HomeMy WebLinkAbout20-02_CO__1_(FINAL)_12-1-22TO: VINTON CONSTRUCTION CO CHANGE ORDER #1 (FINAL) P.O. BOX 137 TWO RIVERS, WI 54241 Your present contract with the City of Oshkosh, Contract No. 20-02, awarded November 10, 2020, is hereby amended and changed as follows: $22,246.30 $25,166.80 $47,413.10 SECTION I TOTALS BID TOTAL $2,587,589.47 $2,587,589.47 CO #1 $47,413.10 $47,413.10 CONTRACT TOTAL $2,635,002.57 $2,635,002.57 CITY OF OSHKOSH BY: I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. Approved as to form: City Attorney DATE: DECEMBER 1, 2022 ______________________________ Comptroller ______________________________ Contractor ______________________________ Approved and accepted: ______________________________ City Manager City Clerk ______________________________ NET INCREASE TO SECTION I: NET INCREASE TO ADDITIONAL WORK: NET INCREASE TO CONTRACT: DocuSign Envelope ID: 273A1925-58EA-43B5-A67F-2F060822E001 CONTRACT 20-02 CHANGE ORDER #1 (FINAL) 20-02 ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE A-1010 Clearing; complete as specified Stations 14.00 14.00 $500.00 A-1020 Grubbing; complete as specified Stations 14.00 14.00 $500.00 A-1050 Mobilization; complete as specified Lump Sum 1.00 1.00 $103,475.00 A-1051 Mobilization (extra); complete as specified Lump Sum 1.00 0.00 -1.00 $1.00 ($1.00) A-1110 Removing curb and gutter; complete as specified Linear Feet 166.00 166.00 $3.00 A-1125 Pulverize pavement; complete as specified Square Yards 5,500.00 5,765.00 265.00 $4.70 $1,245.50 A-1200 Unclassified excavation; complete as specified Cubic Yards 17,000.00 28,654.00 11654.00 $11.25 $131,107.50 A-1210 Borrow excavation; complete as specified Cubic Yards 7,900.00 0.00 -7,900.00 $0.01 ($79.00) A-1324 9" concrete pavement doweled; base in place and grading; complete as specified Square Yards 17,700.00 17,616.00 -84.00 $37.52 ($3,151.68) A-1325 9" concrete pavement doweled; HES; with 6" CABC and grading; complete as specified Square Yards 10,875.00 10,627.00 -248.00 $42.00 ($10,416.00) A-1360 Adjust manholes and inlets; complete as specified Each 62.00 64.00 2.00 $350.00 $700.00 A-1410 12" radius curb with 6" CABC and grading; complete as specified Linear Feet 240.00 306.00 66.00 $9.00 $594.00 A-1520 8" concrete sidewalk/ driveway/ramp with 3" CABC and grading; complete as specified Square Feet 13,825.00 12,924.00 -901.00 $5.15 ($4,640.15) A-1700 Sawing existing pavement; complete as specified Linear Feet 60.00 95.00 35.00 $3.00 $105.00 A-1800 Base aggregate dense; 3/4"; complete as specified Tons 550.00 666.29 116.29 $24.70 $2,872.36 A-1801 Base aggregate dense; 1- 1/4"; complete as specified Tons 2,025.00 2,089.11 64.11 $6.00 $384.66 A-1810 Breaker run; complete as specified Tons 8,600.00 0.00 -8,600.00 $9.28 ($79,808.00) A-1900 Tack coat; complete as specified Gallons 440.00 200.00 -240.00 $3.00 ($720.00) A-1905 5" asphaltic pavement MT with 10" CABC and grading; complete as specified Square Yards 6,225.00 6,471.00 246.00 $24.92 $6,130.32 A-1974 Pavement markings; epoxy; 4" (white); complete as specified Linear Feet 4,075.00 4,051.00 -24.00 $0.79 ($18.96) Page 2 of 8 DocuSign Envelope ID: 273A1925-58EA-43B5-A67F-2F060822E001 CONTRACT 20-02 CHANGE ORDER #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE A-1975 Pavement markings; epoxy; 4" (yellow); complete as specified Linear Feet 3,850.00 3,840.00 -10.00 $0.79 ($7.90) A-1976 Pavement markings; epoxy; 8" (white); complete as specified Linear