CHANGE ORDER NO. 1
Date: September 17, 2003
Your present contract with the City of Oshkosh for construction of a pedestrian trail known as the Sawyer Creek
Pedestrian Trail West Leg, is hereby amended and changed as follows:
ADD:
Per the attached letter dated September 17, 2003
$13,022.00
RECOM~/F.~D.~
Dire¢oro~b~muni~elopment
I certify that provision has been made to
pay the liability that will accrue to the City
of Oshkosh, Wisconsin, under the within
Change Order.
Finance Dimc[or
r~enson, A~ant-(~ty At~o~'ney
September 18, 2003
Mr. Jackson Kinney
City of Oshkosh
P.O. Box 1130
OShkOsh, WI 53903-1130
Reference: Sawyer Creek Pedestrian Trail West Leg
Change Request #1
Dear Mr. Kinney:
Please review the following Change .Request and call with any questions.
The changes to the scope of work are as follows:
Install a 11' high wall in lieu of a 4' high Wall for the bridge
abutment to reinforce the long-term viability of the
structure given the topographical conditionS.
1. Form, reinforce, and pour extra wall, $ 4,340.00
2, Excavate extra so~ due to tallerwalL $ 945.00
3. Extend boardwalk 16-feet. $ 2,376.00
4. Add riprap for erosion control under boardwalk, $ 400:00
The following items were not anticipated or seen during
the bidding process:
5. Remove trees from site.
6. Repair muddy 340-foot by 12-foot area by
removing 9inches of material and installing 12
inches of 3-inch minus base matedaL
$ 1,050.00
$ 3,911.00
Add per change request #1. $ 13,022.00
Original lump sum price: $ 94,124.00
Revised Contract Amount: $ 107,146.00
Thank you for the opportunity tO provide you with this Change Request. '
Sincerely,
C. R. MEYER AN0 SONs COMPANY
Todd M. Dalbec, E.LT.
Project Engineer