Loading...
HomeMy WebLinkAboutCost Estimate SEH Fire Training Center 2024Revised 1/8/2024 Oshkosh Fire Department Training Facility Adaptive Reuse Renovation Cost Estimate Review and Revision Item Quantity Unit Remarks Low High Low High Armory Renovation Selective Demolition 11,305 SF 5.50 7.00 $ 62,178 $ 79,135 Training Facility & EOC 7,705 SF 190.00 265.00 $ 1,463,950 $ 2,041,825 Apparatus Bay & Dirty Room 3,600 SF 120.00 135.00 $ 432,000 $ 486,000 Subtotal $ 1,958,128 $ 2,606,960 Cold Storage Building Selective Demolition 1,300 SF 5.50 7.00 $ 7,150 $ 9,100 Storage Renovation 1,300 SF 150.00 185.00 $ 195,000 $ 240,500 Subtotal $ 202,150 $ 249,600 Site Work South Lot at Training Tower 21,138.00 SF 9.00 11.00 $ 190,242 $ 232,518 North Lot Asphalt Paving 25,000 SF 9.00 11.00 $ 225,000 $ 275,000 Concrete Flatwork 5,000 SF 7.50 10.50 $ 37,500 $ 52,500 Sub-Total $ 452,742 $ 405,630 Construction Allowances Full Roof Replacement 25,000.00 SF $10.50 $13.75 $ 262,500 $ 343,750 App Bay Direct Capture Exhaust System 6 $17,000.00 $19,000.00 $ 102,000 $ 114,000 Hydrant Loop and Fire Protection 1 $185,000.00 $200,000.00 $ 185,000 $ 200,000 Fence Gate Controls 2 $14,000.00 $17,000.00 $ 28,000 $ 34,000 Landscape Restoration 1 $20,000.00 $28,000.00 $ 20,000 $ 28,000 Generator 1 $45,000.00 $60,000.00 $ 45,000 $ 60,000 Firefighters' Memorial 1 $25,000.00 $50,000.00 $ 25,000 $ 50,000 Site Lighting 1 $60,000.00 $80,000.00 $ 60,000 $ 80,000 Sub-Total $ 727,500 $ 909,750 Escalation (8% per year)$ 267,242 $ 333,755 Assume construction starts in Fall 2024 Sub-Total Hard Construction Cost $ 3,607,761 $ 4,505,695 Hard Cost Contingency (17%)$ 613,319 $ 765,968 $ 4,221,080 $ 5,271,663 Allowances for Items to be Purchased by the City Asbestos Abatement 16,000 SF $9.00 $11.25 $144,000.00 $180,000.00 Furniture and Equipment (5%)$ 102,280 $ 124,860 Computer Systems $ 30,000 $ 40,000 Wireless Network System $ 12,000 $ 18,000 Maintenance/Janitorial Equipment $ 3,500 $ 5,000 Telephone System $ 7,500 $ 10,000 Wireless Telephone Boosters/Amplifiers $ - $ - Not included FD Training Equipment $ 50,000 $ 75,000 SCBA, Extractor, Etc. California Tower $ 0 $ 0 Fully Installed 2021 30' x 24' Burn Box $ 250,000 $ 320,000 Single Story Miscellaneous Equipment and Furnishings $ 20,000 $ 30,000 For items such as lobby display, etc. $ 619,280 $ 802,860 Allowances for Items Fees and Soft Costs Total Allowances for Items to be Purchased by the City Cost/Unit Construction Cost Total Estimate of Probable Hard Construction Cost DocuSign Envelope ID: 10BD28A2-7558-4D89-A826-E2BB072F33B7 Revised 1/8/2024 Oshkosh Fire Department Training Facility Adaptive Reuse Renovation Cost Estimate Review and Revision A/E Fees (9.5%) of construction cost $ 401,003 $ 500,808 Incl. civil, security and landscape design Surveys & Soil Investigations $ 12,000 $ 15,000 Material Testing During Construction $ 15,000 $ 20,000 Building Commissioning $ 25,000 $ 35,000 DSPS Review $ 5,000 $ 8,000 Permit Fees $ - $ - Assumed to be waived by the City Printing Costs $ 5,000 $ 8,000 $ 25,000 $ 35,000 Moving Costs $ 18,000 $ 24,000 Utility costs during construction $ 10,000 $ 12,000 Total Allowances for Fees and Soft Costs $ 516,003 $ 657,808 Owner's Soft Cost Contingency (5%)$ 170,292 $ 219,100 TOTAL PROJECT BUDGET $ 5,526,655 $ 6,951,432 NOTES: Utility Company Charges (Electric, Gas, Telephone) The budget for this project is based on historical information and current construction industry cost trends. Many assumptions were made in order to establish pricing for the work as shown. These costs may vary significantly as the design is more fully developed. Market conditions, including labor and material cost escalation, at the time the project is bid will impact the pricing. The project budget does not include financing costs or legal fees. DocuSign Envelope ID: 10BD28A2-7558-4D89-A826-E2BB072F33B7