HomeMy WebLinkAboutPW CNT 03-03/Cng Ord #2 C7~Þ CHANGE ORDER # 2 DATED: April 30, 2004 TO: James Cape & Sons Co. 6422 N. HWY 31 P. O. Box 044580 Racine, WI 54304-7012 Your present contract with the City of Oshkosh, Contract No. and changed as follows: 03-03 , is hereby amended NET DECREASE TO SECTION I - CONCRETE PAVING: ($40,755.08) ($40,755.08) NET DECREASE TO CONTRACT: Recommended: JJ-J ~.~ Director of Public orks Approved and accepted: :I~~ -q~¡D9iI~ ontraétor r s-j; f I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. Zß~a ~ Comptroller CONTRACT: 03-03 CHANGE ORDER # 2 SECTION I . CONCRETE PAVING DESCRIPTION 1. Approx. 6,850 square yards of pavement removal, complete as soecified, oer sQuare vard 6,850.00 6,796.50 -53.50 $3.00 ($160.50 2. Approx. 59,950 square feet of sidewalk and driveway removal, compiete as specified, per square foot 59,950.00 65,253.90 5,303.90 $0.58 $3,076.26 3. Approx. 23,300 cubic yards of excavation, complete as specified, per cubic yard ($2,510.00 23,300.00 22,798.00 -502.00 $5.00 4. Approx. 19,550 square yards of 7" non-reinforced concrete pavement, includln9 integral curb and grading (base in place), complete as specified, per ($7,211.60) SQuare vard 19,550.00 19,222.20 -327.80 $22.00 5. Approx. 30,750 square yards of 7" non-reinforced concrete pavement, including integral curb, 5" base material & grading, complete as specified, per sQuare vard 30,750.00 30,445.20 -304.80 $22.20 ($6,766.56) 6. Approx. 3,750 square yards of 8" non- reinforced concrete pavement, including integral curb, 6" base material & grading, complete as specified, per ($707.20' SQuare vard 3,750.00 3,724.00 -26.00 $27.20 7. Approx. 1,250 square yards of 8" non- reinforced concrete pavement H.E.S., Including integral curb, 6" base material & grading, complete as specified, per sQuare vard 1,250.00 1,504.10 254.10 $35.60 $9,045.96 8. Approx. 250 square yards of 8" reinforced concrete pavement, including integral curb, 6" base materiai & grading, complete as specified, per SQuare vard 250.00 275.00 25.00 $28.00 $700.00 Page 1 CONTRACT: 03-03 CHANGE ORDER # 2 ITEM CONTRACT INSTALLED NET NET CDSTPER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 9. Approx. 1,965 linear feet of 12" wide radius curb head, complete as specified, per linear foot 1,965.00 2,415.50 450.50 $3.21 $1,446.11 10. Approx.100 iinearfeetof standard 24" curb & gutter, compiete as specified, per iinearfoot 100.00 159.50 59.50 $14.90 $886.55 11. Approx. 1,350 linear feet of standard 30" curb & gutter, complete as specified, per linear foot 1,350.00 1,420.10 70.10 $13.78 $965.98 12. Approx. 130 linear feet of 6" x 12" curb, complete as specified, per linear foot 130.00 122.00 -8.00 $13.26 ($106.08 13. Approx. 195 linear feet of standard 36" curb & gutter (mountable), complete as ($156.25 specified, ner linear foot 195.00 184.70 -10.30 $15.17 14. Approx. 29,200 square feet of 4" concrete sidewalk, complete as specified ner sQuare foot 29,200.00 33,072.30 3,872.30 $2.28 $8,828.84 15. Approx. 57,625 square feet of 6" concrete sidewalk & driveway, complete as specified, per SQuare foot 57,625.00 57,710.20 85.20 $2.62 $223.22 16. Approx. 70 square feet of 6" concrete steps, complete as specified, per SQuare foot 70.00 82.30 12.30 $30.00 $369.00 17. Approx. 155 square yards of 3" thick asphaltic concrete driveway, compiete as specified, per sQuare yard 155.00 146.30 -8.70 $27.00 ($234.90 18. Approx. 2,750 square yards of 3" asphaltic concrete transition, complete as specified, per SQuare yard 2,750.00 2,018.60 -731.40 $17.34 ($12,682.48 19. Approx. 