HomeMy WebLinkAbout22-08 CO #1 (FINAL)_9-28-23 Vinton Co.TO: VINTON CONSTRUCTION CO CHANGE ORDER #1 (FINAL)
1322 33RD STREET
TWO RIVERS, WI 54241
Your present contract with the City of Oshkosh, Contract No. 22-08, awarded August 10, 2022, is hereby amended
and changed as follows:
NET DECREASE TO WORK UNIT A: ($42,059.42)
NET DECREASE TO CONTRACT ($42,059.42)
SECTION I TOTALS
BID TOTAL $429,929.75 $429,929.75
CO #1 ($42,059.42)($42,059.42)
CONTRACT TOTAL $387,870.33 $387,870.33
CITY OF OSHKOSH
BY:
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Approved as to form:
City Attorney
DATE: SEPTEMBER 28, 2023
______________________________
Comptroller
______________________________
Contractor
______________________________
Approved and accepted:
______________________________
City Manager
City Clerk
______________________________
DocuSign Envelope ID: 0EE7B08C-9A4F-4DA0-9529-8996278D3814
CONTRACT 22-08 CHANGE ORDER #1 (FINAL)
22-08
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
1050
Mobilization; complete as
specified
Lump
Sum 1.00 1.00 $61,000.00
1103
Removing building
foundations; complete as
specified
Linear
Feet 525.00 20.00 -505.00 $5.00 ($2,525.00)
1110
Removing curb and gutter;
complete as specified
Linear
Feet 250.00 244.23 -5.77 $3.00 ($17.31)
1120
Removing concrete and
asphalt sidewalk and
driveway; complete as
specified
Square
Feet 1,000.00 1,100.62 100.62 $0.85 $85.53
1200
Unclassified excavation;
complete as specified
Cubic
Yards 725.00 717.39 -7.61 $33.76 ($256.91)
1220
Excavation special (paving);
complete as specified Tons 110.00 0.00 -110.00 $23.91 ($2,630.10)
1250
Furnish and install dumpster
enclosure (includes
foundation; concrete slab;
walls; gates; and all
associated materials and
labor); complete as specified
Lump
Sum 1.00 1.00 $66,169.00
1313
8" concrete pavement HES;
with 6" CABC and grading;
complete as specified
Square
Yards 85.00 88.26 3.26 $96.00 $312.96
1319
8" concrete pavement HES
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
as specified
Square
Yards 450.00 490.19 40.19 $105.00 $4,219.95
1340
Crushed aggregate base
course; complete as specified Tons 400.00 17.90 -382.10 $18.75 ($7,164.38)
1350
Pavement ties; complete as
specified Each 12.00 15.00 3.00 $10.00 $30.00
1360
Adjust manholes and inlets;
complete as specifiec Each 5.00 5.00 $470.00
1370
Turf restoration; complete as
specified
Square
Yards 250.00 194.52 -55.48 $18.00 ($998.64)
1380
Cold weather covering
(concrete pavement) - single
visquine; complete as
specified
Square
Yards 150.00 0.00 -150.00 $1.50 ($225.00)
1382
Cold weather covering
(concrete pavement) - double
visquine; complete as
specified
Square
Yards 150.00 0.00 -150.00 $3.00 ($450.00)
Page 2 of 7
DocuSign Envelope ID: 0EE7B08C-9A4F-4DA0-9529-8996278D3814
CONTRACT 22-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
1384
Cold weather covering
(concrete pavement) - double
visquine with 6" hay;
complete as specified
Square
Yards 150.00 0.00 -150.00 $12.00 ($1,800.00)
1390
Up-charge for late season
cold weather concrete
pavement; complete as
specified
Cubic
Yards 35.00 0.00 -35.00 $15.00 ($525.00)
1440
30" curb and gutter; 7"; with
5" CABC and grading;
complete as specified
Linear
Feet 100.00 98.63 -1.37 $60.00 ($82.20)
1441
30" curb and gutter; plain; 7";
with 5" CABC and grading;
complete as specified
Linear
Feet 225.00 220.61 -4.39 $60.00 ($263.40)
1448
30" concrete curb and gutter
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
as specified
Linear
Feet 70.00 84.01 14.01 $70.00 $980.70
1460
Sidewalk curb; complete as
specified
Linear
Feet 25.00 26.56 1.56 $35.00 $54.60
1500
4" concrete sidewalk with 3"
CABC and grading; complete
as specified
Square
Feet 310.00 364.19 54.19 $10.50 $569.00
1506