Feet 100.00 100.00 $3.00 A-1978 Pavement markings; stop-line epoxy; 18" (white); complete as specified Linear Feet 36.00 36.00 $16.00 A-1979 Pavement markings; arrow epoxy; Type 1 (white); complete as specified Each 2.00 2.00 $275.00 A-1999 EDA project sign; complete as specified Lump Sum 1.00 1.00 $2,079.00 A-2004 Furnish and install 12" RCP Class III storm sewer; complete as specified Linear Feet 1,393.00 1,368.00 -25.00 $64.80 ($1,620.00) A-2007 Furnish and install 15" RCP Class III storm sewer; complete as specified Linear Feet 132.00 130.00 -2.00 $59.00 ($118.00) A-2013 Furnish and install 21" RCP Class III storm sewer; complete as specified Linear Feet 15.00 17.00 2.00 $67.80 $135.60 A-2016 Furnish and install 24" RCP Class III storm sewer; complete as specified Linear Feet 649.00 634.00 -15.00 $86.90 ($1,303.50) A-2022 Furnish and install 30" RCP Class III storm sewer; complete as specified Linear Feet 661.00 675.00 14.00 $78.50 $1,099.00 A-2023 Furnish and install 30" RCP Class V storm sewer; complete as specified Linear Feet 100.00 104.00 4.00 $101.50 $406.00 A-2047 Furnish and install 19" x 30" HERCP Class III storm sewer; complete as specified Linear Feet 114.00 112.00 -2.00 $90.60 ($181.20) A-2051 Furnish and install 29" x 45" HERCP Class III storm sewer; complete as specified Linear Feet 136.00 144.00 8.00 $104.00 $832.00 A-2053 Furnish and install 34" x 53" HERCP Class III storm sewer; complete as specified Linear Feet 146.00 144.00 -2.00 $128.00 ($256.00) A-2140 Furnish and install 12" RCP Class III apron endwall with joint ties; complete as specified Each 2.00 2.00 $1,256.00 A-2141 Furnish and install 15" RCP Class III apron endwall with joint ties; complete as specified Each 2.00 2.00 $828.00 Page 3 of 8 DocuSign Envelope ID: 273A1925-58EA-43B5-A67F-2F060822E001 CONTRACT 20-02 CHANGE ORDER #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE A-2142 Furnish and install 18" RCP Class III apron endwall with joint ties; complete as specified Each 2.00 0.00 -2.00 $881.00 ($1,762.00) A-2146 Furnish and install 30" RCP Class III apron endwall with joint ties; complete as specified Each 2.00 2.00 $1,597.00 A-2155 Furnish and install 19" x 30" RCP Class III apron endwall with joint ties; complete as specified Each 4.00 4.00 $1,698.00 A-2157 Furnish and install 29" x 45" RCP Class III apron endwall with joint ties; complete as specified Each 4.00 4.00 $1,780.00 A-2158 Furnish and install 34" x 53" RCP Class III apron endwall with joint ties; complete as specified Each 4.00 4.00 $2,552.00 A-2201 Furnish and install standard storm sewer manhole (4' diameter); complete as specified Vertical Feet 37.42 37.05 -0.37 $264.00 ($97.68) A-2202 Furnish and install standard storm sewer manhole (5' diameter); complete as specified Vertical Feet 37.32 37.35 0.03 $449.00 $13.47 A-2204 Furnish and install standard storm sewer manhole (7' diameter); complete as specified Vertical Feet 3.65 4.00 0.35 $972.00 $340.20 A-2213 Furnish and install standard storm sewer inlet manhole (4' diameter); complete as specified Vertical Feet 8.36 8.33 -0.03 $264.00 ($7.92) A-2214 Furnish and install standard storm sewer inlet manhole (5' diameter); complete as specified Vertical Feet 3.26 3.04 -0.22 $565.00 ($124.30) A-2215 Furnish and install standard storm sewer inlet manhole (6' diameter); complete as specified Vertical Feet 5.76 4.50 -1.26 $652.00 ($821.52) A-2226 Furnish and install storm sewer outlet structure; complete