2,375 square yards of 5" asphaltic concrete transition, complete as specified, per SQuare yard 2,375.00 2,299.60 -75.40 $17.77 ($1,339.86) 20. Approx. 425 square yards Qf 2" asphaltic CQncrete pavement over 8" concrete base course, compiete as specified, per souare yard 425.00 412.20 -12.80 $39.10 ($500.48 Page 2 CONTRACT: 03-03 CHANGE ORDER # 2 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 21. Approx. 70 tons of asphaltic concrete binder material, compiete as ($279.82) specified, oer ton 70.00 63.20 -6.80 $41.15 22. Approx. 60 tons of asphaltic concrete surface material, complete as specified, per ton 60.00 64.17 4.17 $43.95 $183.27 23. Approx. 17 gallons of tack or prime coat, complete as specified, per callan 17.00 15.10 -1.90 $10.10 ($19.19 24. Approx. 630 square yards of asphaltic pavement milling, complete as soecified, ner sQuare yard 630.00 602.50 -27.50 $5.30 ($145.75 25. Preparation of foundation for asphalt paving on Cleveland Avenue, complete as specified, lump sum 1.00 1.00 $928.00 26. Furnish and install approx. 8,600 tons of crushed stone base course, complete as specified, per ton 8,600.00 2,560.76 -6,039.24 $6.58 ($39,738.20 27. Approx. 4,030 linear feet of sawing, cornplete as ($47.42 soecified, ner linear foot 4,030.00 4,002.90 -27.10 $1.75 28. Furnish and install approx. 405 pavernent ties, complete as specified, each 405.00 414.00 9.00 $6.00 $54.00 29. Adjust approx. 295 manholes and inlets, complete as specified, each 295.00 280.00 -15.00 $357.15 ($5,357.25) 30. Furnish and install approx. 840 linear feet of No.4 reinforcing bars, complete as specified, per linear foot 840.00 1,500.00 660.00 $0.75 $495.00 31. Remove approx. 205 linear feet of railroad rails and ties, complete as specified, er linear foot 205.00 213.00 8.00 $6.00 $48.00 32. Furnish and install approx. 16 trees, complete as specified, each 16.00 4.00 -12.00 $250.00 ($3,000.00 33. Remove approx. 390 I.D. of trees and stumps, complete as specified, per inch diameter 390.00 376.00 -14.00 $20.15 ($282.10 Page 3 CONTRACT: 03-03 CHANGE ORDER # 2 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 34. Remove approx. 26 I.D. of stumps, complete as specified, per inch ($5.76) diameter 26.00 24.00 -2.00 $2.88 35. Terrace work on Central Street, complete as specified, lump sum 1.00 1.00 $2,275.68 36. Terrace work on Cherry Park Court, complete as soecified, lump sum 1.00 1.00 $8,083.40 37. Terrace work on Cleveland Avenue, complete as specified, lumo sum 1.00 1.00 $89.88 38. Terrace work on Farmstead Lane, complete as specified, lump sum 1.00 1.00 $4,776.88 39. Terrace work on Frederick Street, complete as soecified, lumo sum 1.00 1.00 $4,049.24 40. Terrace work on Greenbriar Court, complete as specified, lump sum 1.00 1.00 $1,802.00 41. Terrace work on Grove Street, complete as specified, lump sum 1.00 1.00 $9,161.16 42. Terrace work on Guenther Street, complete as specified, lumn sum 1.00 1.00 $9,316.32 43. Terrace work on Hearthstone Drive, complete as specified, lump sum 1.00 1.00 $3,889.36 44. Terrace work on Ida Avenue, complete as specified, lumn sum 1.00 1.00 $707.04 45. Terrace work on Melvin Avenue, complete as specified, lump sum 1.00 1.00 $2,604.16 46. Terrace work on Minnesota Street, complete as specified, lump sum 1.00 1.00 $6,598.60 47. Terrace work on Park Ridge Avenue, complete as sDecified, lumn sum 1.00 1.00 $954.20 48. Terrace work on Parkway Avenue, complete as