4" concrete sidewalk with
false curb; 3" CABC; and
grading; complete as
specified
Square
Feet 300.00 67.90 -232.10 $15.00 ($3,481.50)
1510
6" concrete sidewalk/
driveway/ramp with 3" CABC
and grading; complete as
specified
Square
Feet 300.00 386.72 86.72 $10.50 $910.56
1516
6" concrete sidewalk/
driveway/ramp with false
curb; 3" CABC; and grading;
complete as specified
Square
Feet 90.00 0.00 -90.00 $16.00 ($1,440.00)
1526
6" concrete sidewalk with 3"
CABC and grading; London
Paver pattern; complete as
specified
Square
Feet 120.00 29.33 -90.67 $14.50 ($1,314.72)
1540
Curb ramp detectable
warning field (natural/non-
painted); complete as
specified
Square
Feet 12.00 0.00 -12.00 $45.00 ($540.00)
1550
No. 4 reinforcing rods -
deformed; epoxy-coated;
complete as specified
Linear
Feet 60.00 36.00 -24.00 $2.00 ($48.00)
1560
Drilled No. 4 sidewalk tie bars
- deformed; epoxy-coated;
complete as specified Each 35.00 37.00 2.00 $7.00 $14.00
Page 3 of 7
DocuSign Envelope ID: 0EE7B08C-9A4F-4DA0-9529-8996278D3814
CONTRACT 22-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
1580
Cold weather covering
(sidewalk) - single visquine;
complete as specified
Square
Feet 300.00 0.00 -300.00 $0.50 ($150.00)
1582
Cold weather covering
(sidewalk) - double visquine;
complete as specified
Square
Feet 300.00 0.00 -300.00 $1.00 ($300.00)
1584
Cold weather covering
(sidewalk) - double visquine
with 6" hay; complete as
specified
Square
Feet 300.00 0.00 -300.00 $2.00 ($600.00)
1590
Up-charge for late season
cold weather concrete
sidewalk; complete as
specified
Cubic
Yards 4.50 0.00 -4.50 $15.00 ($67.50)
1650
Locate existing property
monuments; complete as
specified Each 4.00 0.00 -4.00 $125.00 ($500.00)
1652
Replace existing property
monuments; complete as
specified Each 4.00 0.00 -4.00 $125.00 ($500.00)
1700
Sawing existing pavement;
complete as specified
Linear
Feet 630.00 671.66 41.66 $3.00 $124.98
1710
Sawing concrete pavement
full depth; complete as
specified
Linear
Feet 125.00 123.57 -1.43 $3.00 ($4.29)
1801
Base aggregate dense; 1-
1/4"; complete as specified Tons 310.00 304.00 -6.00 $15.00 ($90.00)
1802
Base aggregate dense; 3";
complete as specified Tons 520.00 456.00 -64.00 $15.00 ($960.00)
1900
Tack coat; complete as
specified Gallons 120.00 50.00 -70.00 $2.73 ($191.10)
1901
HMA Pavement LT; complete
as specified Tons 350.00 307.90 -42.10 $80.09 ($3,371.79)
1903
HMA cold weather paving;
complete as specified Tons 105.00 0.00 -105.00 $102.21 ($10,732.05)
1905
5" asphaltic pavement MT
with 10" CABC and grading;
complete as specified
Square
Yards 315.00 306.25 -8.75 $71.77 ($627.99)
1916
4" asphaltic surface LT with
6" CABC and grading;
complete as specified
Square
Yards 7.50 22.75 15.25 $137.87 $2,102.52
1918
Asphaltic cold weather
paving; complete as specified
Square
Yards 95.00 0.00 -95.00 $17.57 ($1,669.16)
1960
Prepare foundation for
asphaltic paving; complete as
specified
Lump
Sum 1.00 1.00 $6,666.00
1974
Pavement markings; epoxy;
4" (white); complete as
specified
Linear
Feet 1,100.00 1,211.27 111.27 $5.50 $611.99
Page 4 of 7
DocuSign Envelope ID: 0EE7B08C-9A4F-4DA0-9529-8996278D3814
CONTRACT 22-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
1979
Pavement markings; arrow
epoxy; Type 1 (white);
complete as specified Each 1.00 1.00 $250.00
1980
Pavement markings; arrow
epoxy; Type 2 (white);
complete as specified Each 4.00 4.00 $275.00
1984
Pavement markings; symbol;
epoxy; 4" (white); complete
as specified Each 2.00 2.00 $250.00
1985
Temporary pavement
marking; paint; 4" (white);
complete as specified
Linear
Feet 275.00 0.00 -275.00 $15.00 ($4,125.00)
2001
Furnish and install 8" storm
sewer; complete as specified
Linear
Feet 35.00 34.00 -1.00 $83.30 ($83.30)
2002
