Loading...
HomeMy WebLinkAbout22-11 CO #1 (Final)_8-22-23TO: WOOD SEWER & EXCAVATING E9238 COUNTY ROAD X NEW LONDON, WI 54961 Your present contract with the City of Oshkosh, Contract No. 22-11, awarded July 26, 2022, is hereby amended and changed as follows: ($51,396.11) $6,527.00 ($44,869.11) $533,527.50 $533,527.50 ($44,869.11)($44,869.11) $488,658.39 $488,658.39 CITY OF OSHKOSH BY: I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. Approved as to form: City Attorney BID TOTAL CO #1 CONTRACT TOTAL CHANGE ORDER #1 FINAL DATE: AUGUST 22, 2023 NET DECREASE TO SECTION I: NET INCREASE TO ADDITIONAL WORK: NET DECREASE TO CONTRACT ______________________________ Comptroller ______________________________ Contractor ______________________________ Approved and accepted: ______________________________ City Manager City Clerk ______________________________ DocuSign Envelope ID: 7320847E-2306-49A9-BCD0-D49F348154ED CONTRACT 22-11 CO #1 (FINAL) 22-11 ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1050 Mobilization; complete as specified Lump Sum 1.00 1.00 $24,500.00 1120 Removing concrete and asphalt sidewalk and driveway; complete as specified Square Feet 750.00 681.30 -68.70 $1.75 ($120.23) 1308 7" concrete pavement removal and replacement; including sawing; pavement ties; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete as specified Square Yards 800.00 493.70 -306.30 $88.00 ($26,954.40) 1309 7" concrete pavement HES removal and replacement; including sawing; pavement ties; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete as specified Square Yards 50.00 103.10 53.10 $108.00 $5,734.80 1318 8" concrete pavement removal and replacement; including sawing; pavement ties; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete as specified Square Yards 50.00 0.00 -50.00 $99.00 ($4,950.00) 1319 8" concrete pavement HES removal and replacement; including sawing; pavement ties; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete as specified Square Yards 450.00 402.30 -47.70 $115.00 ($5,485.50) 1370 Turf restoration; complete as specified Square Yards 100.00 108.20 8.20 $18.00 $147.60 1373 Replace and set CITY- supplied manhole castings and frames; complete as specified Each 88.00 92.00 4.00 $410.00 $1,640.00 1374 Furnish and install concrete adjustment rings; complete as specified Vertical Feet 45.00 33.22 -11.78 $360.00 ($4,240.80) 1375 Furnish and install rubber adjustment rings; complete as specified Vertical Feet 5.00 4.02 -0.98 $890.00 ($872.20) Page 2 of 6 DocuSign Envelope ID: 7320847E-2306-49A9-BCD0-D49F348154ED CONTRACT 22-11 CO #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1376 Tuck point manholes; complete as specified Each 15.00 16.00 1.00 $189.00 $189.00 1380 Cold weather covering (concrete pavement) - single visquine; complete as specified Square Yards 150.00 123.60 -26.40 $1.00 ($26.40) 1382 Cold weather covering (concrete pavement) - double visquine; complete as specified Square Yards 50.00 42.90 -7.10 $2.00 ($14.20) 1390 Up-charge for late season cold weather concrete pavement; complete as specified Cubic Yards 200.00 53.40 -146.60 $12.00 ($1,759.20) 1500 4" concrete sidewalk with 3" CABC and grading; complete as specified Square Feet 250.00 186.30 -63.70 $12.50 ($796.25) 1510 6" concrete sidewalk/ driveway/ramp with 3" CABC and grading; complete as specified Square Feet 500.00 495.00 -5.00 $13.50 ($67.50) 1540 Curb ramp detectable warning field (natural/non- painted); complete as specified Square Feet 16.00 16.00 $50.00 1550 No. 4 reinforcing rods - deformed; epoxy-coated; complete as specified Linear Feet 30.00 0.00 -30.00 $5.00 ($150.00) 1560 Drilled No. 4 sidewalk tie bars - deformed; epoxy-coated; complete as specified Each 10.00 36.00 26.00 $15.00 $390.00 1904 Remove and replace HMA pavement; including sawing; fine grading; turf restoration; and traffic control; complete as specified Square Yards 275.00 288.10 13.10 $80.00 $1,048.00 1918 Asphaltic cold weather paving; complete as specified Square Yards 100.00 126.70 26.70 $10.00 $267.00 1930 Temporary cold mix asphaltic patch; complete as specified Square Yards 200.00 42.60 -157.40 $0.01 ($1.57) 3000 Furnish and install 8" sanitary sewer (relay); complete as specified Linear Feet 25.00 33.00 8.00 $90.00 $720.00 3002 Furnish and install 10" sanitary sewer (relay); complete as specified Linear Feet 10.00 5.00 -5.00 $135.00 ($675.00) Page 3 of 6 DocuSign Envelope ID: 7320847E-2306-49A9-BCD0-D49F348154ED CONTRACT 22-11 CO #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 3008 