March 24, 2004
City of Oshkosh
P.O. Box 1130
Oshkosh, WI 54903-1130
Attention:
David Patek, DPW
Re:
Agreement for Planning Services
Pearl Avenue Transportation Study
This is an Agreement between the City of Oshkosh, hereinafter referred to as OWNER, and
Strand Associates, Inc., hereinafter referred to as ENGINEER, to provide planning services
(Services) related to the Pearl Avenue Corridor from N. Main Street to W. Murdoch Avenue.
This Agreement shall be in accordance with the following Scope of Services, Compensation,
Payment, Schedule, and other General Conditions contained herein.
Scope of Services
A.
Collect Information
I. Perform PM peak tuming movement counts at key intersections
a. Main Street! Algoma Boulevard
b. Main Street/High Avenue
c. Main StreetlPearl Avenue
d. Algoma Boulevard/High Avenue
Collect existing plat maps/right-of-way
Create a photo log of affected streets
2.
3.
B.
Construct traffic operations computer model and evaluate traffic operations
I. Create existing network traffic volume schematic (P.M. peak)
2. Create proposed network traffic volume schematic (P.M. peak)
3. Create a Synchro model of the existing network
4. Create a Synchro model of the proposed street network
C.
Develop roadway concepts
I. Typical sections for Pearl Avenue
a. Block I (East)
b. Block 2 (Middle)
c. Block 3 (West)
Develop needed intersection configurations
a. Main StreetlPe¡¡¡:l,.Ayenue
b. Pearl Avenue~~"Street
c. PearlAvenue/High Avenue
d. Pearl Avenue/High Avenue/Algoma Boulevard
Develop horizontal alignment and right-of-way needs on plan sheets
2.
3.
51
STRAND
Assoe'ATES, 'Ne'
ENS'NEERS
City of Oshkosh
Page 2
March 24, 2004
D.
Measure impacts
1. Right-of-way Needs
2. Construction Costs
3. Hist!4fpreliminary review
E.
Document findings in a draft and final report
ENGINEER will attend two coordination meetings with the OWNER during the alternatives
development. These planning services do not include meetings with the University, affected
landowners, or the public.
Compensation
The Services performed under this Agreement shall be provided for a lump sum fee of $34,850.
The fee assumes there will be no significant delays, extensions, amendments, or changes in the
Scope of Services.
Payment
OWNER shall make monthly payments to ENGINEER for Services performed in the preceding
month based upon monthly statements. Nonpayment 30 days after the date of receipt of invoice
may, at ENGINEER's option, result in assessment of a I percent per month carrying charge on
the unpaid balance.
Schedule
A"'-(;,usrl
Assuming ENGINEER receives the signed Agreement by ~, 2004, a draft report will be
completed about A'Ig1'gt 15, 2g(K
~N. I '1.coS
Termination
This Agreement may be terminated with cause in whole or in part in writing by either party
subject to a two-week notice and the right ofthe party being terminated to meet and discuss the
termination before the termination takes place. ENGINEER shall be paid for all completed or
obligated Services up to the date of termination.
Remedies
Except as may be otherwise provided in this Agreement, all claims, counterclaims, disputes, and
other matters in question between OWNER and ENGINEER arising out of or relating to this
Agreement or the breach thereof shall be decided by mediation.
MA Y,mrolS,\@Sai\351--400\3821016lWrdlP"dAwTro,pSldy.Agr.doc
51
STRAND
ASSOO'ATES. 'Ne'
ENG'NEERS
City of Oshkosh
Page 3
March 24, 2004
IN WITNESS WHEREOF the parties hereto have made and executed this Agreement.
ENGINEER:
STRAND ASSOCIATES, INc.
--T7.~¿¡;vfí/~ ::3 /2 'J/o,r:
Roger H. Huchthausen Date
Corporate Secretary
OWNER:
CITY OF OSHKOSH
~ø~
Richard A. Wollangk
City Manager
1-;fJ i;;exf-f
ate
I certify that provision has been made to pay the
liability that will accrue to the City of Oshkosh,
Wisconsin under this Change Order.
APPROVED AS TO FORM:
I'~
'U .~
A j
~ity ney
MAY,mroIS,\@S,i\351--400\38210161WrdlP"dAwTrmpStdy.Agr.doc
7 ~;+.q -dOO':!
Date
7-ðY'" n4
Date
;2$.oj"
Date
RECEIVED
JUL 27 2004
¡ DOE[:HT. OF PUBLIC WORKS
, 0 KOSH WISCONSIN
TM
July 26, 2004
Mr. David C. Patek
Director of Public Works
City of Oshkosh
215 Church Avenue
P.O. Box 1130
Oshkosh,WI54903-1130
Re: Pearl Avenue Transportation Study
Dear Mr. Patek,
This letter acknowledges and confirms that UW Oshkosh will provide partial funding in
the amount of $17,425 for the Pearl Avenue Transportation Study. I understand that the
Department of Public Works will administer the agreernent with the engineering firm and
send an invoice at the completion of the study. I would like to be included in all
meetings with the firm once the contract has been signed.
Sincerely,
~G.~
Steven A. Arndt
Cc:
Tom Sonnleitner
Jackson Kinney