as specified Each 1.00 1.00 $5,300.00 A-2237 Furnish and install Type 3 inlet (with 18" sump); complete as specified Each 16.00 16.00 $1,380.00 A-2246 Reconstruct 4' diameter storm sewer manhole; complete as specified Vertical Feet 8.00 3.00 -5.00 $485.00 ($2,425.00) Page 4 of 8 DocuSign Envelope ID: 273A1925-58EA-43B5-A67F-2F060822E001 CONTRACT 20-02 CHANGE ORDER #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE A-2247 Reconstruct 5' diameter storm sewer manhole; complete as specified Vertical Feet 12.00 7.00 -5.00 $575.00 ($2,875.00) A-2254 Reconstruct 6' x 6' storm sewer box manhole; complete as specified Vertical Feet 6.00 4.00 -2.00 $950.00 ($1,900.00) A-2506 Furnish; install; maintain; and remove Type D inlet protection; complete as specified Each 50.00 50.00 $75.00 B-2508 Furnish; install; maintain; and remove Type D modified inlet protection; complete as specified Each 4.00 4.00 $75.00 B-2510 Sediment removal - Type D modified inlet protection; complete as specified Each 4.00 4.00 $5.00 A-2512 Furnish; install; maintain; and remove stone tracking pad; complete as specified Each 2.00 0.00 -2.00 $1,000.00 ($2,000.00) A-2514 Furnish; install; maintain; and remove silt fence; complete as specified Linear Feet 4,450.00 4,730.00 280.00 $2.75 $770.00 B-2516 Furnish; install; maintain; and remove stone bag; complete as specified Each 5.00 5.00 $15.00 B-2518 Furnish; install; maintain; and remove 12" diameter sediment logs; complete as specified Linear Feet 24.00 24.00 $10.00 A-2522 Furnish; install; maintain; and remove ditch check; complete as specified Each 35.00 35.00 $75.00 B-2524 Furnish; install; maintain; and remove dewatering tank system; complete as specified Each 1.00 1.00 $1,500.00 A-2602 Install salvaged topsoil 6" depth; complete as specified Square Yards 34,625.00 41,542.00 6917.00 $1.00 $6,917.00 A-2610 Furnish and install native seeding; complete as specified Square Yards 34,625.00 41,542.00 6917.00 $1.75 $12,104.75 A-2630 Furnish and install Class I; Type A erosion control mat; complete as specified Square Yards 18,600.00 19,924.00 1324.00 $1.50 $1,986.00 A-2648 Furnish and install medium rip-rap with filter fabric; complete as specified Square Yards 14.00 32.00 18.00 $58.00 $1,044.00 A-2802 Abandon 15" and larger storm sewer; complete as specified Linear Feet 498.00 498.00 $17.00 A-2804 Remove 30" and smaller storm sewer; complete as specified Linear Feet 426.00 435.00 9.00 $12.50 $112.50 Page 5 of 8 DocuSign Envelope ID: 273A1925-58EA-43B5-A67F-2F060822E001 CONTRACT 20-02 CHANGE ORDER #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE A-2810 Abandon storm sewer manholes and inlets; complete as specified Each 1.00 1.00 $550.00 A-2812 Remove storm sewer manholes and inlets; complete as specified Each 6.00 6.00 $400.00 A-2850 Connect to existing storm sewer main; complete as specified Each 1.00 1.00 $850.00 A-2902 Strip and stockpile topsoil; complete as specified Square Yards 38,750.00 37,874.00 -876.00 $0.90 ($788.40) B-3006 Furnish and install 15" sanitary sewer (relay); complete as specified Linear Feet 350.00 236.00 -114.00 $105.00 ($11,970.00) B-3100 Furnish and install standard sanitary sewer manhole (4' diameter); complete as specified Vertical Feet 38.35 37.90 -0.45 $270.00 ($121.50) B-3114 Furnish and install external sanitary sewer manhole chimney seal; complete as specified Each 2.00 2.00 $370.00 B-3116 Furnish and install external sanitary sewer manhole chimney seal