HomeMy WebLinkAbout23-17 Addendum No. 1City o� Oshkosh Addendum No.1 City Contract 23-17 EAST PARKWAY AVENUE WATERSHED DETENTION BASIN - CONSTRUCTION TO ALL CONTRACTORS: Based on questions received related to the excavation support, which will be necessary for the construction of the retaining wall on the east and west sides of the detention basin, the design of the wall is being re-evaluated to raise the bottom elevation of the footing along the majority of the wall. No modification is anticipated at the location of the inlet sewer pipe where the bottom of footing will remain at Elevation +749 ft. The re -design will raise the bottom of the footing elevation for the majority of the remainder of the wall to Elevation +753 ft in an effort to reduce the excavation support requirements. In order to raise the bottom of the footing elevation, construction surcharge loading adjacent to the wall will be limited to 100 pounds per square foot (psf). Revised drawings will be made available to bidders on Tuesday, August 8, 2023 in Addendum No. 2. Listed below are Bidding Questions (Q) received and the Bidding Answers (A) provided to contractors: (Q) Will the project require site security? With the drop offs involved will simple safety fencing be enough or are we going to need an actual construction fence? (A) As discussed in Section SP-13, site security and site safety are the responsibility of the Contractor. The Contractor shall submit a safety and security plan to the City prior to the start of construction. It is the Contractor's responsibility to determine measures which are appropriate for the activities which will be performed. (Q) If the Contractor plans to encroach on the CN Railroad Right of Way, are any delays in securing access cause for a time extension or is securing the necessary permissions from the railroad entirely at the Contractor's risk? I:\Engineering\2021-2030 Contracts\2023 CONTRACrS\23-17 E Parkway Det Page 1 of 4 Basin\Project Information\Contract Info\Addendum \Addendum #1\23-17 Addendum 13-4-23.docx City Hall, 215 Church Avenue P.O. Box 1130 Oshkosh, WI 54903-1130 http://www.cl,oshkosh.\Wi.us (A) Time is of the essence for the completion of the Project, due to planned construction on Grand Street in 2024. However, consideration will be given to extending the substantial completion date beyond November 24, 2023 if delays in the Project are solely a result of responsiveness of CN in securing a construction easement or right of entry. In order to consider this, the City will need to see that progress has been made and the Contractor shall prove that every attempt possible has been made in coordinating and communicating with CN. (Q) There appear to be three 12" by 12" Nyloplast inlets along the backside of the west wall. They appear to daylight through the wall with a check valve. Do these also connect into the 6" hard stick pvc underdrain behind the wall? Since there is not item for these, I would assume that all of these along with the 6" drain tile is incidental to the wall? _ (A) The profiles and details on Sheet C-7 are intended to show that the 6" perforated PVC line behind the west retaining wall will be connected into the Nyloplast square inlets before discharging through the check valves and into the basin. As indicated in Section SP-22, furnishing and installing drain tile, drain basins, and backflow preventers is considered incidental to the wall construction. (Q) The formliner limits extend 1' minimum below grade. Alternate 1 is for concrete staining of the formliner. A 28 day concrete cure time is typically required prior to placement of concrete stain per manufacturer recommendations. Provided the formliner limits, the last 1' of fill will not be able to be placed until after the formliner is applied 28 days after the last concrete pour. Assuming 2 weeks to complete concrete staining, placement of the last 1' of fill, and restoration; the last concrete pour must be on October 101" to achieve +the November 24th completion date should Alternate 1 be selected. Temperature conditions in November may require the wall to be heated and housed to meet concrete stain manufacturer application temperature requirements as well. Would the owner consider keeping November 24th as an interim completion date and revise the contract completion date to spring/summer 2024 to complete the concrete staining if Alternate 1 is selected? (A) The formliner limits should extend one foot (1') below grade as shown �on the Drawings; however, the concrete staining would be limited to the form liner which is extending above finished grade. Concrete staining, if selected, could be deferred to spring of 424 as part of final completion. Substantial completion will be determined once the basin has been constructed, concrete has been poured, final grading has been established, and final restoration is completed. Final completion will include concrete staining, if selected. I:\Engineering\2021- 2030 Contracts\2023 CONTRACTS\23.17 E Parkway Det Page 2 of 4 Basin\ Project_Informadon\Contract Info\Addendum\Addendum M1 \23-17 Addendum 1_8-4-23.docc (Q) Can elements of an earth retention system extend off City property and be left in place after completion of the project? (A) Elements of the temporary shoring system need to remain on City property and no elements can remain in place after construction is complete. (Q) Can you provide photos of the color scheme at the Baldwin Basin? (A) See pictures below: 1:\Bngineering\2021-2030 Contracts\2023 CONTRACI5\23-17 G Parkway Det Page 3 of 4 Basin\ Project_Information\Contract Info\Addendum\Addendum 81\23-17 Addendum 1 8A-23.docx If you have any questions regarding this Addendum, please contact me at (920) 236-5065 between the hours of 8:00 a.m. and 4:00 p.m. weekdays or Jeremy Thomas of AECOM at (847) 702-6639 or by email at ieremy.thomas@aecom.com. Sincerely, VQZ Alyssa Deckert, P.E. Civil Engineering Supervisor AD/tit 1: \Engineering \2021 - 2030 Contracts\2023 CONTRACTS\23-17 E Parkway Det Page 4 of 4 Basin\ Project_Information\Contract Info\Addendum \Addendum M23-17 Addendum 13A-23.docx