Furnish and install 10" storm
sewer; complete as specified
Linear
Feet 90.00 83.00 -7.00 $112.00 ($784.00)
2006
Furnish and install 15" storm
sewer; complete as specified
Linear
Feet 110.00 116.10 6.10 $155.70 $949.77
2201
Furnish and install standard
storm sewer manhole (4'
diameter); complete as
specified
Vertical
Feet 9.00 9.26 0.26 $442.00 $114.92
2235
Furnish and install Type 1
inlet (with 18" sump);
complete as specified Each 3.00 3.00 $2,717.00
2508
Furnish; install; maintain; and
remove Type D modified inlet
protection; complete as
specified Each 12.00 6.00 -6.00 $150.00 ($900.00)
2510
Sediment removal - Type D
modified inlet protection;
complete as specified Each 12.00 0.00 -12.00 $40.00 ($480.00)
2512
Furnish; install; maintain; and
remove stone tracking pad;
complete as specified Each 2.00 1.00 -1.00 $0.01 ($0.01)
2516
Furnish; install; maintain; and
remove stone bag; complete
as specified Each 8.00 0.00 -8.00 $25.00 ($200.00)
2522
Furnish; install; maintain; and
remove 12" diameter
sediment logs; complete as
specified Each 4.00 3.00 -1.00 $150.00 ($150.00)
2800
Abandon 8" - 12" storm
sewer; complete as specified
Linear
Feet 70.00 64.00 -6.00 $10.00 ($60.00)
2810
Abandon storm sewer
manholes and inlets;
complete as specified Each 1.00 1.00 $400.00
2812
Remove storm sewer
manholes and inlets;
complete as specified Each 1.00 0.00 -1.00 $400.00 ($400.00)
Page 5 of 7
DocuSign Envelope ID: 0EE7B08C-9A4F-4DA0-9529-8996278D3814
CONTRACT 22-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
2850
Connect to existing storm
sewer main; complete as
specified Each 1.00 1.00 $300.00
2856
Connect to existing storm
sewer manhole; complete as
specified Each 1.00 1.00 $425.00
2914
Storm sewer utility line
opening (ULO); complete as
specified Each 1.00 0.00 -1.00 $1,250.00 ($1,250.00)
2950
Excavation special (storm);
complete as specified Tons 25.00 0.00 -25.00 $23.91 ($597.75)
5025
Adjust pull box; complete as
specified Each 1.00 1.00 $5.00
5027
Remove concrete base;
complete as specified Each 1.00 0.00 -1.00 $500.00 ($500.00)
5120
Furnish and install 2"
Schedue 40 PVC; complete
as specified
Linear
Feet 70.00 66.00 -4.00 $15.00 ($60.00)
5180
Connect to existing pull box;
complete as specified Each 1.00 1.00 $250.00
5250
Furnish and install 8 gauge
red-coated wire; complete as
specified
Linear
Feet 100.00 96.00 -4.00 $2.50 ($10.00)
5251
Furnish and install 8 gauge
black-coated wire; complete
as specified
Linear
Feet 100.00 96.00 -4.00 $2.50 ($10.00)
5262
Furnish and install 10 gauge
green-coated wire; complete
as specified
Linear
Feet 100.00 96.00 -4.00 $1.20 ($4.80)
5270
Furnish and install 12 gauge
red-coated wire; complete as
specified
Linear
Feet 60.00 60.00 $1.00
5271
Furnish and install 12 gauge
black-coated wire; complete
as specified
Linear
Feet 60.00 60.00 $1.00
5272
Furnish and install 12 gauge
green-coated wire; complete
as specified
Linear
Feet 30.00 30.00 $1.00
5380
Furnish and install fuse
holder; complete as specified Each 4.00 4.00 $75.00
5392
Furnish and install 5A fuse;
complete as specified Each 4.00 4.00 $20.00
5402
Install CITY-supplied double
head fixture; complete as
specified Each 1.00 1.00 $1,750.00
5425
Install CITY-supplied 20' 5"
square pole; complete as
specified Each 1.00 1.00 $1,500.00
Page 6 of 7
DocuSign Envelope ID: 0EE7B08C-9A4F-4DA0-9529-8996278D3814
CONTRACT 22-08 CHANGE ORDER #1 (FINAL)
ITEM
NUMBER DESCRIPTION UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
5502
Furnish and install Type 2
special base; complete as
specified Each 1.00 1.00 $2,750.00
WORK UNIT A (BID ITEMS 1050 - 5502) - SUBTOTAL: $11,081.48 ($53,140.90)
NET DECREASE TO A: ($42,059.42)
NET DECREASE TO WORK UNIT A:($42,059.42)
NET DECREASE TO CONTRACT:($42,059.42)
Page 7 of 7