soecified, lumD sum 1.00 1.00 $901.52 49. Terrace work on Sharratt Drive, complete as sDeclfied lumD sum 1.00 1.00 $3,014.24 Page 4 CONTRACT: 03-03 CHANGE ORDER # 2 ITEM CONTRACT INSTALLED NET NET COSTPER INCREASE IN DECREASE IN DESCRIPTION CONTRACT CONTRACT NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 50. Terrace work on State Street, complete as sDecified, lumo sum 1.00 1.00 $2,233.80 51. Terrace work on Vinland Street, complete as sDecified, lumo sum 1.00 1.00 $3,618.00 52. Terrace work on Weatherstone Drive, complete as specified, lump sum 1.00 1.00 $3,059.00 53. Terrace work on W. 18th Avenue, complete as specified, lump sum 1.00 1.00 $2,565.04 54. Terrace work on W. 20th Avenue railroad crossing, complete as specified, lump sum 1.00 1.00 $1,304.88 55. Provide $375.00 to the City of Oshkosh for project management communications, complete as specified, lump sum 1.00 1.00 $375.00 SECTION I - (BID ITEMS 1 - 55) - SUB-TOTALS $26,322.19 ($81,251.40) ADDITONAL WORK REQUIRED: C.O. # 2 - SECTION I DESCRIPTION 1 Loading, hauling and tipping fees for railroad ties @ Frederick Street & Irving Avenue intersection, lump sum 1.00 1.00 $900.00 $900.00 2 Loading, hauling and tipping fees for railroad ties on 18th Avenue, lump sum 1.00 1.00 $1,483.07 $1,483.07 3 Handling contaminated soils on State Street, lump sum 1.00 1.00 $1,490.20 $1,490.20 4 Additional topsoil and landscaping @ 4085 Sharratt Drive, lump sum 1.00 1.00 $402.00 $402.00 Page 5 CONTRACT: 03-03 CHANGE ORDER # 2 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 16 Landscaping at the intersection of Bismarck Avenue & Sawyer Street due to extension of construction limits, lump sum 1.00 1.00 $289.02 $289.Q2 ADDITIONAL WORK: C.O. # 1 . (ITEMS 1 -16) - SUB.TOTAL $14,174.13 $0.00 ($40,755.08) NET DECREASE TO SECTION 1- NET INCREASE TO SECTION I NET DECREASE TO SECTION I $40,496.32 ($81,251.40) ($40,755.08) NET DECREASE TO CONTRACT: Page 7 CONTRACT: 03-03 CHANGE ORDER # 2 ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE PRICE 5 Clearing and grubbing vision triangle @ southwest corner Cherry Park Court & U.S.H. "45", lumn sum 1.00 1.00 $3,050.00 $3,050.00 6 Provide and install erosion mat @ U.S.H. "45" & Cherry Park Court drainage ditches, per snuare "ard 184.50 184.50 $2.01 $370.85 7 Additional topsail and landscaping on Cleveland Avenue due to additional curb and gutter removed, lumn sum 1.00 1.00 $560.73 $560.73 8 Additonal topsoil, iandscaping and erosion mat on Frederick Street west side from Parkway Avenue to Ida Avenue, lumn sum 1.00 1.00 $1,268.06 $1,268.06 9 Additional landscaping for two (2) sanitary laterals @ Minnesota Street and 18th Avenue, lumn sum 1.00 1.00 $453.35 $453.35 10 Root pruning additonal trees for sidewalk installation on Vinland Street. lumn sum 1.00 1.00 $112.50 $112.50 11 Curb cuts on Vinland Street, W. Parkway Avenue and Hearthstone Drive, lumn sum 1.00 1.00 $678.50 $678.50 12 Five (5) cubic yards of slurry to fill in 10 linear feet of abandoned 48" storm sewer on 24th Avenue @ railroad crossing, per cubic yard 5.00 5.00 $85.00 $425.00 13 200 tons of salvaged base course hauled & placed on Cherry Park Court, per ton 200.00 200.00 $3.50 $700.00 14 Breakdown and reset paving forms for west half of State Street, lumo sum 1.00 1.00 $1,193.72 $1,193.72 15 Extra labor & materials to excavate and place gravel at the intersections of 17th Avenue & 18th Avenue@ Minnesota Street, in lieu of excavation & asphalt transition item, lump sum 1.00 1.00 $797.13 $797.13 Page 6