Mr. Ray Maurer
Parks Director
City of Oshkosh
215 Church Avenue
Oshkosh, Wisconsin 54903-1130
AECOM 2985 South Ridge Road, Suite B
Green Bay, WI 54304
aecom.com
February 21, 2023
Proposal for Environmental and Engineering Consulting Services related to the Demolition of the Quarry Park
Shelter located on Florida, Avenue in Oshkosh, WI
Dear Mr. Maurer,
AECOM Technical Services, Inc. (AECOM) has prepared this proposal to provide environmental and engineering
services related to the demolition of the existing park shelter and site improvements within Quarry Park in Oshkosh,
WI. Quarry Park is located on the site of a historic quarry which was subsequently backfilled with municipal waste
and construction debris. As a result of the historic filling, the area is prone to significant settlement and methane gas
has historically been encountered at the site which is generated during the decomposition of the fill materials. The
site is regulated as a closed landfill by the State of Wisconsin Department of Natural Resources (WDNR). Because of
the potential presence of solid waste and methane, all onsite work will need to be coordinated with the WDNR and will
require additional health and safety protocols are incorporated to protect workers during construction activities at the
site.
The City of Oshkosh previously constructed a Park Shelter at the site along with an asphalt parking area. The park
shelter is served by utilities including domestic water, sanitary sewer and natural gas. Electrical service is supplied by
an overhead feed from Florida Avenue. The Park Shelter building is not currently utilized by the City of Oshkosh, due
in part to the potential for accumulation of Methane within the structure. The asphalt parking area has become
unusable due to settlement of the fill soils at the site. The immediate surroundings of the park shelter including the
parking lot are depressed approximately 2-3 feet below surrounding grades and allow stormwater to form deep
puddles. The City of Oshkosh has evaluated need for the facilities at the site and has determined they can be
demolished, and the site will be regraded, filled to improve surface water drainage and topped off with topsoil and
vegetation will be established at the site to match the surrounding area.
The following letter presents the scope of services which AECOM proposes to complete as part of this project.
Task 1 – Special Provisions and Construction Documents
AECOM will work with the City of Oshkosh to develop bidding documents to solicit proposals from Contractors for the
implementation of the project. AECOM will develop drawings, technical specifications and guidance documents
related to the health and safety requirements for the implementation of the project. Design documents, previously
prepared by AECOM, related to the replacement of land fill gas (LFG) monitoring vault structures will be incorporated
into the bidding documents for the project. The design drawings which will be prepared by AECOM related to the
demolition of the park shelter and associated infrastructure include:
Cover Sheet
Existing Conditions Survey (survey basemap to be provided by the City of Oshkosh)
Demolition Sheet and Erosion Control Drawing
Proposed Grading and Site Restoration Drawing
AECOM will issue Draft drawings for City of Oshkosh review and will then issue final Issued for Bid drawings upon
receipt of one set of compiled review comments.
In addition to the drawings, AECOM will develop special provisions and a draft advertisement document defining the
scope of work for the project. The majority of the scope of work for the project will be implemented in accordance with
City of Oshkosh Standard Specifications. AECOM will develop a technical provision related to the demolition of the
DocuSign Envelope ID: C83706BE-4084-448C-9CF5-8CF24C535023
Quarry Park Shelter Demo Proposal.docx 2/4
structure and will include in the special provisions, requirements related to health and safety precautions which are
necessary to implement the work based on the historic use of the site as a landfill. The development of a project
specific health and safety plan will be the responsibility of the Contractor selected for the project. The Contractor will
remain responsible for the safe implementation of the work and the safety of their employees and the public.
Task 2 – WDNR Coordination
AECOM has held preliminary discussions with the WDNR related to the demolition of the Park Shelter and supporting
infrastructure. From those discussions, we understand the WDNR will not require a plan modification for the closed
landfill but will require notification regarding the scope and schedule of the work to be completed as well as a copy of
the final demolition report. AECOM will provide the bidding documents to the WDNR for notification and keep them
informed on the progress of the project.
