CHANGE ORDER NO. 1, PUBLIC WORKS CONTRACT 02-03B
DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
DORNER-STAHL, INC.
PO Box 129
Luxemburg, WI 54217-0129
Net Decrease to contract:
($17,210.65)
PURPOSE: See attached Change Order.
TO:
Dorner-Stahl, Inc.
P. O. Box 129
Luxemburg, WI 54217
CHANGE ORDER # 1
DATED: December 1, 2003
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
02-03B , is hereby amended
NET DECREASE TO SECTION I - CONCRETE PAVING:
($17,210.65)
Recommended:
Director of Public WOCKS
BY:
CITY OF OSHKOSH
City Manager
City Clerk
~___..~Approv/~and acc~
/ C/n~ra~tor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Approved as to form:
Comptroller
City Attorney
CONTRACT: 02-03B CHANGE ORDER # 1
SECTION I - CONCRETE PAVING
ITEM
NUMBER
DESCRIPTION CONTRACT NET NET COST PER
QUANTITIES INCREASE DECREASE UNIT
~CREASE ~
CONTRACT
PRICE
DECREASEIN
CONTRACT
PRICE
1B. Approx. 1,260 square
/ards of pavement
removal, complete as
specified, per square yard 1,260.00 984.80 -275.20 $5.00 ($1,376.00
2B. Approx. 10,225 square feet
of sidewalk and driveway
removal, complete as
specified, per square foot
10,225.00 10,310.00 85.00 $0.45 $38.25
3B. Approx. 4,800 cubic yards
of excavation, complete as
specified, per cubic yard
4,800.00 4,274.40 -525.60 $5.00 ($2,628.00
4B. Approx. 8,180 square
Cards of 7" non-reinforced
concrete pavement,
including integral curb, 5"
base material & grading,
complete as specified, per
square yard 8,180.00 8,159.20 -20.80 $20.00 ($416.00)
5B. Approx. 445 linear feet of
12" radius curb & head,
complete as specified, per
linear foot 445.00 442.40 -2.60 $10.00 ($26.00)
6B. Approx. 235 linear feet of
standard 30" curb & gutter,
complete as specified, per
linear foot 235.00 247.10 12.10 $20.00 $242.00
7B. No Bid Item
aB. Approx. 2,785 square feet
of 4" concrete sidewalk,
complete as specified, per
square foot 2,785.00 3,064.60 279.60 $2.40 $671.05
aB. Approx. 9,680 square feet
of 6" concrete sidewalk &
driveway, complete as
specified, per square foot 9,680.00 10,154.80 474.80 $2.80 $1,329.44
10B. No Bid Item
11B. Approx. 635 square yards
of 3" asphaltic concrete
Lransition, complete as
specified, per square yard 635.00 649.70 14.70 $19.00 $279.30
12B. Approx. 875 square yards
of 5" asphaltic concrete
[ransition, complete as
specified, per square yard 875.00 976.90 101.90 $20.00 $2,038.00
Page 1
CONTRACT: 02-03B CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST P£R INCREASE IN DECREASE IN
NUMBER DESCRIPTION CONTRACT CONTRACT
QUANTITIES QUANTITIES: INCREASE DECREASE UNIT
PRICE PRICE
13B. Furnish and installapprox.
1,925 tons of crushed
stone base course,
complete as specified, per
ton 1,925.00 0.00 -1,925.00 $8.50 ($16,362.50
14B. Approx. 640 linear feet of
sawing, complete as
specified, per linear foot 640.00 304.30 -335.70 $2.05 ($688.19
15B. No Bid Item
16B. Adjust approx. 53
manholes and inlets,
complete as specified,
each 53.00 53.00 $230.00
17B. Furnish and install approx.
4 trees, complete as
specified, each 4.00 3.00 -1.00 $400.00 ($400.00)
18B.. No Bid Item
19B. Remove approx. 36 I.D. of
trees and stumps,
complete as specified, per
inch diameter 36.0( 40.00 4.00 $22.00 $88.00
20B. No Bid Item
21B. Terrace work on Powers
Street, complete as
specified, lump sum 1.00 1.00 $13,000.00
SECTION I - (BID ITEMS lB - 21B) - SUB-TOTALS
$4,686.04 ($21,896.69)
NET DECREASE TO CONTRACT:
($17,210.65)