HomeMy WebLinkAbout03-512DECEMBER 23, 2003 03-512 RESOLUTION
(CARRIED 7-0 LOST LAID OVER WITHDRAWN )
PURPOSE:
INITIATED BY:
CHANGE ORDER NO. 4, PUBLIC WORKS CONTRACT 02-03A
DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
DORNER-STAHL, INC.
PO Box 129
Luxemburg, WI 54217-0129
Net Decrease to contract:
($57,088.43)
PURPOSE: See attached Change Order.
TO:
Domer-Stahl, Inc.
P. O. Box 129
Luxemburg, WI 54217-0129
CHANGE ORDER# 4
DATED: December 1, 2003
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
02-03A , is hereby amended
NET DECREASE TO SECTION I - CONCRETE PAVING:
($57,088.43)
Recommended:
_.%,,'J c.
Director of Public Works
CITY OF OSHKOSH
BY:
City Manager
City Clerk
Fo'ntr3ctor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Approved as to form:
Comptroller
City Attorney
CONTRACT: 02-03A CHANGE ORDER#4
SECTION ! - CONCRETE PAVING
ITEM DESCRIPTION
NUMBER
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET NET
INCREASE DECREASE
COSTPER
UNIT
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
lA. Approx. 4,700 square
Fards of pavement
removal, complete as
specified, per square yard 4,700.00 4,960.60 260.60 $3.00 $781.80
2A. Approx. 47,550 square feet
3f sidewalk and driveway
removal, complete as
~pecified, per square foot
47,550.00 50,361.55 2,811.55 $0.40 $1,124.62
3A. Approx. 20,880 cubic yards
3f excavation, complete as
specified, per cubic yard
20,880.00 19,507.10 -1,372.90 $5.00 ($6,864.50
4A. Approx. 34,315 square
iyards of 7" non-reinforced
iconcrete pavement,
!including integral curb, 5"
~ase material & grading,
:omplete as specified, per
~squareyard 34,315.00 34,422.90 107.90 $20.00 $2,158.00
5A. Approx: 1,510 linear feet of
i12" radius curb & head,
Icomplete as specified, per
ilinear foot 1,510.00 1,470.30 -39.70 $5.00 ($198.50)
6A. !Approx. 1,630 linear feet of
standard 30" curb & gutter,
complete as specified, per
linear foot 1,630.00 1,584.60 -45.40 $8.00 ($363.20)
7A. Approx. 10 linear feet of 6"
x 18" curb, complete as
specified, per linear foot
10.00 11.40 1.40 $15.00 $21.00
SA. Approx. 32,075 square feet
of 4" concrete sidewalk,
complete as specified, per
square foot 32,075.00 33,546.00 1,471.00 $2.35 $3,456.85
9A. Approx. 32,075 square feet
of 6" concrete sidewalk &
driveway, complete as
specified, per square foot
32,075.00 30,241.60 -1,833.40 $2.80 ($5,133.52
10A. Approx. 575 square yards
of 3" thick asphaltic
concrete driveway,
complete as specified, per
square yard 575.00 546.00 -29.00 $23.80 ($690.20
Page 1
CONTRACT: 02-03A CHANGE ORDER # 4
INCREASE IN DECREASE IN
ITEM DESCRIPTION CONTRACT INSTALLED NET NET COST PER CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
11A. Approx. 1,210 square
yards of 3" asphaltic
concrete transition,
complete as specified, per
squareyard 1,210.00 1,201.40 -8.60 $18.75 ($161.25)
12A. Approx. 475 square yards
of 5" asphaltic concrete
transition, complete as
specified, per square yard 475.00 480.30 5.30 $24.25 $128.53
13A. Furnish and install approx.
14,500 tons of crushed
stone base course,
complete as specified, per
ton 14,500.00 8,330.30 -6,169.70 $8.25 ($50,900.03
14A. Approx. 3,280 linear feet of
sawing, complete as
specified, per linear foot 3,280.00 3,245.50 -34.50 $2.05 ($70.73)
15A. Furnish and install approx.
610 pavement ties,
complete as specified,
each 610.00 511.00 -99.00 $6.00 ($594.00)
16A. Adjust approx. 190
manholes and inlets,
complete as specified,
each 190.00 185.00 -5.00 $230.00 ($1,150.00
17A. Furnish and install approx.
10 trees, complete as
specified, each
10.00 10.00 $400.00
18A. Remove approx. 35 I.D. of
stumps, complete as
specified, per inch
diameter 35.00 52.00 17.00 $20.00 $340.00
19A. Remove approx. 175 I.D.
of trees and stumps,
complete as specified, per
inch diameter 175.00 239.30 64.30 $19.00 $1,221.70
20A. Furnish and installapprox.
660 linear feet of No. 4
reinforcing bars, complete
as specified, per linear foot
660.00 360.00 -300.00 $0.65 ($195.00)
21A. Terrace work on Bay
Street, complete as
specified, lump sum 1.00 1.00 $4,560.00
22A. Terrace work on Cleveland
Avenue, complete as
specified, lump sum 1.00 1.00 $3,868.00
23A. Terrace work on Dove
Street, complete as
specified, lump sum 1.00 1.00 $9,085.00
Page 2
CONTRACT: 02-03A CHANGE ORDER#4
INCREASE IN DECREASE IN
ITEM CONTRACT INSTALLED NET NET COST PER
DESCRIPTION CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
24A. Terrace work on Huron
Avenue, complete as
specified, lump sum 1.00 1.00 $7,204.00
25A. Terrace work on Josslyn
Street, complete as
specified, lump sum 1.00 1.00 $17,605.00
26A. Terrace work on Oak
Street, complete as
specified, lump sum 1.00 1.00 $2,758.00
27A. Terrace work on
Tennessee Avenue,
complete as specified,
lump sum 1.001 1.00 $6,954.00
SECTION I - (BID ITEMS lA - 27A) - SUB-TOTALS
$9,232.50 ($66,320.93)
ADDITONAL WORK REQUIRED: C.C. # '1 - SECTION I - CONCRETE PAVING
ITEM DESCRIP~ON CONTRACT
NUMBER QUAN~ES
INSTALLED NET
QUAN~ES INCREASE
NET
DECREASE
COSTPER
UNIT
INCREASEINIDECREASEIN
CONTRACT CONTRACT
PR CE PR CE
1. Additional concrete paving
replacement on Taft
Avenue, from Josslyn St. to
Bauman St.
I-A. Pavement removal, per sq.
yard 986.80 986.80 $3.00
I-B. New7" non-reinforced
concrete pavement
including integral curb and
grading (base in place),
per sq. yard 986.80 988.80 $20.00
1-C.
Concrete sawing,per lin. ft. 177.60 177.60 $2.05
1-D. Pavement ties 60.00 60.00 $6.00
ADDITIONAL WORK: C.C. # 1 - (ITEMS lA -1D) - SUB-TOTAL $0.00
NET DECREASE TO SECTION I - ($57,088.43
$0.00
NET DECREASE TO CONTRACT:
($57,088.43