Task 3 – Construction Documentation
During construction activities at the site, AECOM will perform part-time oversight and documentation of the activities
being performed. AECOM anticipates the work to be completed in approximately 3 weeks. AECOM will periodically
visit the site during construction, document the activities being completed and provide updates to the City of Oshkosh
and the WDNR. Observations will be documented in a site visit report including photographs. AECOM assumes that
the City of Oshkosh will perform a final topographic survey after the completion of the construction. A demolition
summary report will be prepared and submitted to the WDNR.
AECOM has not budgeted for full time oversight as a means to reduce cost. AECOM cannot accept responsibility for
elements of construction that are completed while we are not on-site and are not observable during our site visits.
Assumptions
1. The City will compile the bidding documents, advertise for bids, and place the documents on Quest CDN.
2. AECOM will prepare special provisions as supplemental documents to the current version of City Standard
Specifications
3. The City will set grade stakes for construction and complete a final topographic survey and provide a competed
as-built drawing to AECOM for inclusion in the documentation report.
4. The City will allow access/use of the clay and topsoil piles at the Southwest Industrial Park for Contractor to use
for the project.
5. If the City requests additional services beyond those stated in this proposal, the City and AECOM agree to
renegotiate the scope and fee.
6. The City will pay all permit fees if required.
7. This project will not require Parks Board, Site Plan or Plan Commission review.
8. The City has sufficient funds to complete the project as bid based on an AECOM opinion of probable cost dated
June 2, 2022 ($118,575)
Estimated Fees
The following summarizes the proposed tasks and estimated fees:
Task Fee
Task 1 – Special Provisions and Construction Documents $6,500
Task 2 – WDNR Coordination $4,500
Task 3 – Construction Documentation and Reporting $12,000
TOTAL PROJECT FEES $23,000
DocuSign Envelope ID: C83706BE-4084-448C-9CF5-8CF24C535023
Quarry Park Shelter Demo Proposal.docx 3/4
Terms and Conditions
If services to be provided under this proposal require the agents, employees, or contractors of AECOM to enter onto
the Project site, Client shall provide right-of-access to the site to AECOM, its employees, agents, and contractors, to
conduct the planned field observations or services. The services described in this proposal will be provided on a time-
and-material basis. AECOM will not exceed the above estimate without your authorization and approval. The
services provided will be performed in accordance with the approved Fee schedule and with the conditions of the
2009 City of Oshkosh Negotiated General Conditions of Service, which are expressly incorporated into, and are an
integral part of, our contract for professional services.
To initiate this work, please sign and return the attached Authorization to the AECOM Oshkosh, Wisconsin office. Our
understanding is that the City of Oshkosh will also issue a Purchase Order for all approved tasks. Please reference
the AECOM proposal in the Purchase Order that is forwarded to the AECOM Oshkosh Office. We are looking forward
to working with you and providing assistance with this project.
If you have any questions or need to clarify a point, please call Jeremy Thomas at 847-702-6639.
Yours sincerely,
AECOM Technical Services, Inc.
Jeremy Thomas, P.E.
Associate
Dave Lowry, P.E. (IL, MO)
Associate Vice President
enclosure: Authorization
DocuSign Envelope ID: C83706BE-4084-448C-9CF5-8CF24C535023
Quarry Park Shelter Demo Proposal.docx 4/4
Authorization
February 21, 2023
I hereby certify that the necessary provisions have been made to pay the liability, which will accrue under this
agreement.
I hereby authorize AECOM to proceed with the scope of work for Environmental and Engineering Consulting Services
related to the Quarry Park Shelter Demolition as described in AECOM’s proposal dated February 21, 2023 with a
budget authorization of $23,000 under the general terms and conditions specified in the proposal.
Signature Date
Mark A Rohloff
Print Name
City Manager
Title/Organization
Signature Date
Jessi L. Balcom
Print Name
City Clerk
Title/Organization
Signature Date
Lynn A. Lorenson
Print Name
City Attorney
Title/Organization
Signature Date
Russ Van Gompel
Print Name
Director of Finance
Title/Organization