template.mxd User: katrinam
Prepared by: City of Oshkosh, WI
Printing Date: 7/11/2024
1 in = 600 ft1 in = 0.11 mi¯3300 MEDALIST DR
City of Oshkosh maps and data are intended to be used for general identification purposes only, and the City of Oshkoshassumes no liability for the accuracy of the information. Those using the information are responsible for verifying accuracy. Forfull disclaimer please go to www.ci.oshkosh.wi.us/GISdisclaimer
Page 13
W 34TH AV
MARVEL DR
MEDALIST DR W 33RD AV
J:\GIS\Planning\Plan Commission Site Plan Map Template\2023 Plan Commission Site Plan Map Template.mxd User: katrinam
Prepared by: City of Oshkosh, WI
Printing Date: 7/11/2024
1 in = 200 ft1 in = 0.04 mi¯3300 MEDALIST DR
City of Oshkosh maps and data are intended to be used for general identification purposes only, and the City of Oshkoshassumes no liability for the accuracy of the information. Those using the information are responsible for verifying accuracy. Forfull disclaimer please go to www.ci.oshkosh.wi.us/GISdisclaimer
Page 14