PURPOSE:
CHANGE ORDER NO.2, PUBLIC WORKS CONTRACT NO. 03-04
INITIATED BY:
DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
THE SELMER COMPANY
2200 WOODALE AVE.
GREEN BAY, WI 54313
Net Increase to contract:
$-0-
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Accl. No. 551-1910-1799-00000 - Sewer Utility - Constr. in Progress
July 20, 2004
CHANGE ORDER NO.2
PROJECT:
OWNER:
CONTRACT:
CONTRACTOR:
Standby Power System and SCADA Upgrade
City of Oshkosh, Wisconsin
03-04
The Selmer Company
Additional work for building foundation caissons; added ADD
length, additional materials and obstruction time.
Trucking and landfill disposal for solid waste fill
material.
Reduce project contingency allowance (pay Request
Line Item No.) from $43,277.85 to $252.29.
Description of Change
2a
2b
2c
TOTAL VALUE OF TInS CHANGE ORDER:
Contract Price Adjustment
Original Contract Price
Previous Change Order Adjustments
Adjustment in Contract Price this Change Order
Current Contract Price including this Change Order
Contract Completion Date Adjustment
Original Contract Completion Date
Contract Completion Date Adjustments
due to previous Change Orders
Contract Completion Date Adjustments
due to this Change Order
Current Contract Completion Dates
including all Change Orders
Substantial Completion
Final Completion
Substantial Completion
Final Completion
Substantial Completion
Final Completion
Substantial Completion
Final Completion
ADD
$37,222.56
$5,803.00
DEDUCT
($43,025.56)
$0.00
$2,837,000.00
$0
$0
$2,837,000.00
November 30, 2004
December 31, 2004
0 days
0 days
0 days
0 days
November 30, 2004
December 31, 2004