extension; complete as specified Each 1.00 1.00 $280.00 A-3122 Reconstruct sanitary sewer manhole (4' diameter); complete as specified Vertical Feet 14.00 11.57 -2.43 $495.00 ($1,202.85) A-3136 Rebuild sanitary sewer manhole (4' diameter); complete as specified Vertical Feet 10.00 0.00 -10.00 $400.00 ($4,000.00) B-3306 Furnish and install connection to existing 15" sanitary sewer mains; complete as specified Each 2.00 2.00 $964.00 B-3340 Furnish and install connection to existing 30" sanitary sewer steel casing; complete as specified Each 2.00 1.00 -1.00 $2,000.00 ($2,000.00) B-3414 Furnish and install 30" sanitary sewer open cut casing pipes; complete as specified Linear Feet 220.00 200.00 -20.00 $489.00 ($9,780.00) B-3700 Closed circuit televising; complete as specified Linear Feet 350.00 0.00 -350.00 $4.00 ($1,400.00) B-3808 Abandon 15" sanitary sewer; complete as specified Linear Feet 55.00 55.00 $15.00 B-3890 Sanitary sewer utility line opening (ULO); complete as specified Each 1.00 1.00 $1,500.00 B-4024 Furnish and install new 10" ductile iron water main with polywrap; complete as specified Linear Feet 10.00 10.00 $176.00 Page 6 of 8 DocuSign Envelope ID: 273A1925-58EA-43B5-A67F-2F060822E001 CONTRACT 20-02 CHANGE ORDER #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE B-4025 Furnish and install new 10" ductile iron water main with polywrap and TR Flex restrained joints; complete as specified Linear Feet 15.00 9.00 -6.00 $176.00 ($1,056.00) B-4062 Furnish and install connections to existing 10" water main; complete as specified Each 2.00 2.00 $1,773.00 B-4088 Furnish and install connections to existing 24" water main steel casing; complete as specified Each 1.00 1.00 $1,000.00 B-4238 Furnish and install 10" 45 degree water main bend; complete as specified Each 2.00 2.00 $910.00 B-4730 Furnish and install 24" water main casing pipe; complete as specified Linear Feet 10.00 10.00 $263.00 $168,899.86 ($146,653.56) $22,246.30 ADDITIONAL WORK REQUIRED: CO #1 ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1-1442 FO #1 Additional 20 feet of 30" curb and gutter with 6" CABC and grading by proposed railroad spur; complete as specified Linear Feet 0.00 20.00 20.00 $48.00 $960.00 1-2144 FO #2 Change from 18" apron endwall with joint ties to 24" apron endwall with joint ties; complete as specified Lump Sum 0.00 1.00 1.00 $2,610.00 $2,610.00 1-2660 FO #3 Temporary seed for City of Oshkosh clay stockpile; disturbed area is 4160 square yards; clay material used as fill material for Clairville Road; complete as specified Lump Sum 0.00 1.00 1.00 $1,872.00 $1,872.00 1-10000 FO #4 Additional staking for Compass Way; complete as specified Lump Sum 0.00 1.00 1.00 $3,765.00 $3,765.00 SECTION 1 (BID ITEMS A-1010 - B-4730) SUBTOTAL: NET INCREASE TO SECTION 1: Page 7 of 8 DocuSign Envelope ID: 273A1925-58EA-43B5-A67F-2F060822E001 CONTRACT 20-02 CHANGE ORDER #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1-30000 FO #5 Additional casing work; labor; materials; equipment; proposed 30" casing on south side of tracks; 24" casing was existing; complete as specified Lump Sum 0.00 1.00 1.00 $15,959.80 $15,959.80 ADDITIONAL WORK CO #1 (BID ITEMS 1-1442 - 1-30000) - SUBTOTAL: $25,166.80 $0.00 NET INCREASE TO ADDITIONAL WORK: $25,166.80 $22,246.30 $25,166.80 $47,413.10NET INCREASE TO CONTRACT: NET INCREASE TO ADDITIONAL WORK: NET INCREASE TO SECTION 1: Page 8 of 8 DocuSign Envelope ID: 273A1925-58EA-43B5-A67F-2F060822E001