The work under this
Contract consists of the
public construction of
concrete pavement and
sidewalk and miscellaneous
asphalt work on Arthur
Avenue, Tyler Avenue,
Coolidge Avenue, and
Bauman Street, along with
storm sewer, sanitary sewer,
water main relay, and
electrical work. The
schedule is subject to
change due to weather
conditions, scheduling changes, and private utility
conflicts. City garbage/
recycling will remain on
your normal day. Please
have your carts to the curb
by 7:00 am. Please note
there will be traffic
restrictions throughout the
duration of this project.
Upcoming construction work in your
area, September 5th–September 8th, 2023.
Project Milestones
Sidewalk Paving Operations (Martell Construction Inc., 920-468-8071)
Through September 8th: Contractor is anticipated to continue sidewalk paving
on Tyler Avenue from Josslyn Street to Bauman Street. Upon completion of
sidewalk paving on Tyler Avenue, sidewalk paving on Bauman Street from
Tyler Avenue to Van Buren Avenue will begin.
Pavement Removal & Excavation (Vinton Construction Company, 920-973-8936)
Week of September 5th: Contractor is anticipated to complete pavement
removal and excavation operations on Arthur Avenue.
*Notice to Property Owners on Tyler Avenue: During the summer, there has been
property owner parking in the Roosevelt Elementary School parking lot. With school
beginning September 1st, if this continues to occur, your vehicles will be ticketed
and towed at the owner’s expense. Additionally, absolutely no thru traffic in the
paved playground east of Roosevelt Elementary School will be allowed under any
circumstance.
*Notice to All Property Owners: There will be no construction work on Monday,
September 4th, in observation of Labor Day.