HomeMy WebLinkAbout04-256.doc
JULY 27, 2004
04-256
RESOLUTION
(CARRIED 7 -0
LOST
LAID OVER
WITHDRAWN
PURPOSE:
CHANGE ORDER NO.1, PUBLIC WORKS CONTRACT NO. 04-05
INITIATED BY:
DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
MAXCOR
Lockport, ILL
Change to Contract:
No.1 - Deduct:
No.2 - Additional Work
Net change to contract
($2,200.00)
+ 2,200.00
-0-
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 541-1810-1799-00000 - Water Utility - Const. in Progress
Oshkosh, Wisconsin
1,250,000 Gallon Hydropillar (Washburn Street Tank)
City of Oshkosh Contract No. 04-05
Contract No. 49-71-06-01-04
June 17, 2004
Change Order No.1
All General Conditions and Information for Bidders shall apply. This Change Order shall
become a portion of the original Contract Documents.
1.
The following is a price adjustment (deduction) is for the design change on the
manway:
Original bid price for "Manway" was $8,300. Price adjustment (deduction)for
the design change is:
Two Thousand. Two Hundred Dollars
($2.200)
2.
The following work shall be completed as additional to the contract:
Increase the specified new wet interior ladder length from 20ft. to 29ft. Work to
include installation of a new fall prevention device on the new section. Perform
all other work per Item 3.21-NEW LADDER found in Section 05000-Metals.
The contractor agrees to perform the work for the sum of:
Two Thousand. Two Hundred Dollars
$2.200
Original Contract Price:
No 1 Deduct:
No.2 Additionill Work:
Adjusted Contract Price:
$174,400
- (2,200)
2.200
$174,400
Contract time remains the same.