Furnish and install 18" sanitary sewer (relay); complete as specified Linear Feet 10.00 4.00 -6.00 $188.00 ($1,128.00) 3010 Furnish and install 21" sanitary sewer (relay); complete as specified Linear Feet 25.00 11.00 -14.00 $212.00 ($2,968.00) 3012 Furnish and install 24" sanitary sewer (relay); complete as specified Linear Feet 10.00 5.00 -5.00 $252.00 ($1,260.00) 3100 Furnish and install standard sanitary sewer manhole (4' diameter); complete as specified Vertical Feet 6.00 5.83 -0.17 $1,050.00 ($178.50) 3101 Furnish and install standard sanitary sewer manhole (4' diameter) with slurry backfill; complete as specified Vertical Feet 18.00 18.40 0.40 $1,500.00 $600.00 3103 Furnish and install standard sanitary sewer manhole (5' diameter) with slurry backfill; complete as specified Vertical Feet 1.00 0.00 -1.00 $1,900.00 ($1,900.00) 3105 Furnish and install standard sanitary sewer manhole (6' diameter) with slurry backfill; complete as specified Vertical Feet 8.50 8.00 -0.50 $2,600.00 ($1,300.00) 3114 Furnish and install external sanitary sewer manhole chimney seal; complete as specified Each 85.00 83.00 -2.00 $780.00 ($1,560.00) 3116 Furnish and install external sanitary sewer manhole chimney seal extension; complete as specified Each 13.00 6.00 -7.00 $420.00 ($2,940.00) 3118 Furnish and install internal sanitary sewer manhole chimney seal; complete as specified Each 5.00 2.00 -3.00 $510.00 ($1,530.00) 3120 Furnish and install internal sanitary sewer manhole chimney seal extension; complete as specified Each 1.00 1.00 $460.00 3123 Reconstruct sanitary sewer manhole (4' diameter) with slurry backfill; complete as specified Vertical Feet 105.00 103.62 -1.38 $900.00 ($1,242.00) 3160 Pour and reshape manhole bench; complete as specified Each 6.00 7.00 1.00 $1,113.00 $1,113.00 Page 4 of 6 DocuSign Envelope ID: 7320847E-2306-49A9-BCD0-D49F348154ED CONTRACT 22-11 CO #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 3210 Furnish and install 8" x 6" sanitary sewer factory wyes or tees; complete as specified Each 1.00 1.00 $500.00 3222 Furnish and install 6" sanitary sewer "Insert-A-Tee" or "Kor- N-Tee"; complete as specified Each 1.00 1.00 $600.00 3234 Furnish and install 4"/6" sanitary sewer lateral (relay); complete as specified Linear Feet 20.00 10.00 -10.00 $75.00 ($750.00) 3235 Furnish and install 4"/6" sanitary sewer riser (relay); complete as specified Linear Feet 5.00 0.00 -5.00 $93.00 ($465.00) 3236 Furnish and install sanitary sewer lateral marker balls; complete as specified Each 3.00 2.00 -1.00 $55.00 ($55.00) 3300 Furnish and install connection to existing 8" sanitary sewer mains; complete as specified Each 2.00 4.00 2.00 $1,000.00 $2,000.00 3302 Furnish and install connection to existing 10" sanitary sewer mains; complete as specified Each 1.00 1.00 $1,120.00 3308 Furnish and install connection to existing 18" sanitary sewer mains; complete as specified Each 1.00 1.00 $1,190.00 3310 Furnish and install connection to existing 21" sanitary sewer mains; complete as specified Each 3.00 3.00 $1,320.00 3312 Furnish and install connection to existing 24" sanitary sewer mains; complete as specified Each 1.00 1.00 $1,650.00 3892 Excavation special (sanitary); complete as specified Tons 10.00 0.00 -10.00 $50.00 ($500.00) 3974 Furnish sanitary sewer manhole grouting setup; complete as specified Each 7.00 7.00 $1,600.00 3975 Furnish and install sanitary sewer manhole grouting; complete as specified Gallons 50.00 155.26 105.26 $10.50 $1,105.24 3976 Furnish sanitary sewer manhole cementitious liner setup; complete as specified Each 2.00 1.00 -1.00 $1,600.00 ($1,600.00) Page 5 of 6 DocuSign Envelope ID: 7320847E-2306-49A9-BCD0-D49F348154ED CONTRACT 22-11 CO #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 3977 Furnish and install sanitary sewer structural cementitious liner-PERMACAST by AP/M PERMAFORM; complete as specified Vertical Feet 10.00 5.90 -4.10 $210.00 ($861.00) SECTION I - (BID ITEMS 1050-3977) - SUBTOTAL $14,954.64 ($66,350.75) ($51,396.11) ADDITIONAL WORK REQUIRED: CO #1 ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1-30000 W. Waukau spot repair (8' sanitary sewer); complete as specified Lump Sum 0.00 1.00 1.00 $6,527.00 $6,527.00 ADDITIONAL WORK REQUIRED: CO #1 (BID ITEM 1-30000) SUBTOTAL:$6,527.00 $0.00 $6,527.00 NET DECREASE TO SECTION I ($51,396.11) NET INCREASE TO ADDITIONAL WORK CO #1: $6,527.00 NET DECREASE TO CONTRACT:($44,869.11) NET INCREASE: NET DECREASE TO SECTION I: Page 6 of 6 DocuSign Envelope ID: 7320847E-2306-49A9-BCD0-D49F348154ED