HomeMy WebLinkAboutPW CNT 02-03B/Cng Ord #1TO:
Dorner-Stahl, InC.
P. O. Box 129
Luxemburg, WI 54217
CHANGE ORDER # 1
DATED: December 1, 2003
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
02-03B
is hereby amended
NET DECREASE TO SECTION I - CONCRETE PAVING:
$17,210.65)
Recommended:
Director of Public Wo~s
CITY OF OSHKOSH ~
- '' ' City
"" Cit9 C[~rk ./'" ~
.Approv and acc "-...~)
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Appr/~ved as to forte:
City Attorney _ v
CONTRACT: 02-03B CHANGE ORDER# 1
SECTION I - CONCRETE PAVING
ITEM DESCRIPTION CONTRACT
NUMBER QUANTITIES
INSTALLED
QUANT/T/ES
NET
INCREASE
NET
DECREASE
COST PER INCREASE IN
CONTRACT
UNIT PRICE
PR CE
lB. Approx. 1,260 square
~,ards of pavement
removal, complete as
specified, per square yard 1,260.00 984.80 -275.20 $5.00 ($1,376.00
2B. Approx. 10,225 square feel
of sidewalk and driveway
removal, complete as
specified, per square foot
10,225.00 10,310.00 85.00 $0.45 $38.25
3B. Approx. 4,800 cubic yards
~f excavation, complete as
specified, per cubic yard
4,800.00 4,274.40 -525.60 $5.00 ($2,628.00
4B. Approx. 8,180 square
ards of 7" non-reinforced
:oncrete pavement,
including integral curb, 5"
base material & grading,
:omplete as specified, per
square yard 8,180.00 8,159.20 -20.80 $20.00 ($416.00)
5B. Approx. 445 linear feet of
12" radius curb & head,
complete as specified, per
linear foot 445.00 442.40 -2.60 $10.00 ($26.00)
6B. Approx. 235 linear feet of
standard 30" curb & gutter,
complete as specified, per
linear foot 235.00 247.10 12.10 $20.00 $242.00
7B. No Bid Item
aB. Approx. 2,785 square feet
Df 4" concrete sidewalk,
complete as specified, per
square foot 2,785.00 3,064.60 279.60 $2.40 $671.05
9B. Approx. 9,680 square feet
Df 6" concrete sidewalk &
driveway, complete as
specified, per square foot 9,680.00 10,154.80 474.80 $2.80 $1,329.44
10B. No Bid item
11B. Approx. 635 square yards
of 3" asphaltic concrete
transition, complete as
specified, per square yard 635.00 649.70 14.70 $19.00 $279.30
12B. &pprox. 875 square yards
of 5" asphaltic concrete
transition, complete as
specified, per square yard 875.00 976.90 101.90 , $20.00 $2,038.00
Page 1
CONTRACT: 02-03B CHANGE ORDER # 1
INCREASE IN DECREASE IN
ITEM CONTRACT INSTALLED NET NET COST PER
DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
13B. Furnish and install approx.
1,925 tons of crushed
stone base course,
complete as specified, per
ton 1,925.00 0.00 -1,925.00 $8.5C ($16,362.50
14B. Approx. 640 linear feet of
sawing, complete as
specified, per linear foot 640.00 304.30 -335.70 $2.05 ($688.191
15B. No Bid Item
16B. Adjustapprox. 53
manholes and inlets,
complete as specified,
each 53.00 53.00 $230.00
17B. Furnish and install approx.
¢ trees, complete as
specified, each 4.00 3.00 -1.00 $400.00 ($400.00)
18B. No Bid Item
19B. F~emove approx. 36 I.D. of
[rees and stumps,
;omplete as specified, per
inch diameter 36.00 40.00 4.00 $22.00 $88.00
20B. No Bid Item
21B. Terrace work on Powers
Street, complete as
specified, lump sum 1.00 1.00 $13,000.00
SECTION I - (BID ITEMS lB - 2t B) - SUB-TOTALS
$4,686.04 ($21,896.69)
NET DECREASE TO CONTRACT:
($'17,2'10.65)
Page 2